Earthing Inspection Check List
Earthing Inspection Check List
Project:
Client:
Consortium:
Contractor:
Has the formation level been achieved as per the approved shop
6
drawings?
Has the Tool Box Training been delivered to QA/QC Personnel and
site engineers?
10
Have the earth rods (if required) are installed as per the approved
shop drawings?
12
Have the earth mesh been laid as per the approved design and shop
drawings?
15
Has the earth mesh been feasibly executed to allow for proper
connection with the next section of earthing system?
16
Page 1 of 16
INSPECTION & TEST PLAN FOR GRID EARTHING AND BONDING
Has the supplier provided special tools to carry out
17
Exothermic welding?
Have the earth rods been made up of low carbon steel with
20
copper molecularly bonded?
Has the location of the earth rod been checked as per the Shop
22
drawings?
Are the risers running vertically throughout the base slab Within
25 PVC pipe sleeve of adequate diameter and length?
Page 2 of 16
INSPECTION & TEST PLAN FOR GRID EARTHING AND BONDING
Page 3 of 16