Ruralstar Site Tower Construction SOP V3.0

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 48

RuralStar Site CW and Tower Implementation

SOP

2024

Security Level:
1. Responsibility Matrix

2. Solution Overview

3. Part 1 Civil Work SOP

4. Tool Preparation of Supplier

5. Checklist

2 Huawei Confidential
CW Responsibility Matrix for ET Rural Star sites

Responsible by
Item Item Description
Huawei ET

1 Foundation Clearing and leveling, excavation and backfilling R


2 Inland Transportation R
3 Tower Foundation steel base assembly R
4 Installation of site earthing system (less than 10 Ohm) R
5 Site finishing and crushed stone spreading(0.1m) R
6 Tower Erection with all accessories R
7 Supply and install concrete Grade beam for fence 2m*3m and Fence Installation R
8 Equipment Foundation and VSAT Foundation R
9 TE Equipment Installation R
10 Civil Work supervision R S

“R” that means: ‘Responsibility’;

“S” that means: ‘Support’;

“I” that means: ‘Information’;

“A” that means: ‘Approve’;

3 Huawei Confidential
1. Responsibility Matrix

2. Solution Overview

3. Part 1 Civil Work SOP

4. Tool Preparation of Supplier

5. Checklist

4 Huawei Confidential
Rural Star Solution(G4U1)_With MW, Typical Power Consumption 463W(87 Sites)
Type Frequency Gain Size/ Weight Qty
Antenna Omni antenna 694~960MHz 11 dBi φ58 mm*3360mm/6.9kg 2
A7WS09MAC-3NX,7W,600mm,UHP-M,Single Polarization,
0.6m MW Antenna Direct(XMC)/Separate(All RTN ODU) 1
Mount,35.3dBi,3deg,30dB,With English doc,C3

Band Config RRU Power Qty


RF 900Mhz 2T2R RRU5909 2*60W 1
Omni Antenna*2

MW Frequency Size/ Weight Qty


MW RTN320F 6GHz~42GHz 220mm×300mm×60mm 1
Height: 35m 20W per GSM TRx XMC-3 7G 195mm×43.5mm×195mm/2.8kg 1
40W per UMTS Cells

RRU5909*1 BBU Item BBU Board Qty Description Qty

BBU box BBU5900A 1 Low power consumption BBU 1

Item Description Qty Size/ Weight/(per item)


2279mm × 1134mm × 35mm/
Solar PV 540Wp 8
29.1kg
ICC30-N1 Power System 1 380*480*750mm/ 50kg

Power ESC30-N1 Battery Cabinet 2 380*480*750mm / 50kg

Solar Panel ESM-48100B1 Lithium Battery, 100AH 5 442*396*130mm / 43kg


BBU5900A ICC30-N1 ESC30-N1
(PV540Wp) Remark:
1. Typical Power Consumption:463W, Actual backup time: 48h
2. monthly average peak hours of sunlight in case of worst sunlight: 3.8h/day

5 Huawei Confidential
Rural Star Solution(G4U1) Satellite Solution 451W (13 Sites)

Type Frequency Gain Size/ Weight Qty


Antenna Omni 3360mm x
694-960 11 dBi 2
antenna Φ58mm/6.9kg

Band Config RRU Power Qty


RF
Omni Antenna 900Mhz 2T2R RRU5909 2*60W 1

TX Satellite Transmission

Item BBU Board CFG


BBU
RRU5909 BBU5900A 1*UMTPT + 1*UBBPg1 G4+U1 (900Mhz)

Item Description Qty Size/ Weight/(per item)


