Professional Documents
Culture Documents
Ruralstar Site Tower Construction SOP V3.0
Ruralstar Site Tower Construction SOP V3.0
Ruralstar Site Tower Construction SOP V3.0
SOP
2024
Security Level:
1. Responsibility Matrix
2. Solution Overview
5. Checklist
2 Huawei Confidential
CW Responsibility Matrix for ET Rural Star sites
Responsible by
Item Item Description
Huawei ET
3 Huawei Confidential
1. Responsibility Matrix
2. Solution Overview
5. Checklist
4 Huawei Confidential
Rural Star Solution(G4U1)_With MW, Typical Power Consumption 463W(87 Sites)
Type Frequency Gain Size/ Weight Qty
Antenna Omni antenna 694~960MHz 11 dBi φ58 mm*3360mm/6.9kg 2
A7WS09MAC-3NX,7W,600mm,UHP-M,Single Polarization,
0.6m MW Antenna Direct(XMC)/Separate(All RTN ODU) 1
Mount,35.3dBi,3deg,30dB,With English doc,C3
5 Huawei Confidential
Rural Star Solution(G4U1) Satellite Solution 451W (13 Sites)
TX Satellite Transmission
6 Huawei Confidential
Tower Solution:35m with guyed wires
For the details, please refer to the tower assembly drawing.
7 Huawei Confidential
Rurarstar Site Implementation Schedule
Take 35m tower 12 PV site for example:
Efficiency Baseline Preparation(9 days) Mos-On Air(8 days) On Air -PAC(7 days)
Mandatory/
S/N Delivery Milestione Owner Duration
Optional 1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7
Baseline(day)
1 Site Planning ET Mandatory 3.0
2 Planning Approval ET Mandatory 2.0
3 Site Acquisition ET Mandatory 30.0
4 Site Survey ET Mandatory 2.0 2
5 Soil Test ET Mandatory 5.0 5
6 Site Design HW Mandatory 2.0 2
7 Cleaning and Leveling ET Optional 0.5 1
8 Site Excavation ET Mandatory 2.0 2
9 Foundation Installation ET Mandatory 1.0 1
10 Tower Erection HW Mandatory 2.5 3
11 Cabinet Foundation Casting ET Optional 0.5 1
12 Fence Installation ET Optional 0.5 1
13 Earthing Installation ET Mandatory 1.0 1
14 Site finishing & crushed stone spreading ET Mandatory 0.5 1
15 TE I&C HW Mandatory 3.0 3
16 SSV HW Mandatory 1.0 1
17 Acceptance HW Mandatory 0.5 6
8 Huawei Confidential
1. Responsibility Matrix
2. Solution Overview
5. Checklist
9 Huawei Confidential
Part 1 Civil Work SOP
10 Huawei Confidential
Civil Work:Kick off, Startup Meeting
Sample Picture Working Procedure
Steps
2 Confirm with site owner the site area match the site acquisition contract area;
Find four corners of site and mark them with rebar sprayed red. Find a point to be a
4
benchmark;
Critical Techniques
11 Huawei Confidential
Civil Work:Site Cleaning & Leveling
Sample Picture Working Procedure
Steps
1 Remove the obstacles, clean grass and cut off trees if necessary;
2 Clear out all crop and tree roots, remove all organic soil on the surface of ground;
Critical Techniques
12 Huawei Confidential
Civil Work:Site Setting Out and Measurement
Sample Picture Working Procedure
Steps
1 Put string line and use warning tape to enclose the boundaries (29m×27m);
Critical Techniques
Confirm 3 guyed position at 0°, 120° and 240° refer to true North (0°).
1
13 Huawei Confidential
Civil Work:Tower and Guyed Foundation Excavation
Sample Picture Working Procedure
Steps
Critical Techniques
1 Inform HW SE immediately if soil bearing capacity is different from the soil test report;
14 Huawei Confidential
Civil Work:Central Steel Frame Installation,
Sample Picture Working Procedure
Steps
1 Concrete foundation under tower base firstly (Optional, based on project design);
Critical Techniques
1 Locate the foundation precisely; distance from the center to the anchor check on DD.
2 Check and confirm the foundation base is leveled with water label;
3 The center steel base distance from the 3 anchor base should follow the design standard.
15 Huawei Confidential
Civil Work:Guyed Steel Foundation Installation,
Sample Picture Working Procedure
Steps
Critical Techniques
The guyed steel base distance from the center base should follow the design standard;
1
2 From each anchor bolt 3 guyed wire will projected to the Tower (30m and 35m Tower) .
16 Huawei Confidential
Civil Work:Backfilling
Sample Picture Working Procedure
Steps
1 Clean and drain the pits, lay soil, leveling and compacting with machine.
Critical Techniques
2 Remark 20cm to the tower base using color, then as proof to the backfilling QC task;
If the team not use frog compactor pls check the compaction instruction for the specified
3
Compactor used.
