ABU DHABI GAS INDUSTRIES (GASCO)

FEED/DETAILED DESIGN ENGINEERING STUDY FOR REPLACEMENT OF 7G-116 A&B FRESH FIRE WATER PUMPS

LIST OF DELIVERABLES WITH MAN-HOURS

DISCIPLINE : ELECTRICAL
Litwin Ref : ELEL130218 REV.0 (01/09/2013)

MAN-HOURS

IN-HOUSE OUTSOURCE
Sl. No. DESCRIPTION QTY.(Lot) TYPE SIZE

Engineer CADD TOTAL Engineer CADD TOTAL

NON-DELIVERABLES
1.0 SITE VISIT / DATA COLLECTION

1.1 Site Visit 20 20 0

1.2 Discussion with Client / data collection 20 20 0

I SUB-TOTAL 40 0 40 0 0 0

ENGINEERING DELIVERABLES
2.0 DOCUMENTS 0

2.1 Design Basis (Electrical input) 1 Doc A4 8 8

2.2 Electrical load list/summary 1 Doc A4 15 15

2.3 Data sheet for MV motors 1 Doc A4 10 10

2.4 Data sheet for MV & LV cables 1 Doc A4 15 15

2.5 Specification for Bulk materials including MV &LV cables 1 Doc A4 15 15

2.6 Adequacy check for MV switchgear 1 Doc A4 25 25

2.7 Cable Sizing calculation 1 Doc A4 10 10

2.8 Cable schedule 1 Doc A4 10 10

2.9 Lighting calculation 1 Doc A4 10 10

2.10 Relay setting schedule 1 Doc A6 30 30

2.11 MRQ for HV&LV cables 1 Doc A4 15 15

2.12 MRQ for bulk materials 1 Doc A4 15 15

2.13 Bill of materials 1 Doc A3 15 15

2.14 Cost estimate - Electrical input 1 Doc A4 15 15

2.15 EPC scope of work- Electrical input 1 Doc A4 10 10

3.0 DRAWINGS 0 0

3.1 Demolition drawing(SLD,Cable schedule,cable routing etc) 2 Drg. A3 10 20 30

3.2 Single Line Diagram- MV Switchboard 1 Drg. A3 10 15 25

3.3 Cable routing Layout 1 Drg. A3 10 20 30

3.4 Earthing layout 1 Drg. A3 10 20 30

3.5 Lighting Layout 1 Drg. A3 10 20 30

3.6 Electrical Tie-in List 1 Drg. A3 10 10 20

3.7 Typical Installation drawings 1 Drg. A3 10 20 30

3.8 Interface Diagram 1 Drg. A3 10 20 30

II SUB-TOTAL 298 145 443 0 0 0

VENDOR DOCUMENT REVIEW


0 0 0

0 0

III SUB-TOTAL 0 0 0 0 0 0

CONSTRUCTION SUPPORT
0

0 0

IV SUB-TOTAL 0 0 0 0 0 0

GRAND TOTAL 298 145 443 0 0 0

ACTIVITIES
Inter discipline check 10 10

V SUB-TOTAL 10 0 10 0 0 0

Drafting 145 0
Sr. Engineer 92 0
RESPONSIBILITY SPLIT Engineer 216 0
NOTES:
1) Cathodic Protection is not envisaged hence not considered

2) Technical Bid Evaluation is not considered.

3) Power System Study is not envisaged and is not considered for this project