2279mm × 1134mm × 35mm/
Solar PV 540Wp 8
29.1kg
650 mm × 650 mm × 1600
ICC330-D1 Power System 1
mm/129Kg
Power ESM-48100B1 Lithium Battery, 100AH 5 442*396*130mm / 43kg
43.6mm×442mm×330mm
ETP23006-C1A1 Inverter 1
40.8 mm x 105 mm x 269mm
BBU5900A I23003G1 Inverter Module 1
Solar Panel
(PV540Wp) ICC330 Remark:
1. Typical Power Consumption:451W, Actual backup time: 48h
2. monthly average peak hours of sunlight in case of worst sunlight: 3.8h/day

6 Huawei Confidential
Tower Solution:35m with guyed wires
For the details, please refer to the tower assembly drawing.

7 Huawei Confidential
Rurarstar Site Implementation Schedule
Take 35m tower 12 PV site for example:

35m 12PV Ruralstar Site Delivery Schedule and Efficiency

Efficiency Baseline Preparation(9 days) Mos-On Air(8 days) On Air -PAC(7 days)
Mandatory/
S/N Delivery Milestione Owner Duration
Optional 1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7
Baseline(day)
1 Site Planning ET Mandatory 3.0
2 Planning Approval ET Mandatory 2.0
3 Site Acquisition ET Mandatory 30.0
4 Site Survey ET Mandatory 2.0 2
5 Soil Test ET Mandatory 5.0 5
6 Site Design HW Mandatory 2.0 2
7 Cleaning and Leveling ET Optional 0.5 1
8 Site Excavation ET Mandatory 2.0 2
9 Foundation Installation ET Mandatory 1.0 1
10 Tower Erection HW Mandatory 2.5 3
11 Cabinet Foundation Casting ET Optional 0.5 1
12 Fence Installation ET Optional 0.5 1
13 Earthing Installation ET Mandatory 1.0 1
14 Site finishing & crushed stone spreading ET Mandatory 0.5 1
15 TE I&C HW Mandatory 3.0 3
16 SSV HW Mandatory 1.0 1
17 Acceptance HW Mandatory 0.5 6

8 Huawei Confidential
1. Responsibility Matrix

2. Solution Overview

3. Part 1 Civil Work SOP

4. Tool Preparation of Supplier

5. Checklist

9 Huawei Confidential
Part 1 Civil Work SOP

10 Huawei Confidential
Civil Work:Kick off, Startup Meeting
Sample Picture Working Procedure
Steps

1 Confirm GPS location and match site coordinates;

2 Confirm with site owner the site area match the site acquisition contract area;

3 EHS check, no violation;

Find four corners of site and mark them with rebar sprayed red. Find a point to be a
4
benchmark;

Critical Techniques

1 PPE is required absolutely whiles at site to work;

2 Confirm with site owner before start any work;

3 Find out the site Northing Direction;

4 True Northing should be perpendicular to 29m.

11 Huawei Confidential
Civil Work:Site Cleaning & Leveling
Sample Picture Working Procedure
Steps

1 Remove the obstacles, clean grass and cut off trees if necessary;

2 Clear out all crop and tree roots, remove all organic soil on the surface of ground;

3 Level the ground to get a horizontal working area;

4 Consider the working area while clearing the compound

Critical Techniques

Removal of any extrude object in the site;


