NGM-OXY-ZZ-ZZ-MS-M-0001 Method Statement For Installation and Testing of Ducts and Accessories
NGM-OXY-ZZ-ZZ-MS-M-0001 Method Statement For Installation and Testing of Ducts and Accessories
NGM-OXY-ZZ-ZZ-MS-M-0001 Method Statement For Installation and Testing of Ducts and Accessories
Status Comment
A Accepted
Others
The RAMS documentation submitted by the subcontractor should include the following
RISK ASSESSMENTS Yes No PERSONAL PROTECTIVE EQUIPMENT Yes No
COSHH Yes No EMERGENCY ARRANGEMENTS Yes No
FULL DESCRIPTION OF METHODOLOGY AND MATERIALS, WASTE REMOVAL
Yes No Yes No
SEQUENCE OF WORK HOUSEKEEPING AND STORAGE
ACCESS / EGRESS Yes No ENVIRONMENTAL Yes No
OCCUPATIONAL HEALTH Yes No LOGISTICS Yes No
WORK AT HEIGHT Yes No TECHNICAL INFORMATION Yes No
COMMUNICATION/MANAGEMENT/
PLANT / EQUIPMENT/TOOLS Yes No Yes No
TRAINING
PERMITS Yes No Yes No
Please note – referring to the RAMS Pro Forma (SAF 072) will assist in what information is needed
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Proposed start date 10/06/2024 Duration of task As per the project requirement
Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures
Section G McLaren Site Specific HSE Safety Induction
Section H Welfare facilities
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used
Section L Temporary Works
Section M Inspection and Test Regime
Section N Communication/Toolbox Talks/Training Requirements
Section O Works Permits
Section P Environmental and Waste Management
Section Q Programme for the Works
Section R Housekeeping and Storage
Section S Working at Height
Section T Occupational Health
Section U Sequence of Works/Activities
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets
Appendix D Risk Assessments
Appendix E Technical Information
Appendix F Inspection and Test Plans
Appendix G Third Party competency/certifications
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Rev. No Date Reason for Amendment Amended By Signature Has this amendment been
(Name) briefed to the operatives
involved and have the
operatives signed the register?
P01 17/05/2024 Initial submission
This method statement has been prepared in conjunction with the following documents;
1. UAE Federal Law No. 8, chapter V, Article 91 of 1980.
2. United Arab Emirate Ministerial Order 337/2, Medical care to Workers
3. UAE Fire & Life Safety Code of Practice 2018.
4. UAE Ministerial Order No. 32 of 1982.
5. Federal Environmental Authority Law No.24/1999 and its supplements.
6. Federal Law No. (20) of 1991 Concerning the Civil Aviation Law.
7. Ministerial Resolution 688 of 2013, Regarding Fixing of Working Hours During Summer
8. Dubai Municipality Code of Construction Safety Practice, 2007-2011 edition
9. Dubai Municipality Technical Guidelines
10. Dubai Development Authority HSE Regulations
11. Local order No. 61 of 1991on Environment Protection Regulation in the Emirates of Dubai.
12. Articles (3,4,5,7) Local Law No. 21/2005 (Waste Management)
13. Local Order No. 11 of 2003 concerning Public Health & community Safety in the Emirate of Dubai
14. ISO 45001:2018, ISO 14001:2015 ISO 9001:2015
15. McLaren’s Integrated Management System Policy Statement
16. McLaren Management Procedures (MMP) and Function Procedures
17. McLaren’s site specific SHEQ Plan
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Existing Services
As per current information, there are no service with the site boundaries.
Not applicable
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly Point,
which is indicated on the site logistics drawing, as indicated by the symbol below. A roll call will be taken and
registers checked to ensure that everyone is accounted for. No one will be allowed to leave the assembly point
until the Emergency Response Controller confirms that it is safe to do so.
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available within the
First Aid Room and in the Main Office Reception.
On completion of the HSE induction, those involved in this activity will be briefed on the contents of the RAMS
by their respective Site Engineer or Supervisor. They will then be required a sign a RAMS Briefing Register (SAF019
UAE) confirming that they have been briefed and that they fully understand the RAMS and what is expected from
them during the execution of the works.
