Annexure I- Price Schedule (for 1 WTG foundation & 1 USS)- R3

Package: "Execution of Civil Works for WTG Foundation & Unit Substation (USS)" for Khavda Hybrid Renewable Power Project at R
(RE) Park, Near Karimshahi, Vighakot Road (50 km from India Bridge), Khavda – 370510, Kachchh – Gujarat.

USS As BOQ
UO
Sr. No. Item Description
M Qty. for USS

No. of WTG Foundations 1

Excavation of earth for WTG machine foundations, trenches, pipe lines, etc. including
setting out, clearing & grubbing, removal of debris, dewatering if required, strutting,
shoring, if required (sheet piling not required), dressing the sides, leveling to grade and
ramming the bottom, stacking/ disposal of surplus excavated material within an initial
lead of 1 km (Radial distance) including respective lifts, loading, transporting,
unloading and spreading with all machinery, manpower, tools & tackles, fuel,
1.00 consumables etc. complete as per Drawings, Specifications and instruction of Engineer
in Charge for the following:
(Execution shall be as per approved excavation plan as per Site requirement. Mode of
measurement shall be PCC dimension of individual footings [i.e. authorized Length &
Width] & depth up to bottom of PCC, as indicated in the Construction Drawing. No
additional payment shall be made for excavation carried out for surrounding working
space and side protection slope.)

All types of soils including, laterite, morrum and weathered rock which can be
1.01 excavated by means of mechanical excavator (but does not require crow bar, pick axe,
chiseling or blasting)
a Up to 1.50M from GL Cum 25.20

b from 1.50m up to 3.0m depth from GL Cum 6.96

Disposal of surplus excavated material beyond 1.0 Km, for every 0.50 Km lead
1.02 Cum Rate Only
(over and above Item no. 1.00)

Backfilling/ Filling for foundation, equipment and machine foundations, trenches,


pipe lines, storm water drains, plinth etc. including dewatering if required, for selected
earth/ soils/ useful cut spoils of rock stacked within the lead of 1.0km (Radial distance)
or as directed by Engineer, including loading, unloading, transporting, watering and
2.00 ramming in layers of 30 cm Compacted thickness to 95% standard proctor maximum Cum 34.36
dry density, compacted, levelling and dressing, including all machinery, manpower,
tools & tackles, fuel, consumables etc. complete as per Drawings, technical
specifications and instruction of Engineer in Charge.
(Backfilling due to any over excavation shall not be measured and paid.)

Transportation of Selected Earth/ soil for Backfilling beyond 1.0km, for every 0.50
2.01 Cum
Km lead (over and above Item no. 2.00)

Filling with selected earth/ morrum/ material bought from approved borrow
areas outside the Site and arranged by the Contractor, for under floors, in foundation
and plinths which includes excavation, loading, transporting for all leads, unloading,
spreading in layers of 30 cm compacted thickness at all depths, watering, compaction
3.00 Cum Rate Only
by manual or mechanical means to minimum 95% of proctor density, dressing and
levelling including all machinery, manpower, tools & tackles, fuel, consumables,
taxes, royalty, screening, etc. complete as per Drawings, technical specifications and
instruction of Engineer in Charge.
De-watering:
Providing services for dewatering using 5- 10 HP capacity diesel pumps depending on
the quantity of discharge of water, required pumping motor with specified
4.00 required/design horse power including providing suction & delivery pipe, foot valve, Hrs. -
fuel & required consumables, all tools and tackles, loading and unloading, shifting,
transportation, manpower etc. all complete as per specifications, details, and/or as
directed by EIC.

Stone Blanket:
Providing and Laying of Stone blanket of 500 mm thickness in 2 layers using
approved quality stone aggregate conforming to IS 383 below finished ground floor
level, below foundation level, hand packing, thoroughly compacting in layers by
5.00 MT -
means of rollers (Small bobcat– Min 3 MT), dressing and levelling including all
machinery, manpower, tools & tackles, fuel, consumables etc. complete as per
Drawings, Specifications and instruction of Engineer in Charge. Gradation of Stone
aggregate shall be as per the QA requirement & as directed by Engineer in Charge.

Loading, unloading, transportation from stores and fixing in position High yield
strength deformed reinforcement steel bar conforming to IS:1786 for foundation &
pedestal work, including handling, decoiling wherever necessary, cleaning, cutting
tack welding lap joint in longitudinal bars, straightening, carting, bending to shapes
6.00 and length as per details, supplying and binding with 16 SWG one strand/ 18 SWG
two strand/ 20 SWG three strand binding wire to the longitudinal bars, etc. complete
for all depths as per specification and as directed by the Engineer-in-charge.
Cut and bend Reinforcement Steel bar for WTG foundation shall be free issue to
the Bidder.

High yield strength deformed bars conforming to grade Fe 500D CRS of IS :1786

a) For WTG foundation and pedestal (Cut & Bend- FIM) MT -


For USS foundation, column & slabs (Cutting & bending shall be in the scope of
b) MT 2.59
bidder)

Laying/ pouring of Ready Mix Concrete (RMC) of any Grade (RCC) into the
WTG foundation & pedestal, other structures of USS incl. Precast cover etc. using
boom placer (wherever required) at all heights / depths, any shape, any position,
thickness including pouring, vibrating, finishing the surface smooth, curing etc. all
7.00 Cum 25.99
complete as per specification, QA requirement, drawings and direction of Employer's
Project Manager. Cost of all material, Tools & tackles, labour, supervision, boom
placer (wherever required), etc. shall be in the scope of Bidder.
Note: Ready Mix Concrete (RMC) shall be Free Issue Material from Employer.

Laying/ Pouring of Ready Mix Concrete (RMC) of any Grade for PCC using
boom placer (wherever required) as levelling course/ fill around foundations, pipes,
floors on grade, water retaining structures, equipment foundations, under foundations,
8.00 flooring under bed, etc. including formwork, scaffolding & staging, materials, Cum 3.20
manpower, Tools & tackles, Consumables, curing etc. all complete as per
specification, drawings and direction of Engineer In Charge.
Note: Ready Mix Concrete (RMC) shall be Free Issue Material from Employer.
Providing and laying of Plum Plain Cement Concrete (Plum PCC): Mix 1:3:6
The plum Concrete ratio shall be 40/60, 40% plums (Boulders), and 60% concrete.
Plums of 75mm to 150mm size shall be used for concrete works. The stones should be
9.00 Cum 13.29
spread evenly and should not be denser than 150mm from surface.
Note: Ready Mix Concrete (RMC) of Mix 1:3:6 shall be Free Issue Material to
Bidder from Employer, however Plum (boulders) shall be in the scope of Bidder.