1

2 Surround the compound with caution tape;

12 Huawei Confidential
Civil Work:Site Setting Out and Measurement
Sample Picture Working Procedure
Steps

1 Put string line and use warning tape to enclose the boundaries (29m×27m);

2 Locate true North with compass;

3 Mark a site compound with caution tape;

4 Mark the excavation pads with red limen.

Critical Techniques

Confirm 3 guyed position at 0°, 120° and 240° refer to true North (0°).
1

13 Huawei Confidential
Civil Work:Tower and Guyed Foundation Excavation
Sample Picture Working Procedure
Steps

1 Tower foundation: as project tower design;

2 Guyed foundation of 3 guyed: as project tower design;

3 Clean the underground water if necessary;

4 Rain cover plastic sheet should be prepared in advance in case of raining.

Critical Techniques

1 Inform HW SE immediately if soil bearing capacity is different from the soil test report;

2 Machine for excavation is required absolutely if have rocky or hard soil;

3 Prepare rain cover plastic sheet.

4 Center Excavation should be 1000mm and Anchor Excavation 2350mm Depth.

14 Huawei Confidential
Civil Work:Central Steel Frame Installation,
Sample Picture Working Procedure
Steps

1 Concrete foundation under tower base firstly (Optional, based on project design);

2 Foundation must be installed horizontally.

Critical Techniques

1 Locate the foundation precisely; distance from the center to the anchor check on DD.

2 Check and confirm the foundation base is leveled with water label;

3 The center steel base distance from the 3 anchor base should follow the design standard.

15 Huawei Confidential
Civil Work:Guyed Steel Foundation Installation,
Sample Picture Working Procedure
Steps

1 Installation of guyed base according to the tower design;

2 Installation of guyed wires according to the tower design.

Critical Techniques

The guyed steel base distance from the center base should follow the design standard;
1

2 From each anchor bolt 3 guyed wire will projected to the Tower (30m and 35m Tower) .

3 Only Towers with 18m/24m/30m/35m have guyed.

4 Anchor Excavation depth should be 2350mm.

16 Huawei Confidential
Civil Work:Backfilling
Sample Picture Working Procedure
Steps

1 Clean and drain the pits, lay soil, leveling and compacting with machine.

2 Compact soil every 20cm when backfilling using compactor machine.

3 Add some water to keep moisture and ensure compacting efficiency

4 Repeat the above steps to reach the final level.

Critical Techniques

1 Ensure backfilling soil bearing capacity must be more than 16KN/m3;

2 Remark 20cm to the tower base using color, then as proof to the backfilling QC task;

If the team not use frog compactor pls check the compaction instruction for the specified
3
Compactor used.

17 Huawei Confidential
Tower Erection
Sample Picture Working Procedure
Steps

Install the 1st section on the base, check the geometrical dimension of the 1st section,
1
tighten the bolts and nuts;
Install the 2nd section and fixed it with bolts, then follow the same procedure to lift the other
2
section until all the section is installed.

5 Remark;- Sample pictures taken from other project with non 35m tower.

Critical Techniques

1 When installing the 2nd section, make sure the PV panels direction north to south.

2 Be careful not to damage the tower galvanization during the installation;

3 Tower verticality must be checked finally.

18 Huawei Confidential
Tower Erection/ Solar Adapter
Sample Picture Working Procedure
Steps

Check whether the solar panel is installed towards the equator. If not, remove the tower and
1
reinstall it.
North
2 The solar panels need to face to equator.
North
3 The solar panels and the horizontal ground are at an angle of 15 degrees.
15
South
4

5 Remark;- Sample pictures taken from other project with non 35m tower.
Adapter
Critical Techniques
South
1 The solar adapter direction checking on the 1st section installation is mandatory

2 Solar PV Panel direction should be from north to south direction( towards the equator)

19 Huawei Confidential
Guyed Wires Fixation
Sample Picture Working Procedure
Steps

After installed the 1st 4 sections of tower, install and fix the bottom guyed wires and after
1 installing the 1st 8 sections install the middle guyed wires and after complete all section
install the last guyed wires.
Team should tighten the guyed wire straight and verify all the nuts are tightened after
2
finishing tower erection.

Critical Techniques

1 Guyed wired have to keep tight and straight.

2 Guyed wire tension meter to do the if have available tool.

20 Huawei Confidential
Guyed Wires Fixation.. Conti..
Sample Picture Working Procedure
Steps

1 Tight the wire with man power and fix it on top section 1.

S1 2 By adjusting the tower verticality retighten the wire till Section 2

3 All the wires should be tight enough to support the tower and also Tower verticality attained.

4
S2
5

Critical Techniques
S3
1 Guyed wired have to keep tight and straight.

When the edge clamps reach section 3 need to correct again because it will be difficult to
2
tight when on future correction needed .