Any operative who will be operating any plant or equipment will be required to produce a copy of their Dubai/
Abu Dhabi Municipality/EIAC approved competency certificate/card and proof of health to enable McLaren to
issue them with the Plant Operators Authorisation (SAF023 UAE).
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
1. Hand tools
2. Power tools
*Note: All relevant competency certificates to be submitted to HSE Manager/Eng./Advisor prior to start of any
activity.
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description of Training Has the Training been If not, when will be
completed? (Yes/No) completed (Date)
1 Manual Handling No, training to be provided prior to
commencement of activity
2 COSHH HANDLING No, training to be provided prior to
commencement of activity
3
4
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren
7 Permit to Work with Ladders, steps/scaffold McLaren
8 Permit to Work at Height McLaren
9 Permit to Work – Electrical above 110V McLaren
10 Permit to Work with COSHH Items McLaren
11 Permit to Work at External Face of The Building McLaren
12 Permit for Removal of Existing Fall Protections McLaren
13 Permit for Pressure Testing McLaren
14 Other Permit
Any other permits if required to be added
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
1. Metal
2. Plastic
3. General
4. Inert
5. Food waste
6. Hazardous
7. Wood Waste
Due to the nature of the works and the current site conditions, water shall be sprayed onto dirt/sand roads so
as to minimize dust pollution.
Where any plant is used, drip trays shall be placed underneath to catch any spilled oils or fuels. Oils and fuels will
be managed in accordance with the MSDS and the site Waste Management Plan.
All hazardous liquids must store in suitable, labelled containers with secondary containment to prevent ground
and water contamination.
Emergency spills kits must be available where any hazardous material is used.
Section Q- Programme for the Works.
The works will commence and will continue as per the project requirement.
Combustible materials will be carefully managed and monitored in order to reduce the risk of fire.
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Item Description Preventative Measures, (see also within the Risk Assessments)
1 Safety Critical Roles Anyone identified as safety critical (i.e. operators, riggers,
scaffolders, banksmen etc.) must have a medical check-up before
starting work
2 Bad Back/sprain due to A manual handing assessment will be carried out for all activities and
improper Manual handling all Operatives will receive Manual Handling training
3 Hand/Arm Vibration Exposure Action Values (EAVs) will be calculated for all vibration
activities. Where required, job rotation will be put in place and
recorded
4 Construction dust Roads shall be watered to minimise dust and housekeeping to be
carried out regularly.
RPE shall be provided for those at risk from hazardous dust
5 Noise Noise values will be monitored. Where required, job rotation will be
put in place and recorded. Where it is not possible to control noise,
PPE will be provided
6 Sun & Heat Sun creams will be provided for those that require it.
Drinking water and electrolyte additives will be provided.
Clothing shall cover legs and arms, gloves will be worn.
Summer Working Plans
7 Skin PPE shall be provided as required by MSDS
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
All the materials received as site shall be handled and stored as per the manufacturer’s
recommendation.
All materials received at site shall be inspected by Consultant representative, ensure that the
material as per the approved material submittal in terms of their make/ model, type and country
of origin.
Pre installation
Safety Induction and Tool-Box-Talk before the start of work.
All materials, drawings and documentation related to a particular section of works should
be checked by the Project Engineer prior to commencement of work and ensure that they
are the correct type as reviewed and approved by the Consultant.
All ducts and accessories shall be identified, marked and segregated for respective areas as
per approved drawings and schedule.
Title: INSTALLATION OF DUCTS AND ACCESSORIES Ref. No: NGM-OXY-ZZ-ZZ-MS-M-0001
Project: Nad Al Sheba Gardens Mall Dubai Rev. No: P01 Suitability Code: S3
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Installation of PI Ducts
Pre insulated duct work will be used as per the material submittal and approved shop
drawing.
Factory fabricated duct is interconnected with invisible Chair flange and H bayonet.
All the joints are closed with Aluminium tape.
Duct joint corners are capped off with corner plate.
Installation of dampers
Install dampers as per the approved shop drawing
Make sure damper handle is accessible and there is no obstruction
Install Fire dampers on every fire rated walls required as per NFPA.
Provide Retaining angle for fire damper sleeves on wall.
Record UL reference number prior to installation.
Ensure Fusible link is properly working.
Provide duct access door for all the fire dampers.