Providing, fixing and removing formwork at all elevations including providing all
materials, labours, equipment's, consumables, scaffolding, staging, providing pockets,
10.00
etc. complete as per specifications, drawings and as directed & approved by engineer
in charge for the following :

Formwork using steel below finished ground floor level for all types of foundations
a) including up to Raft Top Level, footings, bases of columns, walls, pedestals, beams, Sqm 15.00
mass concrete trenches etc.

Formwork using steel above finished ground floor level for columns, beams,
b) suspended floors, roofs, lintels, cantilevers, staircases, landings, balconies, domes, Sqm 150.00
arches etc. for all heights.

Formwork for Pockets


Formwork for all types of pockets of required size & depth as per drawing for all
elevations including making of required size pocket, shifting, installing form work
c) Sqm 1.00
using required density of thermocol/shuttering for pockets in proper line & level and
removal after initial setting of concrete etc. all complete as directed by Engineer In
Charge. Bidder shall be responsible for maintaining exact pocket size till handing over.

Collecting, Transporting from Employer's Store, fixing & aligning in position of


MS foundation bolts / Anchor cage/ steel stub / template assembly in concrete
along with nuts locknuts, washers, anchor plates, threading, closer plates, stiffener
plates, protective tapes, etc. for slab, pedestals, etc. including pipe sleeves, templates
wherever necessary etc. complete at all levels and required alignment as per
specifications and as directed by the Engineer.
Note:
11.00 1. Anchor bolts / part of Anchor cage/ steel stub and associated accessories shall be MT
free issue to the contractor.
2. Item rate shall be inclusive of cost of fixing of templates.
3. Payment shall be made for weight of each complete foundation bolts / steel stub
excluding with nut, lock nut, washer, stiffener, anchor plates, pipe sleeves etc.
4. Torque Wrench required for tighting of bolts shall be in the scope of Bidder.
5. 120 MT Tyre mounted Crane shall be provided by Employer Free of Cost for fixing
of foundation bolts & its template.

Grouting:
Providing and Laying of Low shrinkage grout with a minimum resistance of C90/105
including roughening surface, cleaning with compressed air, wetting the surface for
several hours, removing accumulated water, curing etc. complete, as per specification
12.00 and as directed by the Engineer In Charge. Cum 0.10
Approved Product: Fosroc-Conbextra BB 92-O/ BASF-Master flow 9375 IN/Sika
Grout 3200 IN.
Note: Low shrinkage grout with a minimum resistance of C90/105 shall be used for
the grout layer
Providing and supplying of sealing material for joints including cleaning the
surface with compressed air, groove cutting etc. complete, as per specification and as
13.00 directed by the Engineer In Charge. KG
Approved Product: Fosroc Thioflex 600 GG/ Sika Polysulphide Gun Grade (AB) IN/
MasterSeal PG 477

Supply, laying, fitting & fixing of Double Walled Corrugated (DWC) HDPE pipe
in to WTG foundation, pedestal & USS including all required bends, junctions,
sockets, adapters, caulking, and all other necessary fittings items at all elevations etc.,
14.00 complete as per drawings, specifications and as directed by the Engineer In-Charge. RMT
Pipe Diameter 175 mm OD / 146 mm ID, Orange One End Coupler with O Ring with
Rodent repellent and NFP Properties, Astral Telerex, Type 750N Compressive
Strength (Part No. A111175C0006E)

Providing and applying of Coal tar-based epoxy protective coating in 2 coats of


approved brand and manufacturer at 600gms/sqm including surface preparation,
mixing, application etc., as per drawing, specification and directed by Engineer in
15.00 Sqm
charge.
Approved Product: NITOCOTE ET 402, Sikagard -5310 Coal Tar, Master Protect
1818, Shalipoxy CTE-303 MI

Providing and laying non-pressure RCC pipes, confirming to IS:458, at all levels,
for all kind of work, collar joined with stiff mixture of Cement Mortar 1:2 (1 Cement :
2 Sand), including providing, laying, installation and jointing of pipes and fittings,
16.00 with all labour, material, equipment, testing etc., all complete, as per specifications, RMT 3.00
drawings and instructions of the Employer's Project Manager. (Excavation, Bedding
and Backfilling shall be paid separately under relevant items).
Pipe with 150 mm NB, class NP3

Supply, laying, fitting & fixing of Double Walled Corrugated (DWC) pipe in USS
including all required bends, junctions, sockets, adapters, caulking, and all other
necessary fittings items at all elevations etc., complete as per drawings, specifications
17.00 RMT 20.00
and as directed by the Engineer In-Charge.
Pipe Diameter 400 mm PE DWC Pipe (6 Mtr) SN 8, Plain With One Coupler and 2
Rubber Ring Drainage Rodent Repellent, Make: Astral D-Rex

Providing and fixing of Sealant of size 50 x 75mm including surface preparation,


mixing, application etc., as per drawing, specification and directed by Engineer in
18.00 charge. RMT Rate Only
Approved Product: Fosroc Nitoseal PU 50, Sikaflex Construction+ IN Con,
MasterSeal NP 473 U
Augur Boring (Tractor/Truck mounted) - 350 dia up to 1000mm depth
Providing, surveying, marking, boring with suitable manual means / mechanical
drilling equipment mechanically operated augur (tractor / truck mounted)/ DTH
machine, for installation of Cast-in-situ bored concrete vertical piles, through all type
of soil/ weathered rock/hard rock up to the specified depth and up to 100mm average
height above finish ground level as indicated in the drawing; using cement concrete of
grade M25 with OPC/PPC conforming to Standard Codes and 20 mm downgraded
coarse aggregate, steel post shall be properly embedded in concrete with desired
elevation, alignment and level; with minimum cement content of 325 kg/cum. The
water cement ratio shall not exceed 0.5 and slump shall be 130-150 mm.
Notes:-
19.00 RMT 31.00
1) Concrete production using Self Loading Concrete Mixers (Ajax Fiori) or
Concrete Mixture Machine and pouring of the same shall be in the scope of
Bidder. Only Cement shall be FIM to Bidder.
2) If any pile is found defective, the Contractor shall rectify/replace it at his own
expense; as directed by the Engineer-in-Charge. This may include
i) Replacement of defective piles.
ii) Providing additional piles.
3) The spoil, boring mud etc. shall be disposed with in 1 Km radial distance.
4) No tremie method, casing pipe and bentonite slurry to be considered.
5) The templates shall not be removed before final setting of concrete, based on final
setting time determined as per mix design.

