SCHEDULE OF MATERIALS, LABOUR AND EQUIPMENT

CLIENT Mr Oroma Kenneth


LOCATION KEYI-B
PROJECT PROPOSED HOUSE

WORKS: Raska & Boys (before roofing)


DURATION 5 work days

DESCRIPTION UNIT QTY RATE AMOUNT

A.1 Materials
A.1 Cement Trips 15 34,000 510,000
A.2 Pit Sand No 1 250,000 250,000
A.3 Hook Iron No 1 35,000 35,000
A.4 Timber for formwork platform No 4 15,000 60,000
A.5 Eucalytpus poles for scaffolding No 6 8,000 48,000
A.6 Ropes No 5 2,000 10,000

Sub-total 913,000

A.2 Transport
A.2.1 Tranportation Costs Sum 1 30,000 30,000

Sub-total 30,000

Total 943,000

A.3 Labour

A.3.1 Fundis No 10 18000 180000


A.3.2 Helpers No 10 10000 100000
280000

Grand Total 1,223,000

NB: These walls somehow help push down overrall cost of roof.