Chapter 7 Long Activity
Chapter 7 Long Activity
13–1
Questions:
1. Draw Gantt chart
2. Calculate PV,EV,AC by considering the progress report
3. Calculate scheduled variance(SV)
4. Cost variance(CV)
5. Scheduled performance index(SPI)
6. Cost performance index(CPI)
7. Calculate estimated cost at completion (EAC)
8. Draw cost/schedule graph showing PV,EV,AC,SV,CV,EAC,BAC
13–2
Step 1: Draw Gantt Chart
1
A 0 1
B 0 2
2
C
1 3
2
D 3 5
0 1 2 3 4 5
A 0 1
2 $100
B 0 2
2 $200
C
1 3
2 $100
D 3 5
0 1 2 3 4 5
1
Sun Mon Tue Wed Thu
2 $100
80% , cost $110
B 0 2
2 $200
20% , cost $30
C
1 3
$100
2
D 3 5
0 1 2 3 4 5
1
Sun Mon Tue Wed Thu
Progress Report: Project started on Sunday, and we received the following progress repot at the
end of Monday (day2)
13–5
Step 4 : Deriving PV, EV, AC
1 $50
100% , cost $60
A 0 1
2 $100
80% , cost $110
B 0 2
2 $200
20% , cost $30
C
1 3
$100
2
D 3 5
0 1 2 3 4 5
1
Sun Mon Tue Wed Thu
A B C
(BCWS) PV : 50 + 100 + 100 = $ 250
(BCWP)EV : 50 + 80 + 40 = $170
(ACWP)AC: 60 + 110 + 30 =$ 200
13–6
13–7
Step 5 : Calculating Variances (SV,CV )and index values (SPI,
CPI) using PV, EV and AC
A B C
(BCWS) PV : 50 + 100 + 100 = $ 250
(BCWP) EV : 50 + 80 + 40 = $170
(ACWP) AC: 60 + 110 + 30 =$ 200
13–8
Forecasting Model: EACf
13–9
Step 6: Forecasting Model: EACf
450- 170
= _____________
= $ 329.4
0.85
= 329.4+200= $ 529.4
13–10
&600
EAC= $529.4
&500
BAC= $450
&400
&300
$250
$200
SV=- $80
&200
CV=- $30
PV
$170
&100
0 1 2 3 4 5
13–11
Chapter 7 Class Activity -2 (Revision)
Consider the activity table and progress report :
Activity Predecessor Time(days) Estimated Cost
A None 1 $ 90
B None 2 $120
C A 2 $ 200
D B 1 $ 60
E C 1 $100
Progress Report
The project started on Sunday and we received the following progress report at the end of Tuesday (day 3):
Activity A is Completed 100%, and the cost incurred is 70$
Activity B is Completed 100%, and the cost incurred is $110
Activity C is completed 70% and the cost incurred is $90
Activity D is completed 90% and the cost incurred is $ 50
13–12
Questions:
1. Draw Gantt chart
2. Calculate PV,EV,AC by considering the progress report
3. Calculate scheduled variance(SV)
4. Cost variance(CV)
5. Scheduled performance index(SPI)
6. Cost performance index(CPI)
7. Calculate estimated cost at completion (EAC)
8. Draw cost/schedule graph showing PV,EV,AC,SV,CV,EAC,BAC
13–13
Step 1: Draw Gantt Chart
1
A 0 1
2
B 0 2
2
C 3
1
1
D 2 3
1
E 3 4
4
0 1 2 3 4 5
A None 1 $ 90
B None 2 $120
C A 2 $ 200
D B 1 $ 60
E C 1 $100
13–14
Step 2: Placing Estimated Cost
1 $90
A 0 1
$120
2
B 0 2
2 $200
C 3
1
1 $60
D 2 3
$100
E 3 4
0 1 2 3 4 5
A None 1 $ 90
B None 2 $120
C A 2 $ 200
D B 1 $ 60
E C 1 $100
13–15
Step 3: Showing Progress Report on Gantt Chart
1 $90
100% , cost $70
A 0 1
$120
2
100% , cost $110
B 0 2
$200 70% , cost $90
2
C 3
1
1 $60 90% , cost $50
D 2 3
$100
E 3 4
0 1 2 3 4 5
Progress Report
The project started on Sunday and we received the following progress report at the end of Tuesday (day 3):
Activity A is Completed 100%, and the cost incurred is 70$
Activity B is Completed 100%, and the cost incurred is $110
Activity C is completed 70% and the cost incurred is $90
Activity D is completed 90% and the cost incurred is $ 50
13–16
Step 4 : Deriving PV, EV, AC
1 $90
100% , cost $70
A 0 1
$120 100% , cost $110
2
B 0 2
$200 70% , cost $90
2
C 3
1
1 $60 90% , cost $50
D 2 3
$100
E 3 4
0 1 2 3 4 5
A B C D
(BCWS) PV : 90 + 120 + 200 + 60= $ 470
(BCWP) EV : 90 + 120 + 140 + 54 = $404
(ACWP) AC: 70 + 110 + 90 + 50 = $ 320
13–17
Step 5 : Calculating Variances (SV,CV )and index values (SPI,
CPI) using PV, EV and AC
(BCWS) PV = $ 470
(BCWP) EV = $404
(ACWP) AC = $320
13–18
Step 6: Forecasting Model: EACf
570- 404
= _____________
= $ 131.7
1.26
= 131.7+320= $ 451.7
13–19
$600 BAC= $570
$ 500
EAC= $451
SV=- $66
PV $470
$ 300 $320
$ 200
$100
0 1 2 3 4 5
13–20