Ensure Actuators and handles are accessible around motorized dampers
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX A
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX B
Nad Al Sheba gardens Mall Dubai UAE
CRISIS PLAN
Upon an incident, being discovered the first member of McLaren’s staff or the site operative
1.
discovering the incident shall inform the Project Manager and HSE department by Project
Emergency no- 0502559731
The Safety Officer and the First Aider(s) are to attend the scene.
2.
Both the Safety Officer and the First Aider are to assess the situation, raise the alarm if required/
3.
contact the relevant Emergency Team members and put in place the relevant systems to end/deal
with the emergency.
In the case of an emergency where the site needs to be evacuated and the alarm is raised, the Fire
4.
Wardens will ensure the site is evacuated to the Assembly Point(s), the Fire Wardens and the Safety
Officer are to ensure all trades are gathered at the assembly point and liaise with supervisor to
account for all operatives - no person should leave site.
The Safety Officer or the First Aider will brief the Project Manager (Or his Deputy) on the Emergency
5.
and inform him/her of which emergency services are required. The Project Manager (Or his Deputy)
contacts the Emergency Services.
The Project Manager calls all relevant McLaren staff.
6.
Both the Safety Officer and the first Aider waits for the emergency services to guide them to the
7.
incident scene.
Once emergency services arrive, The Project Manager will telephone the relevant authorities, i.e.
8.
the HSE/Client’s Safety Advisor/McLaren’s Operations & QHSE Manager.
Both the Safety Officer and the first Aider keep trades informed of the situation and releases trades
9.
to return to work or leave site only when emergency services or The Project Manager instruct that
it is safe to do so, and all names of witnesses are recorded.
The Project Manager/ Construction Manager/ Safety Officer are to ensure the scene is made safe
10.
and secured/ cordoned off as to prevent tampering and then arrange for photographs of the scene
to be taken.
11. A full investigation of the Incident is to be carried out, with a written report being submitted the
QHSE Manager and Operations Director, as soon as practicably possible after the incident, including
all witness statements, photos of the scene, induction and method statement records,
recommendation to prevent a re-occurrence and what action has been taken since the incident
taking place.
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Emergency Flowchart
Injury
Incident
(Injured Person (IP))
Initially
Yes
No thought
Do not move the IP
serious
Inform HSE project Make area safe and restrict Make area safe and restrict
management team access access
No Yes
Notify Client
Call ambulance
First Aider to Representative &
access IP and Enforcing Authority
decide
treatment
required Handover patient to
paramedic
IP returns to work
IP forward medical
following First Aider
report to HSE Team
instructions
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX C
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Manufacturer/Supplier: Carling Fire research and technologies FZE Tel No: + 971 434035516
Application
Duct installation
& Use
Note - These instructions only apply to the method of application and location stated above.
Eye irritation
TYPES OF EXPOSURE
Eye
Inhalation Skin x Injection x x Ingestion x
Contact
Corrosive Oxidising Flammable Env. Explosive Acute Harmful / Serious Gas Under
Toxicity Irritant Health Pressure
Hazard
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
x x x x x
SKIN CONTACT Wash off with plenty of water and soap immediately
In case of contact with eyes, rinse immediately with plenty of water and seek immediate
EYE CONTACT
medical attention.
To be disposed of in compliance
with existing regulations.
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX- D
RISK ASSESSMENT
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX-E
TECHNICAL INFORMATION
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX-F
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
1.1 Pre-Qualification document SC/QAQC/PM/CON Document As per Specification Initial PQ document submittal H H NA
Activities
Pre-Start
plian
Complianc Com
ce
4.1 Inspection SC/QAQC/PM/CON Visual/document As per project specification Completion WIR, Highlighted Area, Photos H I I
Final
4.2 As Built Information SC/QAQC/PM/CON Visual/document As per shop drawing Completion WIR, Highlighted Area, Photos H R R
Prepared By (Sign):
Date: 17-05-2024
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
3 check and ensure that the Bop are as per the approved shop drawing
10 Sound attenuator, flexible duct and access panel are installed as per
approved shop drawing.
Checked by :
Name :
Signature :
Date :
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024
APPENDIX-G
Prepared By: SWALIH SULAIMAN Approved By: Mahin Abubacker Rev. Date: 17/052024