Mokshith WO Status
Mokshith WO Status
PY Section
UoM Rate
Activity Description
Main Line Civil Works mtr 1,774.50
Mainline Stringing & Welding - 20" mtr 1,453.00
Field Joint Coating - 20" mtr 151.00
Lowering- 20" mtr 107.00
Tie-in HDD, LFP, BVS, terminal & 20" Mainline Valve installation mtr 307.00
Total>>>
AP Section
UoM Rate
Activity Description
Main Line Civil Works mtr 1,775.00
Mainline Stringing & Welding - 20" mtr 1,453.00
Field Joint Coating - 20" mtr 151.00
Lowering- 20" mtr 107.00
Tie-in HDD, LFP, BVS, terminal & 20" Mainline Valve installation mtr 307.00
Total>>>
Current WO Billed Balance Final Bill
Qty Amount Qty Amount Qty Amount Qty
800.25 1,420,043.63 671.02 1,190,726.76 129.23 229,316.86 135.15
1,349.15 1,960,314.95 1,237.61 1,798,242.97 111.54 162,071.98 140.29
1,253.00 189,203.00 1,105.31 166,901.96 147.69 22,301.04 361.59
1,185.30 126,827.10 708.08 75,764.45 477.22 51,062.65 206.52
1,045.00 320,815.00 - - 1,045.00 320,815.00 -
Total>>> 4,017,203.68 3,231,636.15 785,567.53
Current WO Billed Balance Final Bill
Qty Amount Qty Amount Qty Amount Qty
1,659.02 2,944,760.50 998.51 1,772,355.25 660.51 1,172,405.25 35.96
2,035.16 2,957,087.48 1,145.08 1,663,802.69 890.08 1,293,284.79 46.84
1,283.70 193,838.70 1,089.95 164,582.60 193.75 29,256.10 49.80
1,850.34 197,986.38 994.50 106,411.50 855.84 91,574.88 62.31
1,134.90 348,414.30 - - 1,134.90 348,414.30 -
Total>>> 6,642,087.36 3,707,152.04 2,934,935.32
Final Bill Difference
Amount Qty Amount
239,818.80 -5.92 -10,501.93
203,847.91 -28.75 -41,775.93
54,599.94 -213.90 -32,298.90
22,098.18 270.70 28,964.47
- 1,045.00 320,815.00
520,364.82 265,202.71
Final Bill Difference
Amount Qty Amount
63,821.90 624.55 1,108,583.35
68,065.78 843.23 1,225,219.00
7,519.50 143.95 21,736.60
6,667.60 793.53 84,907.28
- 1,134.90 348,414.30
146,074.78 2,788,860.54