17 Huawei Confidential
Tower Erection
Sample Picture Working Procedure
Steps
Install the 1st section on the base, check the geometrical dimension of the 1st section,
1
tighten the bolts and nuts;
Install the 2nd section and fixed it with bolts, then follow the same procedure to lift the other
2
section until all the section is installed.
5 Remark;- Sample pictures taken from other project with non 35m tower.
Critical Techniques
1 When installing the 2nd section, make sure the PV panels direction north to south.
18 Huawei Confidential
Tower Erection/ Solar Adapter
Sample Picture Working Procedure
Steps
Check whether the solar panel is installed towards the equator. If not, remove the tower and
1
reinstall it.
North
2 The solar panels need to face to equator.
North
3 The solar panels and the horizontal ground are at an angle of 15 degrees.
15
South
4
5 Remark;- Sample pictures taken from other project with non 35m tower.
Adapter
Critical Techniques
South
1 The solar adapter direction checking on the 1st section installation is mandatory
2 Solar PV Panel direction should be from north to south direction( towards the equator)
19 Huawei Confidential
Guyed Wires Fixation
Sample Picture Working Procedure
Steps
After installed the 1st 4 sections of tower, install and fix the bottom guyed wires and after
1 installing the 1st 8 sections install the middle guyed wires and after complete all section
install the last guyed wires.
Team should tighten the guyed wire straight and verify all the nuts are tightened after
2
finishing tower erection.
Critical Techniques
20 Huawei Confidential
Guyed Wires Fixation.. Conti..
Sample Picture Working Procedure
Steps
1 Tight the wire with man power and fix it on top section 1.
3 All the wires should be tight enough to support the tower and also Tower verticality attained.
4
S2
5
Critical Techniques
S3
1 Guyed wired have to keep tight and straight.
When the edge clamps reach section 3 need to correct again because it will be difficult to
2
tight when on future correction needed .
21 Huawei Confidential
Guyed Wires Fixation.. Conti..
Sample Picture Working Procedure
Steps
1 Fix the guyed wire after bent @ two section as picture showen.
Critical Techniques
22 Huawei Confidential
Installation of Omni Antenna Bracket
Sample Picture Working Procedure
Steps
Route the U-bolt through the hole of the support and tighten the nut.
1
Place an antenna against the pole
Route the U-shaped clamp through the U-bolt and tighten the nut.
2
Secure the fixing clip for the antenna support against the pole.
Use two U-bolts around the pole and route them through the holes on the support, and
3
tighten the nuts.
Critical Techniques
23 Huawei Confidential
Installation of Yagi Antenna Bracket and MW/RRU Bracket
Sample Picture Working Procedure
Steps
2 Adjust the support direction to make Yagi antenna face to the planned DeNB.(Optional)
Critical Techniques
24 Huawei Confidential
Installation of Solar Panel Frame
Sample Picture Working Procedure
Steps
Critical Techniques
2 The lowest side of Solar power bracket must face to the true south
25 Huawei Confidential
Installation of Power Cabinet Bracket and BBU Bracket
Sample Picture Working Procedure
Steps
3 For the site with 2 battery cabinet install as the sample picture4.
Critical Techniques
Tighten the bolts with a proper torque based on the requirements specified in design
2
drawings.
4 4
26 Huawei Confidential
Site Earthing System
Sample Picture Working Procedure
Steps
Critical Techniques
27 Huawei Confidential
Installation of Site Earthing: 6m*6m system
Sample Picture Working Procedure
Steps
1 Setting out, excavation. Excavation size is 30cm wide, 70cm deep, 6m*6m.
2 Install the vertical earthing angle steel , install the horizon earthing flat iron.
Install steel earthing tap to join the fence , equipment base frame , and tower to the site
3
earthing system.
4 Backfilling.
5 Test.
Critical Techniques
28 Huawei Confidential
Fence installation
Sample Picture Working Procedure
Steps
3 Prepare formwork for grade beam and put the concreat mix inside.
4 Site cleaning.
Critical Techniques
Fence work stared after the site telecom part installation done to provide the space free for
1
installation team.
Excavation should follow the land scape elevation.
2
3 Mesh wire length 10m so make sure to tighten properly to cover all sides.
Distance from the center pole to fence and also Location for equipment foundation follow
4
CWDD.