21 Huawei Confidential
Guyed Wires Fixation.. Conti..
Sample Picture Working Procedure
Steps

1 Fix the guyed wire after bent @ two section as picture showen.

2 This Ficsetion important to make the wire bent more strong.

3 bent wire length 50mm to 70cm

Critical Techniques

1 Check the two section fixation stay wire clamp.

22 Huawei Confidential
Installation of Omni Antenna Bracket
Sample Picture Working Procedure
Steps

Route the U-bolt through the hole of the support and tighten the nut.
1
Place an antenna against the pole
Route the U-shaped clamp through the U-bolt and tighten the nut.
2
Secure the fixing clip for the antenna support against the pole.
Use two U-bolts around the pole and route them through the holes on the support, and
3
tighten the nuts.

4 Repeat the preceding steps to install the second antenna support.

Critical Techniques

1 Check for all bolt fixed with the require standard.

23 Huawei Confidential
Installation of Yagi Antenna Bracket and MW/RRU Bracket
Sample Picture Working Procedure
Steps

1 Install Yagi antenna bracket.(Optional)

2 Adjust the support direction to make Yagi antenna face to the planned DeNB.(Optional)

3 Install the RRU support.

4 Install MW pole based on the design. (Optional)

Critical Techniques

1 Tighten the bolts.

2 Check the pole installed height based on the design height.

24 Huawei Confidential
Installation of Solar Panel Frame
Sample Picture Working Procedure
Steps

1 Install solar panel bracket according to the detailed tower design

2 Bolts should be fixed and tight properly with torque specified.

Critical Techniques

1 Comply design drawing.

2 The lowest side of Solar power bracket must face to the true south

3 Prepare ladder or scaffold in advance.

25 Huawei Confidential
Installation of Power Cabinet Bracket and BBU Bracket
Sample Picture Working Procedure
Steps

1 Install BBU bracket;

2 Install power cabinet bracket;

3 For the site with 2 battery cabinet install as the sample picture4.

Critical Techniques

1 Comply design drawing.

Tighten the bolts with a proper torque based on the requirements specified in design
2
drawings.

4 4

26 Huawei Confidential
Site Earthing System
Sample Picture Working Procedure
Steps

1 Following design for earthing.

2 Excavation size is 30cm wide, 70cm deep, 6m*6m

3 Totally need 4 angle steel for 6m*6m system.

4 The pit should near small concrete foundation under tower.

Critical Techniques

1 Earthing Resistance should less then 10 Ohm

27 Huawei Confidential
Installation of Site Earthing: 6m*6m system
Sample Picture Working Procedure
Steps

1 Setting out, excavation. Excavation size is 30cm wide, 70cm deep, 6m*6m.

2 Install the vertical earthing angle steel , install the horizon earthing flat iron.

Install steel earthing tap to join the fence , equipment base frame , and tower to the site
3
earthing system.

4 Backfilling.

5 Test.

Critical Techniques

1 The connection shall be reliable.

2 Backfilling shall be done layer by layer and compacted.

3 Earthing resistance must less than 10ohm

4 Totally need 4 angle steel for 6m*6m system.

28 Huawei Confidential
Fence installation
Sample Picture Working Procedure
Steps

1 Excavate grade beam trench based on the design provided.

2 Install the fence steel frame and mesh wire.

3 Prepare formwork for grade beam and put the concreat mix inside.

4 Site cleaning.

Critical Techniques

Fence work stared after the site telecom part installation done to provide the space free for
1
installation team.
Excavation should follow the land scape elevation.
2

3 Mesh wire length 10m so make sure to tighten properly to cover all sides.

Distance from the center pole to fence and also Location for equipment foundation follow
4
CWDD.

29 Huawei Confidential
Installation of Site Earthing: Pit Design (Optional)
1. Grounding pit should near small foundation.
2. Supplier provide cover for the pit of 0.5m(length)*0.5m(width)*0.4m(height).

