Professional Documents
Culture Documents
Swa 2
Swa 2
OWNER PHCCI
CONTRACTOR SBK CONSTRUCTION
SUBJECT STATEMENT OF WORK ACCOMPLISHMENT
AS OF 10 MAY 2024
1,939,895.37
% % work Amount
SECOND FLOOR 100% 696,289.68 35.89% accomplished Acommplished
Demolition of Existing Wall 26,540.00 1.37% 100% 26,540.00
Ceiling 127,251.56 6.56% 40% 50,900.62
Tiling @ Floor 232,531.75 11.99% -
Tiling @ Stairs 78,150.07 4.03% -
Wall Tiling @ Common CR 29,309.05 1.51% 50% 14,654.53
CR Partition & Fixtures 12,540.00 0.65% -
Waterproofing @ CR 8,510.40 0.44% 60% 5,106.24
Painting @ Interior 32,150.80 1.66% 20% 6,430.16
Painting @ Exterior 41,750.10 2.15% 10% 4,175.01
Carpentry & Joinery 54,655.95 2.82% -
Glass Works / Window 52,900.00 2.73% -
In view of the foregoing, we would like to bill the amount of P(127,995.70) ONE HUNDRED TWENTY SEVEN THOUSAND, NINE
HUNDRED NINETY FIVE PESOS AND SEVENTY CENTAVOS.
YOURS TRULY,
RUEL S. RAGANAS