29 Huawei Confidential
Installation of Site Earthing: Pit Design (Optional)
1. Grounding pit should near small foundation.
2. Supplier provide cover for the pit of 0.5m(length)*0.5m(width)*0.4m(height).
30 Huawei Confidential
Installation of Anti-climbing
Sample Picture Working Procedure
Steps
1 Anti-climbing installation
Anti-Climb Blade installation height should be 2m minimum at the tower fixation point, that
2
means higher than 6 steps of the tower ladder
Critical Techniques
31 Huawei Confidential
Installation of Foundation(Optional)
Sample Picture Working Procedure
Steps
Install drain pipe: Each foundation have 4 sides. Just 2 sides need a rigid PVC, diameter is
5
between 30mm--50mm.
Critical Techniques
32 Huawei Confidential
Site Finishing
Sample Picture Working Procedure
Steps
2 Install anti-vegetable sheet on the ground. Add a layer of gravel (Hight: 5cm) inside fence.
4 Site cleaning.
Critical Techniques
33 Huawei Confidential
Special Cases: Special Tower Foundation Conditions-Soft Foundation
Critical Techniques
34 Huawei Confidential
Special Cases: Special Tower Foundation Conditions-Underground Water
2 Special concrete foundation protection design required to reinforce the tower foundation.
Critical Techniques
35 Huawei Confidential
Special Cases: Rainy time excavation and backfilling
1 Use rain protection plastic sheet cover for the rainy season.
2 If water enters the pit, use a pump or manual way to remove the water from the pit.
3 Wait for the pit till it get dry for next action.
1 Allow the soil to dry before backfilling to achieve the required density.
Use lime to dry wet soil on sites and elsewhere to reduce downtime and create a better
2
working surface.
36 Huawei Confidential
1. Responsibility Matrix
2. Solution Overview
5. Checklist
37 Huawei Confidential
1. Responsibility Matrix
2. Solution Overview
5. Checklist
38 Huawei Confidential
Tool Preparation 1
Main Tools Standard Photo Remark
Safety Helmet Safety Shoes Gumboots Reflective Vests
Safety
Safety Gloves WAH Helmet Double Lanyard
Harness
Work Positioning Lanyard First Aid Kit Fire Extinguisher 3kg Caution Tapes
39 Huawei Confidential
Tool Preparation 2
Main Tools Standard Photo Remark
First aid kit and 3k The level of gas must be on the green
Minimum 3kg
GM fire powder fire and it should not be outdated .
Standard
extinguisher
40 Huawei Confidential
Tool Preparation 3
Main Tools Standard Photo Remark
Multimètre Standard
41 Huawei Confidential
Tool Preparation 4
Main Tools Standard Photo Remark
There should be
Jumper compactor
>4HP/KW and Operating enough amount of
machine
fuel gas on site.
42 Huawei Confidential
Tool Preparation 5
Main Tools Standard Photo Remark
43 Huawei Confidential
Tool Preparation 6
Main Tools Quantity and standard Photo Remark
44 Huawei Confidential
Tool Preparation 7
Main Tools Quantity and standard Photo Remark
- Band tape
- Level gauge
- Cord
- Compass
Other Tools Every team should be
- Torque wrench
fully equipped
- Setting out reference
pegs
- Plumb bob
45 Huawei Confidential
1. Responsibility Matrix
2. Solution Overview
5. Checklist
46 Huawei Confidential
Checklist
Domain Item Request Severity Remark
EHS PPE All team members have to wear PPE of good quality. High
Compactor Provide compactor for backfilling. High
Pole, rope and pulley Provide the ginpole that more than 6m. High
Ladder or Scaffolding Improve PV installation efficiency. Middle
Tool Theodolite To check tower verticality after tower erection done Middle
Earth tester To check site earth resistance High
Jackhammer Provide if meet rocky soil. Middle
Water pump Provide if meet the water inside. Middle
Concrete under tower base Apply for 10cm concrete under tower base. High Optional
Compact soil every 20cm when backfilling. And record to ISDP QC. Also
Civil Work Compact soil every 20cm High
add some water.
Earthing resistance Earthing resistance must less than 10ohm. High
PV direction Make sure the PV panels must be toward due south. Middle
Anti-Climb height Anti-Climb installation height should be 2m minimum . Middle
Tower
Erection Tower verticality check Check the tower verticality by theodolite tool High Optional
The window should be closed by fireproofing mud to avoid entering
Small window under tower High
water.
The upper one should be vertical to the ground. The lower one should Optional
Yagi antenna direction High
be parallel to the ground.
TE
Yagi antenna distance The distance between the two Yagi antennas should be 1.2m. High Optional
RRN/BTS3920R1/BTS3920R Record RRN ID and share to Huawei engineer before installation. High
47 Huawei Confidential
Thank you. 把数字世界带入每个人、每个家庭、
每个组织,构建万物互联的智能世界。
Bring digital to every person, home, and
organization for a fully connected,
intelligent world.