30 Huawei Confidential
Installation of Anti-climbing
Sample Picture Working Procedure
Steps

1 Anti-climbing installation

Anti-Climb Blade installation height should be 2m minimum at the tower fixation point, that
2
means higher than 6 steps of the tower ladder

Critical Techniques

31 Huawei Confidential
Installation of Foundation(Optional)
Sample Picture Working Procedure
Steps

1 Excavate foundation to the design depth. Compact soil every 20 cm depth.

Supply and install brick wall: 1.5m(W) * 1.5m(L) * 0.3m(H).


2
0.1m under ground and 0.2m on the ground.

3 Supply and apply concrete for brick surface:0.042 cu.m

4 Concrete should be curing for 5 days.

Install drain pipe: Each foundation have 4 sides. Just 2 sides need a rigid PVC, diameter is
5
between 30mm--50mm.

Critical Techniques

32 Huawei Confidential
Site Finishing
Sample Picture Working Procedure
Steps

1 Leveling the site ground.

2 Install anti-vegetable sheet on the ground. Add a layer of gravel (Hight: 5cm) inside fence.

3 Removal the legacy materials

4 Site cleaning.

Critical Techniques

1 Comply design drawing.

2 Gravel height is 5cm.

33 Huawei Confidential
Special Cases: Special Tower Foundation Conditions-Soft Foundation

Sample Picture Working Procedure


Steps

1 Rural site with Soft Soil <100KPA

2 Special concrete foundation design required to reinforce the tower foundation.

3 Implement the concrete foundation as design.

4 Install tower foundation after concrete foundation done.

Critical Techniques

1 Comply design drawing.

34 Huawei Confidential
Special Cases: Special Tower Foundation Conditions-Underground Water

Sample Picture Working Procedure


Steps

1 Underground water site

2 Special concrete foundation protection design required to reinforce the tower foundation.

3 Implement the concrete foundation as design.

4 Install tower foundation after concrete foundation done.

Critical Techniques

1 Comply design drawing.

35 Huawei Confidential
Special Cases: Rainy time excavation and backfilling

Sample Picture Working Procedure


Rain Excavation Time

1 Use rain protection plastic sheet cover for the rainy season.

2 If water enters the pit, use a pump or manual way to remove the water from the pit.

3 Wait for the pit till it get dry for next action.

Rain Backfilling Time

1 Allow the soil to dry before backfilling to achieve the required density.

Use lime to dry wet soil on sites and elsewhere to reduce downtime and create a better
2
working surface.

36 Huawei Confidential
1. Responsibility Matrix

2. Solution Overview

3. Part 1 Civil Work SOP

4. Tool Preparation of Supplier

5. Checklist

37 Huawei Confidential
1. Responsibility Matrix

2. Solution Overview

3. Part 1 Civil Work SOP

4. Tool Preparation of Supplier

5. Checklist

38 Huawei Confidential
Tool Preparation 1
Main Tools Standard Photo Remark
Safety Helmet Safety Shoes Gumboots Reflective Vests

Safety
Safety Gloves WAH Helmet Double Lanyard
Harness

Basic PPE should


PPE Standard be provided to all
team members

Work Positioning Lanyard First Aid Kit Fire Extinguisher 3kg Caution Tapes

39 Huawei Confidential
Tool Preparation 2
Main Tools Standard Photo Remark

First aid kit and 3k The level of gas must be on the green
Minimum 3kg
GM fire powder fire and it should not be outdated .
Standard
extinguisher

Warning tape Standard Cover 35m*30m area.

All used pulley must be equipped by


automatic lock hooks or closed ring
Pole: more than 4m.
hosting, never use pulley with
Pole, rope and pulley Rope: Diameter
jumped out or missing safety latch of
12.5 mm-10.5 mm
hook. Never use modified or
deformed hooks.

