8 Marking of grove joint to fit Purple heart Tape measure

the panels Tri-square


Ruler
Carpenters’ pencil
Sprit level
9 Cutting the groove joint Purple heart Jig saw
10 Marking of the panels Purple heart Tape measure
Tri-square
Ruler
Carpenters’ pencil
Sprit level
11 Cutting panels Purple heart Jig saw with
appropriate cutter
12 Marking tongue on panels Purple heart Tape measure
Tri-square
Ruler
Carpenters’ pencil
Sprit level
13 Cutting the tongue Purple heart Portable electric circle
saw
14 Marking of dowels Purple heart Carpenters’ pencil
Tri-square
Tape measure
15 Cutting of dowels Purple heart Portable electric circle
Sandpaper saw
Mortise chisel
Sanding block
16 Trial Assembly Purple heart ----------
17 Assembly Purple heart Bar clamps
Dowels Mallet
Wood glue
18 Finishing (sanding) Purple heart Sanding block
Sandpaper Orbit sander
19 Finishing (Painting) Purple heart Paint brush
Wood Primer
Oil based paint
Construction Project-Walkway

Steps of Procedures

No Description Materials Tools and Equipment


1 Measure, Mark and Layout Twine Shovel, Cutlass,
Walkway Wood Sledgehammer
Nails Claw hammer
2 Site preparation Form Board and Claw Hammer and
Nail Sledgehammer
3 Sandfill Sand Wheelbarrow and Spade
4 Setup for concrete work Sand, Cement, Spade, Construction
Stone, and Bucket and Spade
Water
5 Mix Concrete Sand, Cement, Spade and Bucket
Stone, and
Water
6 Transporting Cement mix to Cement Mix Wheelbarrow and Spade
walkway
7 Pour Cement mix into Cement Mix Spade, Trowel
walkway Wheelbarrow
8 Rod Cement mix in walkway Cement Mix Wooden Rod
9 Float Concrete Cement Mix Plastic and Steel Float
Estimate

No Name of Qty Description BM Unit Total Price


part Price ($)
($)
1 Concrete 4 Cement ---- $200 $8000
Mix Sacks 0
17 Sand ---- $100 $17000
0
2 Form 36’ 1×6 (Hardwood) 18 $160 $2880
Work
36’ 2×3 (Hardwood) 18 $260 $4680
3 Fixing Pound 2 ½” --- $300 $300

8 Sacs Cement Total Material $38,860


Cost
Total $5000
Transportation
Cost

Labour Cost $12,953


Grand Total $56,813
Construction Project-Stool

Steps of Procedures

No Description Materials Tools and Equipment


1 Selection of Materials Silverballi ----------
2 Preparation of Materials Silverballi Sand Paper, Electric
Sander, Sanding Block
3 Measurement and layout for Silverballi Tri-Square, Carpenters
specific sizes in according to Pencil, Tape Measure
design
4 Cutting to specific length Silverballi Rip Saw
5 Marking of Joints Silverballi Tri-Square, Carpenters
Pencil, Tape Measure
6 Digging of Joints Silverballi Mortise Chisel, Mallet,
Bench Vise, G-Clamp
7 Cutting of Joints Silverballi Mortise Chisel, Mallet,
Bench Vise, G-Clamp,
Tenon Saw
8 Marking of Grove Joints to fit Silverballi Ruler, Carpenters Pencil,
the Joints (Mortaise) Tri-Square, Mortaise
Chisel
9 Digging/Cutting of Mortaise Silverballi Hammer, Mortaise
Chisel
Drill Press
10 Marking of the Top Silverballi Tri-Square, Ruler,
Carpenters Pencil, Tape
Measure
11 Cutting of Top Silverballi Jig Saw
12 Assesmbly Silverballi Nail Bar Clamp, Wood Glue,
Mallet
13 Finishing (Sanding) Silverballi Electric Sander, Sanding
Block
14 Finishing (Painting) Silverbali Painting Brush, Oil Based
Paint,
Estimate

No Name of Qty Description BM Unit Total Price


part Price ($)
($)
1 Legs 1 2”×2”×3’ 12 $260 $3,120
2 Top Rails 1 1”×3”×3’ 9 $260 $2,340
3 Bottom 1 1”×3”×2’ 6 $260 $1,560
Rails
4 Cross Rails 1 1”×3”×1.5’ 4.5 $260 $1,170
5 Top 1 1’×1’×½” Plywood ------ $7000 $7000

6 Finishing ----2lb 2” Headless ------ $350 $350


Nail
10 80 Grade ------ $100 $1000
Sandpaper
10 120 Grade ------ $100 $1000
Sandpaper
5 fl.oz Wood Glue ------ $1,100 $1,100

¼“ Painting Brush ------ $200 $200

2 pt Oil Based Paint ------ $4000 $4000

Total Material $22,840


Cost
Total $5000
Transportation
Cost

Labour Cost $8,000


Grand Total $35,840
CONTENT PAGE
Topics Page

Section One - Core


Fundamentals Of Industries
 Organizational Structure of a Simple Construction Industry………
 Organizational Structure of a Simple Manufacturing Industry………
 Set Of Safety Rules………………………………………………………………………
 Report of an Accident…………………………………………………………………
 Small Business Plan………………………………………………………………………
Design Analysis and Process
 Design Analysis of a Simple Manufactured Product…………………………
Information Communication Technology
 Power Point Presentation…………………………………………………………………
Section Two- Site Work Operations
 Establishing a Baseline…………………………………………………………………….
 Establishing Corner Profile……………………………………………………………...

Section Three- Basic Architectural Drawing

 Description of Problem…………………………………………………………………
 Orthographic Drawings………………………………………………………………….

Section Four- Construction Project

 Steps of Procedures……………………………………………………………………
 Evidence…………………………………………………………………………………….

Section Five- Furniture Technology Project

 Steps of Procedure…………………………………………………………………….
 Evidence…………………………………………………………………………………...

You might also like