ASSIGNMENT 4
SUBMISSION DATE 17 MAY 2024 (1300HRS)
Q.1Design an approach channel for water flowing at the rate of 22000gpm. The channel will be
lined with bricks n value 0.01. Assume velocity of flow 0.75m/s and depth to breadth ratio D: B =
1: 2.
Q .3 Using the following data, design a pumping station to pump sewage against a head
of 15.0m and conveyed it to a treatment plant located 400m away from the pumping
3
station. The peak hourly wastewater flow rate is 12000m /d.
Time (hr) 2 4 6 8 10 12 14 16 18 20 22 24
Q (m3/hr) 120 450 486 1170 1710 1320 1122 966 348 468 372 234