ODEON - WEEKLY REPORT

Project Name: Odeon


Overall
Contractor: Apex Realty Pvt Ltd
Completion %
55%
Client: MNPHI
Start date: 12/01/22 Total project duration: 48 Months Reporting Date: 04/04/24
Completion date: 12/01/26 Total elapsed days: 719 days Week Number: 118
Consultant: Riyan Pvt Ltd Lost work days: 36 days Dates: 04/04/24
SN Activity Due Date Completed % Comments
Below ground floor works completed
Completion of Ground, Mezzanine and 1st floor Partial slab at 2.8 Mtr height at ground level is completed
1 24/06/23 100%
slabs (3 nos slabs) Mezzanine floor level slab completed
First floor level slab completed on 24/01/23
Completion of 2nd, 3rd, 4th and 5th floor
2 31/10/23 100% 5th floor level slab completed on 31/07/23
(4 nos slab)
8th floor level slab completed on 19/10/23.
Completion of 6th, 7th, 8th ,9th, Roof floor and 9th Floor Slab Completed on 17/11/23
3 Other Concrete Work/Lift head room 26/06/24 100% Terrace Slab Concrete Completed on 18/12/23
(5 nos slab) Roof Slab Concrete Completed on 05/02/24
Swimming Pool Concrete Completed on 28/03/24
Ground Floor Block Masonry work – 50%
Mezzanine Floor Block Masonry work – 75%
Finishing Work-Completion of Ground, 1st Floor Block Masonry work – 100% Completed.
4 Mezzanine and 1st floor (up to 1st floor level) 29/07/24 45%
1st Floor Internal Plastering – 100%
1st Floor Tiling Work- 100% Completed
1st Floor Internal Primer work – 20% Completed
3rd Floor Block Masonry work – 100% Completed.
4th Floor Block Masonry work – 100% Completed.
05th Floor Block Masonry Work- 100% Completed
Finishing Work-Completion of 2nd, 3rd, 4th and 2nd & 03rd Floor Internal Plaster Work – 100% Completed
5 5th floor. 09/12/24 60% 4th Floor Internal Plastering Work-85% Completed
5th Floor Internal Plastering Work- 100% Completed
2nd Floor Tiling Work- 100% Completed
3rd Floor Tiling Work- 45% Completed
4th Floor Tiling Work – 5% Completed
6th Floor Block Masonry work – 100% Completed
7th Floor Block Masonry Work- 100% Completed
08th Floor Block Masonry Work- 85% Completed
Finishing Work-Completion of 6th, 7th, 8th and
6 10/04/25 40% 09th Floor Block Masonry Work- 45% Completed
9th floor.
6th Floor Internal Plastering Work- 100% Completed
7th Floor Internal Plaster Work – 80% Completed
08th Floor Internal Plaster Work – 20% Completed
Finishing Work Completion of Lift m/c room,
7 06/05/25 0% Future Activity
Above Terrace & other misc. facilities

Ground Floor Wall Conduiting 100% Completed


MEP Work-Completion of Ground, Mezzanine
8 02/10/24 35% 01st Floor Wall Conduiting 100% Completed
and 1st floor (up to 1st floor level)
01st Floor Internal Plumbing Work 100% Completed

02nd and 03rd Floor Wall Conduiting 100% Completed


04th Floor Wall Conduiting 100% Completed
05th Floor Wall Conduiting 100% Completed
MEP Work-Completion of 2nd, 3rd, 4th and 5th
9 12/02/25 71% 02nd Floor Internal Plumbing 100% Completed
floor.
03rd Floor Internal Plumbing 100% Completed
04th Floor Internal Plumbing 70% Completed
05th Floor Internal Plumbing 70% Completed

06th Floor Wall Conduiting 100% Completed


MEP Work-Completion of 6th, 7th, 8th and 9th 07th Floor Wall Conduiting 100% Completed
10 16/06/25 40%
floor. 08th Floor Wall Conduiting Work 50% Completed
06th Floor Internal Plumbing 50% Completed

MEP Work Completion of Lift m/c room, Above


11 20/06/25 0% Future Activity
Terrace & other misc. facilities

Approved by: Prepared by:


Name: Kallol Biswas Name: Ravendra Sharma
Designation: GM - Projects Designation: Planning Manager