40 Huawei Confidential
Tool Preparation 3
Main Tools Standard Photo Remark

Tool Box Standard

Multimètre Standard

Material that is free from


organic or other deleterious
Huawei Engineer has to
material, obtained from
Backfill material approve to the soil if SBC
excavation or imported, with a
TL has uncertainty.
particle size for rock not
greater than 20 mm.

41 Huawei Confidential
Tool Preparation 4
Main Tools Standard Photo Remark

There should be
Jumper compactor
>4HP/KW and Operating enough amount of
machine
fuel gas on site.

Excavation tools Excavation tools number


big hammer with depends on the site
chiseler and Jack condition. For Rocky sites
Hummer with >2.8HP/KW and Operating
generator normally

Maximum output capacity For the water if


Water pump
500L/min necessary.

42 Huawei Confidential
Tool Preparation 5
Main Tools Standard Photo Remark

Rain cover plastic For center 4m*4m


sheet For Anchors 3(2m*2m)

Ladder or Improve PV installation


Height should be > 3m
Scaffolding efficiency.

Machine for Earthing resistance must


Standard
earthing test less than 10ohm.

43 Huawei Confidential
Tool Preparation 6
Main Tools Quantity and standard Photo Remark

Strong enough to take


Ginpole
200kg tower member

Guyed Wire Tension


Standard Optional
Tester

Theodolite Main brand Optional

44 Huawei Confidential
Tool Preparation 7
Main Tools Quantity and standard Photo Remark

- Band tape
- Level gauge
- Cord
- Compass
Other Tools Every team should be
- Torque wrench
fully equipped
- Setting out reference
pegs
- Plumb bob

45 Huawei Confidential
1. Responsibility Matrix

2. Solution Overview

3. Part 1 Civil Work SOP

4. Tool Preparation of Supplier

5. Checklist

46 Huawei Confidential
Checklist
Domain Item Request Severity Remark
EHS PPE All team members have to wear PPE of good quality. High
Compactor Provide compactor for backfilling. High
Pole, rope and pulley Provide the ginpole that more than 6m. High
Ladder or Scaffolding Improve PV installation efficiency. Middle
Tool Theodolite To check tower verticality after tower erection done Middle
Earth tester To check site earth resistance High
Jackhammer Provide if meet rocky soil. Middle
Water pump Provide if meet the water inside. Middle
Concrete under tower base Apply for 10cm concrete under tower base. High Optional
Compact soil every 20cm when backfilling. And record to ISDP QC. Also
Civil Work Compact soil every 20cm High
add some water.
Earthing resistance Earthing resistance must less than 10ohm. High
PV direction Make sure the PV panels must be toward due south. Middle
Anti-Climb height Anti-Climb installation height should be 2m minimum . Middle
Tower
Erection Tower verticality check Check the tower verticality by theodolite tool High Optional
The window should be closed by fireproofing mud to avoid entering
Small window under tower High
water.
The upper one should be vertical to the ground. The lower one should Optional
Yagi antenna direction High
be parallel to the ground.
TE
Yagi antenna distance The distance between the two Yagi antennas should be 1.2m. High Optional
RRN/BTS3920R1/BTS3920R Record RRN ID and share to Huawei engineer before installation. High

47 Huawei Confidential
Thank you. 把数字世界带入每个人、每个家庭、
每个组织,构建万物互联的智能世界。
Bring digital to every person, home, and
organization for a fully connected,
intelligent world.

Copyright©2018 Huawei Technologies Co., Ltd.


All Rights Reserved.

The information in this document may contain predictive


statements including, without limitation, statements regarding
the future financial and operating results, future product
portfolio, new technology, etc. There are a number of factors that
could cause actual results and developments to differ materially
from those expressed or implied in the predictive statements.
Therefore, such information is provided for reference purpose
only and constitutes neither an offer nor an acceptance. Huawei
may change the information at any time without notice.