Providing and laying uniformly graded machine crushed stone aggregate of size
40mm in confined area.
Providing and laying uniformly graded machine crushed stone aggregate of size 40mm
20.00 Cum 9.00
in Transformer yard & Switch yard area including spreading & leveling to the required
elevations including all machinery, manpower, tools & tackles, fuel, consumables etc.
complete as per Drawings, Specifications and instruction of Engineer in Charge.

Providing, Supply, Erection of GI Handrail.


Providing, Supply and Erection of GI handrails in proper position at all levels,
alignment with hot deep galvanized of 85 micron min., fixing including of welding,
erection of bolts, inserts and assembly.
21.00 RMT 35.00
The work also includes straightening, making cutting plan, cutting, bending rolling,
grinding, drilling, machining, bolting erection bolts & nuts, assembly, edge
preparation etc. as per approved drawing, specification and directed by Engineer in
charge.

Providing, Supply, Transporting and erection of various sizes of structural


members, metal inserts etc. with red oxide primer and zinc oxide paint/spray
Supply, Detailing, Fabricating, Transporting and Erecting of metal inserts/structural
members including I-section, C-section, angle section with welded plate /lugs
(embedded parts) in proper position at all levels, alignment, applying two coat of red
oxide primer, two coats of zinc oxide paint (25micron each) and final coat of 25micron
22.00 for the finishing with fixing including welding of lugs etc. as per details in approved MT 7.25
fabrication drawings, GA drawings and specifications.
Notes:
1. Item rate shall be inclusive of cost of providing & fixing above items with
templates.
2. Payment shall be made for weight of each complete metal inserts, anchor plates,
lugs, pipe sleeves etc.
Gratings
Providing, Supply, Erection of various Miscellaneous steel work like Gratings and
23.00 other structures with hot deep galvanized with 85 micron min. as per details in MT 0.10
approved fabrication drawings, GA drawings, specifications and directed by Engineer
in charge.

Casting, Pre-stessing, Supply, Transporting, Handling and fixing of Precast


Concrete Pole (150mm x 100mm x 2400mm, Rectangle-Shaped), including
providing and laying cement concrete of M25 (design mix or nominal mix as per
IS:456:2000) with 16mm downgraded aggregate including placing and fixing of 4mm
dia high strength steel wires- 6 nos. (as per IS 2090) tata Steel make, stretching of wire
as per requirement, shuttering, moulds, openings, recesses, chamfering, tampering,
curing and rendering required to give a smooth and even surface, hole arrangement or
strap for fixing of barbed wire etc. all complete, including the cost of shuttering &
24.00 Nos. 23.00
reinforcement for posts, materials, consumables manpower, Transporting the posts
from the manufacturing yard to work site etc. all complete as per specifications,
drawings and as directed by engineer in charge.

Handling and fixing of prestressed poles including transportation of the members to


the respective location, manual or mechanical lifting and erection of poles all complete
as per specifications drawings and as directed by engineer in charge. Contractor has to
submit the quality test report of steel wire.

Galvanized barbed wire


Supplying, Laying & Fixing Galvanized barbed wire which is made from 4 line wire
of 2.5mm each confirming to IS 278 with Galvanizing requirement : 275 GSM
25.00 (minimum), fixed with Precast pole structures with all necessary accessories as shown RMT 222.00
in drawing etc. all complete including respective lifts, loading, transporting, unloading
including all machinery, manpower, tools & tackles, fuel, consumables etc. complete
as per Drawings, Specifications and instruction of Engineer in Charge.

Supply, Fabrication, transportation, erection and alignment of track rails


Supply, Fabrication, transportation, erection and alignment of track rails and fixing in
concrete including clamps, bolits, washers, nuts, fixtures like fish plates, splice plates,
angles welded at pavements, foming sections at expansion joints, welding etc., as per
approved fabrication drawings, specifications and instructions of the Engineer in
26.00 charge. MT 2.86
Notes:
1. Item rate shall be inclusive of cost of providing & fixing above items with
templates, which shall not be measured and paid.
2. Payment shall be made for weight of each complete Items and accessories to
complate the work.

Providing, Supply and installing Galvanized Steel Gate with Box/pipe section
(Single leaf)
Supplying, fabricating and installing gates built with galvanized steel tube
(conforming to IS 1161) frames including providing box/pipe section of rolled steel,
27.00 MT 0.25
channels for posts, hinges, bottom rollers, guide tracks, welded wire fabric (3.15mm
wire, 50 mm square mesh size), locking arrangements, handles, stoppers, pins etc. all
galvanized as per drawing, specification and as per direction of Engineer in charge.
Gate with Single leaf
Concrete block masonry:
Supplying and laying in position concrete block work of designation D (as mentioned
in IS 2185), minimum compressive strength of 5MPa, in cement-sand mortar 1:4 (1
cement: 4 sand), in sub structure, in foundation and plinth of Size 400x200x150mm,
28.00 Cum 1.80
including mixing mortar, laying bricks, raking joints, curing etc. with all materials,
labour complete as per drawings and specification etc. all complete as approved by the
Project manager.
Cement (for Masonry work only) shall be free issue to the Contractor.

18mm Sand faced plaster on exposed surface


Providing and applying 18 mm thick Sand faced Cement Plaster in two layers, first
layer of 12mm with CM 1:4 (1 cement and 4 fine sand) and Second layer 6mm thick
with CM 1:3 (1 cement and 3 fine sand ) mixed with water proofing compound (cost to
29.00 be included in rate) rough finished with using sponge, on all types of concrete / brick Sqm 20.00
surfaces including making grooves, pattas as per detail, scaffolding, curing, all
materials, tools, plant and labour complete as per drawing, specifications and
directions of the Engineer-in-Charge.
Cement shall be free issue to the Bidder.

Providing and applying three coats of white wash


Providing and applying three coats of white wash with lime over the plastered surfaces
30.00 at all heights above finished ground level including scaffolding, cleaning etc., all as Sqm 20.00
per drawing, specifications and directions of the Engineer-in-Charge, all materials,
tools, plant and labour complete.

Total Basic Amount (in Rs.)

