INSPECTION TEST PLAN FOR LV INSTRUMENT

Supplier
CABLE
Document No. TBA
Revision No. A Rev. Date 15 MAY 2024

Prepared by: ITP for: INSPECTION TEST PLAN FOR LOW VOLTAGE INSTRUMENT CABLE Rev: A

Discipline
N/A Date: 16 MAY 2024 No of Pages: 1 of 5
code:
Inspection Point
Activity Controlling Verifying Master Tec Client
No. Acceptance Criteria Frequency
Description Document Document Wire &
Cable Sdn.
Bhd.
1.0 Electrical Test
- FAT As per Technical
1.1 High Voltage Test Procedure for Datasheet, BS EN 50288-7 1 sample per cable
Low Voltage type / data review - Electrical Test
Instrument
Report
Cable H S/R

As per Technical - Electrical Test


- FAT Procedure
Datasheet, BS EN 50288-7 1 sample per Report )
1.2 Conductor Resistance for Low Voltage H S/R
cable type /
Test Instrument Cable
data review

Remarks: Inspection Authority:


H : Hold Point Points where no further works shall proceed without the written approval of the Supervising Supplier TBA
Engineer/ PIC appointed by Contractor
W : Witness Point Points where Contractor can optional to observe/ or visually examine or participate in the QC
operation of the Supplier
S : Surveillance Points where the Supervising Engineer/ PIC appointed by Contractor monitor the Supplier activities
to the degree necessary for confidences that work process/ method is complying with the established
criteria
R : Review Review of the Supplier’s ITP records for correctness and completeness

Page 1 of 5
INSPECTION TEST PLAN FOR LV INSTRUMENT
Supplier
CABLE
Document No.
Revision No. A Rev. Date 15 MAY 2024

Prepared by: ITP for: INSPECTION TEST PLAN FOR LOW VOLTAGE INSTRUMENT CABLE Rev: A

Discipline
N/A Date: 16 MAY 2024 No of Pages: 2 of 5
code:
Inspection Point
Activity Controlling Verifying Master Tec Client
No. Acceptance Criteria Frequency
Description Document Document Wire &
Cable Sdn.
Bhd.
- FAT Procedure for As per Technical Datasheet
Low Voltage (SH20240208-03E-0103), - Electrical Test
Insulation Instrument Cable BS EN 50288-7 1 sample per Report
1.3 H S/R
ResistanceTest cable type /
data review

As per Technical
- FAT Datasheet, BS EN 50288-7
Procedure for 1 sample per - Electrical Test
Continuity Test Low Voltage cable type / Report
1.4 H S/R
Instrument data review
Cable

Remarks: Inspection Authority:


H : Hold Point Points where no further works shall proceed without the written approval of the Supervising Supplier TBA
Engineer/ PIC appointed by Contractor
W : Witness Point Points where Contractor can optional to observe/ or visually examine or participate in the QC
operation of the Supplier
S : Surveillance Points where the Supervising Engineer/ PIC appointed by Contractor monitor the Supplier activities
to the degree necessary for confidences that work process/ method is complying with the established
criteria
R : Review Review of the Supplier’s ITP records for correctness and completeness

Page 2 of 5
INSPECTION TEST PLAN FOR LV INSTRUMENT
Supplier
CABLE
Document No.
Revision No. A Rev. Date 15 MAY 2024

Prepared by: ITP for: INSPECTION TEST PLAN FOR LOW VOLTAGE INSTRUMENT CABLE Rev: A

Discipline
N/A Date: 16 MAY 2024 No of Pages: 3 of 5
code:
Inspection Point
Activity Controlling Verifying Master Tec Client
No. Acceptance Criteria Frequency
Description Document Document Wire &
Cable Sdn.
Bhd.
Dimensional &
2.0
Constructional Test
As per Technical
Conductor - FAT Datasheet, BS EN 50288-7 - Conductor
- Check on type Procedure for 1 sample per Diameter And
- Number of strand & Low Voltage cable type / Breaking Load
2.1 strand diameter Instrument H S/R
data review Inspection
- Measurement of Cable Report
conductor diameter

