Ceragon - Contractors Sub-Contractors and Suppliers Management
Ceragon - Contractors Sub-Contractors and Suppliers Management
SUPPLIER MANAGEMENT
This document is the property of Ceragon Networks Ltd. It is strictly confidential and may on no account be reproduced, copied
or divulged without prior authorization. A printed document is an uncontrolled copy of an electronic master.
Document Control Page
Document Contractor, Sub-contractors Classification Controlled
Name: and Supplier Management
Version Control
Version Date Author Change/Update Description Reviewed By
0.0 5th February Gloria Baha Implementation
2022
Distribution List
The purpose of this procedure is to ensure that all contractor(s), sub-contractor(s) and
suppliers employed by Ceragon Networks Ltd (hereafter Ceragon ), adhere to Ceragon
and Clients’ Absolute Rules, policies, procedures, SHEQ standards and all relevant legal
requirements, before any work commences.
2. SCOPE
3. REFERENCES
Document Title
Ceragon Absolute Rules (Client(s) Absolute Rules
Consequence Management Procedure
Non-conformance, Corrective and Preventative Action Procedure
SHE Self-assessment Questionnaire
Contractor/Sub-Contractor/Supplier’s Performance Form
Corrective Action Request
None
Responsibility Duty
Management Ensure compliance of this procedure is implemented and maintained
SHE Officer Providing all contractors, sub-contractors and suppliers with
Ceragon Absolute rules, Client’s Absolute Rules and
standards, policies, procedures etc.
7. PROCEDURE
d) On receipt of the SHE self-assessment Questionnaire, the SHE Officer will assess the
contractor/sub-contractor by using the ‘Contractor/Sub-Contractor/Supplier’s Performance
Form’. A score of minimum 80% needs to be obtained in order to qualify as an approved
contractor/sub-contractor.
g) In the event of any non-compliance to Ceragon ’s audit findings, the SHE Officer will raise
a Corrective Action Request form against the contractor(s)/sub-contractor(s)/supplier(s) to
complete as per the Non-conformance, Corrective and Preventative Action Procedure.
j) An internal site audit will be scheduled and conducted by the SHE Officer to confirm that
all information provided by the contractor/sub-contractor in the site SHEQ file is site
specific and that adherence to all Ceragon and Client’s requirements, procedures,
policies, client’s standards, HSMS etc. A score of minimum 60% needs to be obtained in
order to qualify as an approved contractor/sub-contractor.
n) The site supervisor shall always be present on site at all times to monitor health and
safety and to ensure that Ceragon and Client(s)’ Absolute Rules, policies, procedures,
standards, specifications and legal requirements are adhered to at all times.
8. RECORDS
9. REVISION STATUS
Pages
Date Revision Clause(s) Re- Revision Details Changed by
Number Amended Issued
First compilation of
18/05/2022 0 - -
document
The purpose is to evaluate contractor(s)/sub-contractor(s) and major suppliers for listing as Approved Suppliers to satisfy ISO
9001:2000, Clause 7.4.1.
PERFORMANCE
OWN (REFER TO KEY)
USING OUR AUDITED
NAME QUALITY
SYSTEM (Y) (YES/NO) DATE
SYSTEM (Y)
1 2 3 4 5 6 7
Note: List new contractor/sub-contractors for the period only and record any changes to the performance of those previously
listed.
Fully = 5 Pts
Adhering to Quality System
1. Partially = 3 Pts
Requirements
Not at all = 0 Pts
Yes with Records = 5 Pts
Quality Control (Inspection and
2. Yes Some Records = 3 Pts
Testing)
Yes No Records = 0 Pts
System in place with certificates proving Validity = 5 Pts
Calibration of Inspection, Measuring
3. System Partially in place = 3 Pts
and Test Equipment
System not in place no evidence = 0 Pts
NOTE: A Contractor/Subcontractor Close-out Report to be completed by the Project Manager/Site Supervisor at the end of the
project and the Contractor/Subcontractor’s performance to be summarised in the Contract Close-out Report