Goods & Services Tax (GST) @ 18%

Grand Total Amount incl. GST


n & 1 USS)- R3
rid Renewable Power Project at Renewable Energy
arat.

USS As BOQ USS as Per Dwg


Amount for USS As per As per drawing
Unit Rate
in Rs. drawing qty. amount

135.00 3,403 28.515 3,849.53

150.00 1,044 7.763 1,164.45

10.00

111.00 3,814 10.44 1,158.84

10.00 - 25.838 258.38

1,465.00 -
350.00 - 0 0

1,260.00 - 0 -

7,000.00 -

10,000.00 25,860 2.86 28,600.00

1,135.00 29,499 23.081 26,196.93

975.00 3,116 3.79 3695.25


1,700.00 22,593 14.53 24707.8

450.00 6,750

500.00 75,000 128.94 64470.5

700.00 700 1 700

8,500.00 -

87,000.00 8,700 0.06


450.00 -

635.00 -

335.00 -

750.00 2,250 0

2,175.00 43,500 0

3,800.00
725.00 22,475 23 16,675.00

2,350.00 21,150 7.41 17,413.50

1,825.00 63,875 20 36,500.00

125,000.00 906,250 0.095 11,875.00


140,000.00 14,000 0.08 11,200

775.00 17,825 33 25,575

21.50 4,773 410.1 8,817

125,000.00 357,500 0 -

135,000.00 33,750 0.25 33,750.00


6,300.00 11,340 3.00 18900

375.00 7,500 20 7,500.00

55.00 1,100 20 1,100.00

1,687,766 344,107

303,798 61,939.32

1,991,564 406,046.65
Measurement sheet
A HT Pannel Slab
Sr.No Description of Item Unit No Nos L B H/D Quantity Remarks

1 Shuttering Work M2

Column

USS Column 6 2 0.300 4.000 14.400

6 2 0.300 4.000 14.400

Tie Beam M2

USS Tie Beam TB2 Shorter side 3 2 1.620 0.300 2.916


USS Tie Beam TB2 Longer side 2 2 1.825 0.300 2.190
2 2 2.075 0.300 2.490

Slab Beam

TB1 Shorter Side 3 2 1.620 0.350 3.402


6 2 0.550 0.350 2.310
USS Tie Beam TB2 Longer side 2 2 1.825 0.350 2.555
2 2 2.075 0.350 2.905
4 2 0.550 0.350 1.540

Slab

Slab Shuttering 1 1 5.900 3.320 19.588

Deduction

Opening 1 1 0.850 0.400


-0.340
1 1 0.850 0.525
-0.446
2 1 0.380 0.115
-0.087
3 2 1.620 0.300 -2.916
6 2 0.550 0.300 -1.980
2 2 1.825 0.300 -2.190
2 2 2.075 0.300 -2.490
4 2 0.550 0.300 -1.320
Total Qty. 56.926
Measurement sheet
Sr.No Description of Item Unit No Nos L B H/D
1 Plum Concrete/PCC M3
plum concrete under Transformer
1 1 2.600 2.200 2.250
Foundation
2.600 2.200 0.075
TOTAL
Quantity Remarks

12.870

0.429
13.299
Sr.No Description Unit Nos Lt Wt Depth Qty

1 Grating Kg 1 0.45 0.45 35 7.0875


35kg/Sqmts Total Qty 7.0875
2 Barbed Wires RMTS 5 55.34 0 276.7
5 Nos of Line
Cross Lines Rmts 20 6.67 0 133.4
Total Qty 410.1

3 Pre cast Columns Nos 33 33


Total Qty 33

4 Structural Steel
a. Insert Plates kg 22 0.07 0.07 47.1 5.07738
b. channel kg 2 1.8 16.8 60.48
c. Insert Plate kg 4 0.2 0.2 94.2 15.072
d. Angles kg 6 0.2 4.5 5.4
Total Qty 86.02938

5 Hand Rail Rmts 1 20.04 20.04


Total Qty 20.04
6 40mm Size aggregate filling Cumts 1 5.45 5.45 0.3 8.91075
-1 2.4 2 0.3 -1.44
-4 0.25 0.25 0.3 -0.075
Total Qty 7.39575
Measurement sheet
Sr.No Description of Item Unit No Nos L B H/D
1 Excavation upto 1.5mts depth M3
plum concrete under
1 1 2.600 2.400 1.500
Transformer Foundation
Burnt oil pit 1 1 3.250 3.250 1.500

TOTAL

Measurement sheet
Sr.No Description of Item Unit No Nos L B H/D
Excavation from 1.5mts to 3.00
1 M3
mts depth
plum concrete under
1 1 2.600 2.400 0.650
Transformer Foundation
Burnt oil pit 1 1 3.250 3.250 0.275
TOTAL
Quantity Remarks

9.360
15.844

25.204

Quantity Remarks

4.056
2.905
6.961
Civil Work WTG Foundation

Measurement sheet
A HT pannel
Sr.No Description of Item Unit No Nos L B H/D Quantity Remarks

1 Shuttering Work M2

Column

USS Column 6 1 0.300 0.300 4.000 2.160

Tie Beam M2

USS Tie Beam TB2 Shorter side 3 1 1.620 0.300 0.300 0.437
USS Tie Beam TB2 Longer side 2 1 1.825 0.300 0.300 0.328
2 1 2.075 0.300 0.300 0.374

Slab Beam

TB1 Shorter Side 3 1 1.620 0.300 0.200 0.292


6 1 0.550 0.300 0.200 0.198
USS Tie Beam TB2 Longer side 2 1 1.825 0.300 0.200 0.219
2 1 2.075 0.300 0.200 0.249
4 1 0.550 0.300 0.200 0.132

Slab

Slab Concreting 1 1 5.900 3.320 0.150 2.938

Deduction

Opening 1 1 0.850 0.400


0.150 -0.051
1 1 0.850 0.525
0.150 -0.067
2 1 0.380 0.115 0.150
-0.013

Total Qty. 7.196


Projects Name: Khavda Wind PJ
Ref. Dwg No:

Bar No. Bar Details Description Bar Shape A (mm)

