FRM-PRC-009 REV00 Vendor Evaluation Form
FRM-PRC-009 REV00 Vendor Evaluation Form
FRM-PRC-009 REV00 Vendor Evaluation Form
xls PRC-FRM-009
Criteria Definition
Handling Performance Number of package that failured divided by total number
of package deliveries by vendor.
Safety Awareness Number of safety issue that occured during delivery
Claim Acknowledgements Claim that due and unpaid divided by total claim to vendor
Price Competitiveness Lowest quoted price of all vendors divided by appraised vendor
Invoicing Late Invoice divided by total invoice per month
#DIV/0!
#DIV/0! #DIV/0!
Fleet Readiness
Failure =
Total Delivery =
Overall Performance
Handling Performance
100.00%
Invoicing #REF!
50.00%
0.00%
Claim Acknowledgements
Monthly Result of
Month Vendor Performance Control
January 97.00 A- YELLOW FLAG
February 98.00 A CONTINUE RELATIONSHIP
March 98.00 A CONTINUE RELATIONSHIP
April 98.00 A CONTINUE RELATIONSHIP
May 98.00 A CONTINUE RELATIONSHIP
June 80.00 D SUSPENSION 12 MONTH
July 100.00 A CONTINUE RELATIONSHIP
August 100.00 A CONTINUE RELATIONSHIP
September 100.00 A CONTINUE RELATIONSHIP
October 90.00 B 2nd WARNING
November 90.00 B 2nd WARNING
December 90.00 B 2nd WARNING
AVERAGE 94.92 B+ 1st WARNING