MONITORING PEKERJAAN SUTT 150 kV KUALA TUNGKAL - PELABUHAN DAGANG

Upd. 13-10-2023
No Tower KP-01 KP-02 KP-03 KP-04 KP-05 KP-06 KP-07 KP-08 KP-09 KP-10 KP-11 KP-12 KP-13 KP-14 KP-15 KP-16 KP-17 KP-18 KP-19 KP-20 KP-21 KP-22 KP-23 KP-24 KP-25
Type Tower Tapping BB+6 AA+6 AA+6 AA+9 BB+3 AA+6 AA+6 AA+6 AA+6 AA+9 BB+6 AA+9 AA+6 AA+6 AA+6 AA+6 AA+6 BB+6 AA+6 AA+9 AA+9 AA+6 BB+9 AA+6
Pondasi Ongoing Ongoing Ongoing Ongoing Ongoing
Lahan Bebas 225 225 400 225 225 225 225 225 225 225 225 225 225 225 225 400 225
K.pondasi 7 6 6 7 7 6 6 6 6 6 6 6 7 6 6 7 6 6 6 6 6 6 7 7
Jarak langsir 420 205 141 100 179 136 459 848 150 149 580 2025 1650 1255 1110 747 370 330 30 60 135 250 20 20
Pekerjaan Borpile 0/4 0/4 0/4 4/4 0/4
Pekerjaan Galian Pad 2/4
Bobok Pile 2/4
Setting Stub 1/4
Pembesian Pad & Ch
Pengecoran Pad & Ch
Timbunan
Final Check Pondasi

No Tower KP-26 KP-27 KP-28 KP-29 KP-30 KP-31 KP-32 KP-33 KP-34 KP-35 KP-36 KP-37 KP-38 KP-39 KP-40 KP-41 KP-42 KP-43 KP-44 KP-45 KP-46 KP-47 KP-48 KP-49 KP-50
Type Tower AA+6 AA+6 AA+9 AA+6 AA+6 AA+9 AA+9 BB+9 BB+6 CC+9 AA+6 AA+6 AA+6 AA+6 AA+9 AA+9 AA+6 CC+12 AA+9 AA+9 AA+6 AA+6 AA+6 AA+6 AA+6
Pondasi Ongoing Ongoing Ongoing
Lahan Bebas 225 225 225 225 225 225 225 225 225 400 225 225 225 225 225 225 225 400 225 225 225 225 225 225 225
K.pondasi 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 7 6 6 6 7
Jarak langsir 20 20 35 35 35 40 35 25 40 0 55 60 70 70 50 50 50 60 60 60 60 60 60 60 60
Pekerjaan Borpile 2/4 0/4 1/4
Pekerjaan Galian Pad
Bobok Pile
Setting Stub
Pembesian Pad & Ch
Pengecoran Pad & Ch
Timbunan
Final Check Pondasi

No Tower KP-51 KP-52 KP-53 KP-54 KP-55 KP-56 KP-57 KP-58 KP-59 KP-60 KP-61 KP-62 KP-63 KP-64 KP-65 KP-66 KP-67 KP-68 KP-69 KP-70 KP-71 KP-72 KP-73 KP-74 KP-75
Type Tower AA+6 AA+6 AA+6 BB+6 AA+6 AA+6 AA+6 AA+6 AA+6 AA+6 AA+6 AA+6 BB+6 AA+6 AA+9 AA+9 AA+6 AA+6 AA+9 AA+9 AA+6 BB+6 AA+6 AA+3 AA+6
Pondasi
Lahan Bebas 225 225 225 400 225 225 225 225 225 225 225 225 400 225 225 225 225 225 400 225 225
K.pondasi 6 6 6 6 6 6 6 6 7 6 1 7 1 1 7 7 7 3 6 7 2 7 2 2 6
Jarak langsir 60 60 25 85 65 60 65 65 70 60 60 55 60 0 195 115 300 85 0 50 100 0 50 110 30
Pekerjaan Borpile
Pekerjaan Galian Pad
Bobok Pile
Setting Stub
Pembesian Pad & Ch
Pengecoran Pad & Ch
Timbunan
Final Check Pondasi

No Tower KP-76 KP-77 KP-78 KP-79 KP-80 KP-81 KP-82 KP-83 KP-84 KP-85 KP-86 KP-87 KP-88 KP-89 KP-90 KP-91 KP-92 KP-93 KP-94 KP-95 KP-96 KP-97 KP-98 KP-99 KP-100
Type Tower AA+6 AA+6 AA+9 AA+9 AA+6 AA+6 AA+15 BB+6 AA+9 AA+9 AA+6 AA+6 AA+9 AA+6 AA+9 BB+9 AA+9 AA+9 AA+3 AA+9 AA+6 AA+6 AA+6 AA+6 AA+9
Pondasi
Lahan Bebas 225 225 225 225 225 225 225 400 225 225 225 225 225 225 225 400 225 225 225 225 225 225 225 225
K.pondasi 2 2 3 1 6 3 7 6 3 6 2 6 2 2 7 7 6 2 3 7 7 7 1 7 7
Jarak langsir 50 100 60 20 63 139 67 0 194 118 30 250 50 120 154 275 105 0 0 433 0 110 160 0 130
Pekerjaan Borpile
Pekerjaan Galian Pad
Bobok Pile
Setting Stub
Pembesian Pad & Ch
Pengecoran Pad & Ch
Timbunan
Final Check Pondasi

KP-105
No Tower KP-101 KP-102 KP-103 KP-104 KP-104 A KP-105
spesial
KP-106 KP-107 KP-108 KP-109 KP-110 KP-111 KP-112 KP-113

Type Tower AA+9 BB+6 AA+6 BB+15 BB+15 BB+0 -3 BB+0 AA+9 BB+6 AA+9 AA+6 AA+3 BB+12 DRD+0
Pondasi
Lahan Bebas 225 400 225 400 400 400 225 400 225 225 225 225 400
K.pondasi 7 7 6 6 6 6 6 6 2 6 7 3 6
Jarak langsir 0 125 70 75 0 80 20 75 160 275 30 25 140 130 0
Pekerjaan Borpile
Pekerjaan Galian Pad
Bobok Pile
Setting Stub
Pembesian Pad & Ch
Pengecoran Pad & Ch
Timbunan
Final Check Pondasi

: Lahan bebas (100) ` : Sondir ulang : On going

: Lahan Belum Bebas (14) : Selesai