1 Beam long(tb1) Main Bar (L) top C 250


A
B

2 Beam long(tb1) Main Bar (L) Top C 250


A B

3 Beam long(tb1) Main Bar (L) bottom C 250


A
B

4 Beam long(tb1) Main Bar (L) bottom C 250


A B

5 Beam long(tb1) Stirrups 240

6 Beam short(tb1) Main Bar (L) top C 250


A
B
7 Beam short(tb1) Main Bar (L) Top C 250
A B

8 Beam short(tb1) Main Bar (L) bottom C 250


A
B

9 Beam short(tb1) Main Bar (L) bottom C 250


A B

10 Beam short(tb1) Stirrups 240

11 Beam long(tb2) Main Bar (L) Bottom C 200


A
B

12 Beam long(tb2) Main Bar (L) Top C 200


A B

13 Beam long(tb2) Stirrups 240

14 Beam short(tb2) Main Bar (L) Bottom C 200


A
B
15 Beam short(tb2) Main Bar (L) Top C 200
A B

16 Beam short(tb2) Stirrups 240

17 Slab long direction Bottom C 100


A B

18 Slab long direction Top C 100


A B

Slab short C
19 Bottom 100
direction A B

Slab short C
20 Top 100
direction A B

21 Extra at Cutout Top - Longer side 0


B

22 Extra at Cutout Top - Shorter side 0


B

23 Extra at Cutout Top - Shorter side 0


B
OPTION-2

Section A

24 Short- Column Main Reinf A 300


B

25 Short- Column Main Reinf A 300


B

26 Short- Column dovels A 300


B

27 Short- Column Stirrups-main 220

28 Short- Column Stirrups-second 155

29 middle- Column Main Reinf A 300


B
30 middle- Column Main Reinf A 300
B

31 middle- Column dovels A 300


B

32 middle- Column Stirrups-main 220

33 middle- Column Stirrups-second 155

34 long- Column Main Reinf A 300


B

35 long- Column Main Reinf A 300


B

36 long- Column dovels A 300


B

37 long- Column Stirrups-main 220


38 long- Column Stirrups-second 155

Section D

39 Short- Column Main Reinf A 300


B

40 Short- Column Main Reinf A 300


B

41 Short- Column dovels A 300


B

42 Short- Column Stirrups-main 220

43 Short- Column Stirrups-second 155

44 middle- Column Main Reinf A 300


B
45 middle- Column Main Reinf A 300
B

46 middle- Column dovels A 300


B

47 middle- Column Stirrups-main 220

48 middle- Column Stirrups-second 155

49 long- Column Main Reinf A 300


B

50 long- Column Main Reinf A 300


B

51 long- Column dovels A 300


B

52 long- Column Stirrups-main 220


53 long- Column Stirrups-second 155

OPTION-1

Section A

A B
54 Short- Column Main Reinf 300
C

55 Short- Column Main Reinf A 300


B
C

56 Short- Column Stirrups-main 220

57 Short- Column Stirrups-second 155

A B
58 middle- Column Main Reinf 300
C
A B
59 middle- Column Main Reinf 300
C

60 middle- Column Stirrups-main 220

61 middle- Column Stirrups-second 155

A B
62 long- Column Main Reinf 300
C

A B
63 long- Column Main Reinf 300
C

64 long- Column Stirrups-main 220

65 long- Column Stirrups-second 155

Section D
A B
66 Short- Column Main Reinf 300
C

A B
67 Short- Column Main Reinf 300
C

68 Short- Column Stirrups-main 220

69 Short- Column Stirrups-second 155

A B
70 middle- Column Main Reinf 300
C

A B
71 middle- Column Main Reinf 300
C

72 middle- Column Stirrups-main 220

73 middle- Column Stirrups-second 155


A B
74 long- Column Main Reinf 300
C

A B
75 long- Column Main Reinf 300
C

76 long- Column Stirrups-main 220

77 long- Column Stirrups-second 155

A C
B

A C
B

*All dimension shall be cross verifi


Bar Bending Shedule
Location: HT-LT PLATFORM (RCC)
Date:

Dia of
B (mm) C (mm) Spacing of Bar(mm) Cutting Length(m) No. of Bar
Bar(mm)

5840 250 16 150 6.276 4

5840 250 12 150 6.292 2

5840 250 16 150 6.276 4

5840 250 12 150 6.292 2

290 72 8 150 1.092 78

3260 250 16 150 3.696 6


3260 250 12 150 3.712 3

3260 250 16 150 3.696 6

3260 250 12 150 3.712 3

290 72 8 150 1.092 66

4720 200 16 150 5.088 6

4720 200 12 150 5.096 6

240 72 8 150 0.992 32

2140 200 16 150 2.508 9


2140 200 12 150 2.516 9

240 72 8 150 0.992 42

5850 100 10 150 6.010 22

5850 100 10 150 6.010 22

3270 100 10 150 3.430 40

3270 100 10 150 3.430 40

2350 0 12 0 2.350 8

2025 0 12 0 2.025 4

1900 0 12 0 1.900 4
OPTION-2

2590 0 12 2.842 4

2590 0 16 2.826 4

1650 0 16 1.886 8

220 72 8 150 0.912 19

155 72 8 150 0.652 19

3050 0 12 3.302 4
3050 0 16 3.286 4

1800 0 16 2.036 8

220 72 8 150 0.912 23

155 72 8 150 0.652 23

3100 0 12 3.352 4

3100 0 16 3.336 4

2350 0 16 2.586 8

220 72 8 150 0.912 26


155 72 8 150 0.652 26

2590 0 12 2.842 4

2590 0 16 2.826 4

1400 0 16 1.636 8

220 72 8 150 0.912 18

155 72 8 150 0.652 18

3050 0 12 3.302 4
3050 0 16 3.286 4

1660 0 16 1.896 8

220 72 8 150 0.912 21

155 72 8 150 0.652 21

3100 0 12 3.352 4

3100 0 16 3.336 4

2200 0 16 2.436 8

220 72 8 150 0.912 21


155 72 8 150 0.652 21

OPTION-1

2600 300 12 3.152 4

2600 300 16 3.136 4

220 72 8 150 0.912 17

155 72 8 150 0.652 17

3140 300 12 3.692 4


3140 300 16 3.676 4

220 72 8 150 0.912 20

155 72 8 150 0.652 20

3650 300 12 4.202 4

3650 300 16 4.186 4

220 72 8 150 0.912 24

155 72 8 150 0.652 24


2350 300 12 2.902 4

2350 300 16 2.886 4

220 72 8 150 0.912 15

155 72 8 150 0.652 15

2975 300 12 3.527 4

2975 300 16 3.511 4

220 72 8 150 0.912 18

155 72 8 150 0.652 18


3100 300 12 3.652 4

3100 300 16 3.636 4

220 72 8 150 0.912 22

155 72 8 150 0.652 22

Total Length(m)
Unit Weight in kg/m
Weight in kgs
Weight in MT
Total Weight in Kgs
Total Weight in MT

shall be cross verified from the actual WTG slope


6841-E-WCV-USS-DC-L-I-0004_R

Total Length(m)