Insulation As per Technical - Cable


- FAT
- Check on core Datasheet, BS EN 50288-7 Thickness
Procedure for 1 sample per
2.2 identification Inspection H S/R
Low Voltage cable type /
- Measurement of Report
Instrument data review
Insulation thickness
Cable
- Measurement of
insulation
diameter
- Core orientation
- Lay direction

Remarks: Inspection Authority:


H : Hold Point Points where no further works shall proceed without the written approval of the Supervising Supplier TBA
Engineer/ PIC appointed by Contractor
W : Witness Point Points where Contractor can optional to observe/ or visually examine or participate in the QC
operation of the Supplier
S : Surveillance Points where the Supervising Engineer/ PIC appointed by Contractor monitor the Supplier activities
to the degree necessary for confidences that work process/ method is complying with the established
criteria
R : Review Review of the Supplier’s ITP records for correctness and completeness

Page 3 of 5
INSPECTION TEST PLAN FOR LV INSTRUMENT
Supplier
CABLE
Document No.
Revision No. A Rev. Date 15 MAY 2024

Prepared by: MASTER TEC WIRE & CABLE ITP for: INSPECTION TEST PLAN FOR LOW VOLTAGE INSTRUMENT CABLE Rev: 00
SDN BHD
Discipline
N/A Date: 16 MAY 2024 No of Pages: 4 of 5
code:
Inspection Point
Activity Controlling Verifying Master Tec Client
No. Acceptance Criteria Frequency
Description Document Document Wire &
Cable Sdn.
Bhd.
As per Technical
Bedding - FAT Datasheet, BS EN 50288-7 - Conductor
- Measurement of Procedure for 1 sample per Diameter And
bedding thickness Low Voltage cable type / Breaking Load
2.3 - Measurement of Instrument H S/R
data review Inspection
bedding diameter Cable (MT- Report
TP-160524-
IC)
Armouring / Braiding - Cable
- FAT
- Armouring As per Technical Thickness
Procedure for 1 sample per
2.4 wire diameter / Datasheet, BS EN 50288-7 Inspection H S/R
Low Voltage cable type /
Braiding Report
Instrument data review
coverage
Cable

2.5 Outer Sheath - Cable


- FAT
- Measurement As per Technical Thickness
Procedure for 1 sample per
of outer sheath Datasheet, BS EN 50288-7 Inspection H S/R
Low Voltage cable type /
thickness Report
Instrument data review
- Measurement
Cable
of overall
diameter

Page 4 of 5
INSPECTION TEST PLAN FOR LV INSTRUMENT
Supplier
CABLE
Document No.
Revision No. A Rev. Date 15 MAY 2024

Prepared by: ITP for: INSPECTION TEST PLAN FOR LOW VOLTAGE INSTRUMENT CABLE Rev: A

Discipline
N/A Date: 16 MAY 2024 No of Pages: 5 of 5
code:
Inspection Point
Activity Controlling Verifying Master Tec Client
No. Acceptance Criteria Frequency
Description Document Document Wire &
Cable Sdn.
Bhd.
Flame Test
3.0
- FAT As per Technical
- Flame Retardant Procedure for Datasheet, IEC 60332-3-22 - SIRIM type
Test (For outer Low Voltage Adduce type test report
sheath LS0H only) Power Cable test report
3.1 H W
from SIRIM

- Fire Resistant As per Technical - SIRIM type


- FAT
Test (For MGT Datasheet, IEC 60331 test report
Procedure for Adduce type
3.2 cable only) H W
Low Voltage test report
Power Cable from SIRIM

Remarks: Inspection Authority:


H : Hold Point Points where no further works shall proceed without the written approval of the Supervising Supplier TBA
Engineer/ PIC appointed by Contractor
W : Witness Point Points where Contractor can optional to observe/ or visually examine or participate in the QC
operation of the Supplier
S : Surveillance Points where the Supervising Engineer/ PIC appointed by Contractor monitor the Supplier activities
to the degree necessary for confidences that work process/ method is complying with the established
criteria
R : Review Review of the Supplier’s ITP records for correctness and completeness

Page 5 of 5