Remarks
8 10 12 16

25.104 common for both

12.584 common for both

25.104 common for both

12.584 common for both

85.176 common for both

22.176 common for both


11.136 common for both

22.176 common for both

11.136 common for both

72.072 common for both

30.528 common for both

30.576 common for both

31.744 common for both

22.572 common for both


22.644 common for both

41.664 common for both

132.22 common for both

132.22 common for both

137.2 common for both

137.2 common for both

18.8 common for both

8.1 common for both

7.6 common for both


11.4

11.3

15.1 angle as per wtg slope

17.328 o/o

12.388 o/o

13.2
13.1

16.3 angle as per wtg slope

20.976 o/o

14.996 o/o

13.4

13.3

20.7 angle as per wtg slope

23.712 o/o
16.952 o/o

11.4

11.3

13.1 angle as per wtg slope

16.416 o/o

11.736 o/o

13.2
13.1

15.2 angle as per wtg slope

19.152 o/o

13.692 o/o

13.4

13.3

19.5 angle as per wtg slope

19.152 o/o
13.692 o/o

12.6 c angle shall be as per wtg

12.5 c angle shall be as per wtg

15.504 o/o A

11.084 o/o

14.8 c angle shall be as per wtg


14.7 c angle shall be as per wtg

18.24 o/o

13.04 o/o

16.8 c angle shall be as per wtg

16.7 c angle shall be as per wtg

21.888 o/o

15.648 o/o
11.6 c angle shall be as per wtg

11.5 c angle shall be as per wtg

13.68 o/o

9.78 o/o

14.1 c angle shall be as per wtg

14.0 c angle shall be as per wtg

16.416 o/o

11.736 o/o
14.6 c angle shall be as per wtg

14.5 c angle shall be as per wtg

20.064 o/o

14.344 o/o

angle as per slope

612.3 538.8 295.6 407.2


0.395 0.617 0.888 1.578
241.59 332.22 262.47 642.66
0.242 0.332 0.262 0.643
1478.94
1.479
Option-2
Total Length(m) 430.8 538.8 211.1 323.1
Unit Weight in kg/m 0.395 0.617 0.888 1.578
Weight in kgs 170.01 332.22 187.44 509.88
Weight in MT 0.17 0.332 0.187 0.51
Total Weight in Kgs 1199.55
Total Weight in MT 1.2
6841-E-WCV-USS-DC-L-I-0004_R1 RFC drawing
B
C
B
Projects Name: Khavda Hybrid Power Project
Ref. Dwg No:

Bar No. Bar Details Description Bar Shape

Transformer
1 top A
Foundation
B

Transformer
2 top A
Foundation
B

Transformer
3 bottom A
Foundation
B

Transformer
4 bottom A
Foundation
B

Transformer
5 side-1 A
Foundation
B

Transformer
6 side-1 A
Foundation
B
Transformer
7 side-2 A
Foundation
B

Transformer
8 side-2 A
Foundation
B

Transformer
9 side-3 A
Foundation
B

Transformer
10 side-3 A
Foundation
B

Transformer
11 side-4 A
Foundation
B

Transformer
12 side-4 A
Foundation
B

B
A

Transformer
13 Chairs
Foundation

14 Pedestal P1 Vertical U - Bar A

B
15 Pedestal P1 stirups

250
Pedestal bottom
16 Pedestal P1 reinforcement local
thickning

17 Sock pit Raft Main Bar in 6.05 A


B

A
18 Sock pit Raft Sump

A
19 Sock pit Raft Sump

Sock pit raft and


20 transformer Straight bars
connecting rebars

A
21 Sock pit Raft Sump

B
A
22 Sock pit Raft Sump

23 Sock pit Raft Main Bar in 5.65 A


B

A
24 Sock pit Raft Sump

A
25 Sock pit Raft Sump

Sock pit raft and


26 transformer Straight bars
connecting rebars

A
27 Sock pit Raft Sump

A
28 Sock pit Raft Sump

A A C BBBBB
A
A
Bar Bending Shedule
Location: WTG USS
Date: 13-09-2023

Spacing
Dia of
Bar Shape A (mm) B (mm) C (mm) of
Bar(mm)
Bar(mm)

C 350 1920 350 10 150

C 350 2320 350 10 150

C 350 1920 350 10 150

C 350 2320 350 10 150

C 350 1920 350 10 150

C 350 970 350 10 150

B
C 350 2320 350 10 150

C 350 970 350 10 150

C 350 1920 350 10 150

C 350 970 350 10 150

C 350 2320 350 10 150

C 350 970 350 10 150

B
500 970 250 10 150
C

A 600 170 50 12

B
170 170 8 150

250 250
1702 10 150
850

C 400 6000 400 10 150

400 5425 300 10 150


B
C

C
800 650 300 10 150

B 3400 0 10 150

400 1700 0 10 150

B
400 1900 0 10 150

C 400 5600 400 10 150

400 5050 300 10 150


B
C

C
800 650 300 10 150

B 3000 0 10 150

400 1800 0 10 150

400 1800 0 10 150

BBBBB BBBC A C Total Length(m)


Unit Weight in kg/m
Weight in kgs
Weight in MT
Total Weight in Kgs
Total Weight in MT
le
WTG USS
Date: 13-09-2023
Total Length(m)
Cutting
No. of Bar
Length(m)
8 10 12 16

2.58 16 41.280

2.98 13 38.740

2.58 16 41.280

2.98 13 38.740

2.58 7 18.060

1.63 13 21.190
2.98 7 20.860

1.63 16 26.080

2.58 7 18.060

1.63 13 21.190

2.98 7 20.860

1.63 16 26.080

1.68 42 70.560

1.374 8 10.992
0.712 20 14.240

1.662 48 79.776

6.76 22 148.720

6.085 4 24.340

1.71 4 6.840

3.4 13 44.200

2.06 13 26.780
2.26 13 29.380

6.36 21 133.560

5.71 4 22.840

1.71 4 6.840

3 16 48.000

2.16 16 34.560

2.16 16 34.560

Total Length(m) 14.24 1054.368 0.0 0


Unit Weight in kg/m 0.395 0.617 0.889 1.58
Weight in kgs 5.625 650.545 0 0
Weight in MT 0.006 0.651 0 0
Total Weight in Kgs 656.17
Total Weight in MT 0.656
Remarks
4 nos. of Pedestal P1
4 nos. of common Pedestal(in to
in dimension )

4 nos. of Pedestal P1,AT 45


DEGREE
GRID
S. NO. DESCRIPTION OF BAR SHAPE OF BAR
NO.

BURNT OIL PIT


RAFT
1 Bottom Main Bar
2 Bottom Main Bar A
B
C
A C
Bottom B
Distribution Bar A
3 B
(Deduction Sump
C
area)
TOP Distribution
4 Bar (Deduction A
B
C
Sump area)
Bottom
Distribution Bar A C
5 (Deduction Sump
B

area)
TOP Distribution
6 Bar (Deduction A
B
C
Sump area)
Bottom
7 Distribution Bar A
B
(Deduction Sump
C
area)
A
8 Top Main Bar
B
WALL
C C
9 Vertical Bars
B
10 Vertical Bars
BA
11 Binders C A

SLAB A
B
C
B
12 Bottom Main Bars

13 Bottom Distribution Bars

14 Top Main Bars

15 Top Distribution Bars

16 Lugs - steps
Extra Bar near cover
17 opening
L1

18 precast cover

19 precast cover(lifting hook


TOTAL LENGTH OF STEEL BAR (M
UNIT WEIGHT OF STEEL KG/M
STEEL WEIGTH IN KG's
STEEL WEIGTH IN MT
GRAND TOTAL IN MT
BAR BENDING SECHDULES (B.B.S.)
CUTTING
DIA SPACING Lap Elongation
(MM) (MM) A (L1) B (L2) C (L3) Addition Deduction
LENGTH
(MM)

12 150 150 3000 150 0 48 3252


12 150 150 3000 150 0 48 3252

12 150 150 2000 200 0 48 2302

12 150 150 2050 350 0 48 2502

12 150 250 850 250 0 48 1302

12 150 250 850 250 0 48 1302

12 150 475 500 200 0 48 1127

12 150 450 400 250 0 48 1052

12 200 250 1960 200 0 48 2362


12 200 250 1960 200 0 48 2362
12 200 100 2300 100 0 48 2452
10 150 100 2300 100 0 40 2460
10 150 100 2300 100 0 40 2460
10 150 100 2300 100 0 40 2460
10 150 100 2300 100 0 40 2460
16 200 150 250 350 0 128 622

12 1000 0 0 0 1000

8 650 0 0 0 650
8 450 0 0 0 450
TOTAL LENGTH OF STEEL BAR (Mtr)
UNIT WEIGHT OF STEEL KG/Mtr
STEEL WEIGTH IN KG's
STEEL WEIGTH IN MT
GRAND TOTAL IN MT
Nos. of TOTAL
LENGTH OF BAR (MTR)
Bar NOS.

8 10 12 16 20 25 32

18 36 0 0 117.072 0 0 0 0
18 36 0 0 117.072 0 0 0 0

4 8 0 0 18.416 0 0 0 0

4 8 0 0 20.016 0 0 0 0

4 8 0 0 10.416 0 0 0 0

4 8 0 0 10.416 0 0 0 0

4 8 0 0 9.016 0 0 0 0

4 8 0 0 8.416 0 0 0 0
0 0 0 0 0 0 0
48 48 0 0 113.376 0 0 0 0
44 44 0 0 103.928 0 0 0 0
17 68 0 0 166.736 0 0 0 0
0 0 0 0 0 0 0
16 16 0 39.36 0 0 0 0 0
16 16 0 39.36 0 0 0 0 0
16 16 0 39.36 0 0 0 0 0
16 16 0 39.36 0 0 0 0 0
9 9 0 0 0 5.598 0 0 0

2 6 0 0 6 0 0 0 0

3 6 3.9 0 0 0 0 0 0
4 4 1.8 0 0 0 0 0 0
5.7 157.44 700.88 5.598 0 0 0
0.395 0.617 0.889 1.578 2.466 3.853 6.320
2.2515 97.14048 623.0823 8.833644 0 0 0
0.002 0.097 0.623 0.009 0.000 0.000 0.000
0.731
REMARK
Measurement sheet
A HT Pannel Slab
Sr.No Description of Item Unit No Nos
1 uss column shuttering option -2 UPTO B
section A SQM
C1 1 4
C2 1 4
C3 1 4
section-D SQM
C1 1 4
C2 1 4
C3 1 4
COLUMN SHUTTERING ABOVE BEAM2 TO BELOW BEAM BOTTOM
SECTION $ SECTION D SQM 6 4

BEAM 2 SHUTTERING QUANTITY


2 LONGER BEAM2 SIDES SQM

OUTER PORTION SQM 2 1


INNER PORTION SQM 2 1

SHORTERV BEAM2 SIDES


OUTER PORTION SQM 2 1
INNER PORTION SQM 4 1

SLAB BOTTOM BEAM QUANTITY


3 LONG BEAM1 SIDES
OUTER PORTION SQM 2 1
INNER PORTION SQM 2 1

SHORTER BEAM1 SIDES


OUTER PORTION SQM 2 1
INNER PORTION SQM 4 1

SLAB BEAM BOTTOM


LONG BEAM BOTTOM SQM 2 1
SHORT BEAM BOTTOM SQM 3 1
SLAB SHUTTERING QUANTITY
5 SLAB SHUTTERING QUANTITY SQM 1 1
SLAB SIDES QUANTITY
LONG SIDES SQM 2 1
SHORTS SIDES SQM 2 1

TOTAL QUANTITY WITH


DEDUCTION

CUTOUT PORTION SQM 1 1


1 2
1 1

BEAM BOTTOM DEDUCTION SQM


LONG BEAM BOTTOM SQM 2 1
SHORT BEAM BOTTOM SQM 3 1

TOTAL QUANTITY OF HT PANEL SHUTTERING

Transformer Foundatio
Shuttering Work M2
Transformer Foundation 2 1
2 1
sump wall 4 1
Shuttering for Outer side grade slab 4 1
grade slab pcc shuttering 4 1

4 1
Shuttering for Inner and outer side
wall
4 1

pedestral 1 column 4 4
1 1
plum shuttering 1 1
plum shuttering
2 1
plum pcc shuttering 2 1
2 1
TOTAL

C Burnt Oil Pit


3 Shuttering Work M2
Shuttering for Burnt oil Pit Raft 4 1
Sump 4 1
p.c.c shuttering 4 1
Shuttering for Burnt oil Pit wall 2 2
2 2
Burnt oil tank top slab 1 1
Deduction
Opening 1 1
TOTAL

TOTAL SHUTTERING FOR ALL ELEMENT


ment sheet
HT Pannel Slab
L B H/D Quantity Remarks
ng option -2 UPTO BEAM2 HEIGHT
0.3 1.35 1.62 2135-1300
0.3 0.835 1.002
0.3 0.2 0.24

0.3 1.215 1.458


0.3 0.675 0.81
0.3 0.08 0.096
AM BOTTOM
0.3 2 14.4

TOTAL COULMN SHUTTERING 19.626

QUANTITY

4.8 0.3 2.88


3.9 0.3 2.34

2.22 0.3 1.332


1.62 0.3 1.944
0
TOTAL QUANTITY OF BEAM2 8.496

QUANTITY
5.9 0.2 2.36
5 0.2 2

3.32 0.2 1.328


2.72 0.2 2.176

5 0.3 3
2.72 0.3 2.448
TOTAL BEAM 1 QUANTITY 13.312

UANTITY
5.9 3.32 19.588

5.9 0.15 1.77


3.32 0.15 0.996

TOTAL QUANTITY WITHOUT DEDUCTION 22.354

0.85 0.4 0.34


0.38 0.115 0.0874
0.85 0.525 0.44625
0
0
TOTAL CUTOUT QUANTUITY 0.87365

5 0.3 3
2.72 0.3 2.448
TOTAL BEAM BOTTOM QUANTUITY 5.448

TOTAL QUAQNTITY OF SLAB 16.03235

T PANEL SHUTTERING 57.46635

ormer Foundation
2.000 1.050 4.200
2.400 1.050 5.040
0.450 0.300 0.540
5.700 0.125 2.850
5.700 0.075 1.710

5.700 0.450 10.260

5.450 0.450 9.810

0.450 0.300 2.160


2.600 1.975 5.135
2.600 2.475 6.435
2.200 2.225 9.790
2.200 0.075 0.330
2.600 0.075 0.390
TOTAL 58.260

Burnt Oil Pit


3.100 0.250 3.100
0.450 0.450 0.810
3.300 0.075 0.990
2.400 1.700 16.320
2.000 1.700 13.600
2.400 2.400 5.760

0.690 0.690 -0.476


TOTAL 40.104

ALL ELEMENT; 155.830


2135-1300
Measurement sheet
A HT Pannel Slab
Sr.No Description of Item Unit No Nos

1 uss column CONCRETE option -2 UPTO B


section A CUM
C1 1 1
C2 1 1
C3 1 1
section-D CUM
C1 1 1
C2 1 1
C3 1 1
COLUMN SHUTTERING ABOVE BEAM2 TO BELOW BEAM BOTTOM
SECTION $ SECTION D CUM 6 1

BEAM 2 CONCRETE QUANTITY


2 LONGER BEAM2 CUM

2 1

SHORTER BEAM2
CUM 3 1

SLAB BOTTOM BEAM QUANTITY


3 LONG BEAM1 SIDES
OUTER PORTION CUM 2 1

SHORTER BEAM1 SIDES


OUTER PORTION CUM 3 1
SLAB SHUTTERING QUANTITY
5 SLAB CONCRETE QUANTITYCUM 1 1

TOTAL QUANTITY WITHOUT


DEDUCTION

CUTOUT PORTION CUM 1 1


1 2
1 1

TOTAL QUANTITY OF HT PANEL SHUTTERING

Transformer Foundatio
Concrete Work M³
Transformer
1 1
Foundation(M35

sump wall(M35) 1 1
Concrete for Outer side
1 1
grade slab(M35)
grade slab pcc Concrete
1 1
(M15)
Concrete for Inner and 4 1
outer side wall
pedestral 1 column
4 1
concrete
1 1
plum concrete
plum concrete

plum pcc concrete 1 1

TOTAL

C Burnt Oil Pit


3 Shuttering Work M2
Concrete for Burnt oil Pit
1 1
Raft-(M35)
Sump(M35) 1 1
p.c.c concrete-M15 1 1
Concrete for Burnt oil Pit
4 1
wall(M35)

Burnt oil tank top slab 1 1

Deduction
Opening 1 1
TOTAL

TOTAL SHUTTERING FOR ALL ELEMENT

Brick Quantity
asurement sheet
HT Pannel Slab
L B H/D Quantity Remarks

NCRETE option -2 UPTO BEAM2 HEIGHT


0.3 0.3 1.35 0.1215
0.3 0.3 0.835 0.07515
0.3 0.3 0.2 0.018
0
0.3 0.3 1.215 0.10935
0.3 0.3 0.675 0.06075
0.3 0.3 0.08 0.0072
ELOW BEAM BOTTOM
0.3 0.3 2 1.08

TOTAL COULMN CONCRETE 1.47195

ETE QUANTITY

4.8 0.3 0.3 0.864

2.22 0.3 0.3 0.5994

0
TOTAL QUANTITY OF BEAM2 1.4634

EAM QUANTITY
5.9 0.3 0.2 0.708

3.32 0.3 0.2 0.5976


TOTAL BEAM 1 QUANTITY 1.3056

NG QUANTITY
5.9 3.32 0.15 2.9382

TOTAL QUANTITY WITHOUT DEDUCTION 2.9382

0.85 0.4 0.15 0.1275


0.38 0.115 0.15 0.114
0.85 0.525 0.15 0.1275
0
0
TOTAL CUTOUT QUANTUITY 0.369

TOTAL QUAQNTITY OF SLAB 2.5692

F HT PANEL SHUTTERING 6.81015

ansformer Foundation
2.000 2.400 1.050 5.040

0.450 0.450 0.300 0.061

5.700 5.700 0.125 4.061

5.900 5.900 0.075 2.611

5.700 0.125 0.450 1.283

0.250 0.250 0.450 0.113

2.600 2.200 2.225 12.727


2.200 2.600 0.075 0.429

TOTAL 26.324

Burnt Oil Pit

3.100 3.100 0.250 2.403

0.450 0.450 0.450 0.091


3.300 3.300 0.075 0.817

2.400 0.200 1.700 3.264

2.400 2.400 0.150 0.864

0.690 0.690 0.150 -0.071


TOTAL 7.367

FOR ALL ELEMENT; 40.501