Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

INSPECTION & TEST PLAN FOR GRID EARTHING AND BONDING

INSTALLATION CHECKLIST FOR GRID EARTHING AND BONDING

Project:

Client:

Consortium:

Contractor:

# DESCRIPTION OF ACTIVITIES YES NO N/A COMMENTS

Has the specialized subcontractor been


1
approved?

Are the latest approved shop drawings the latest revision


2
(Showing compartmentalization)?

3 Are all materials identified, approved and available?

Have all materials been immediately inspected after


4
unloading?

Were materials being stored in shaded area in their original


5
package horizontally?

Has the formation level been achieved as per the approved shop
6
drawings?

7 Have the formation level been compacted with gravel base?

8 Have the excavation and supporting work been completed?

Has the necessary length of copper conductor been left to have


proper connection with the next stage of earthing system?
9

Has the Tool Box Training been delivered to QA/QC Personnel and
site engineers?
10

Are the equipments ready to measure the resistance value of earth?


11

Have the earth rods (if required) are installed as per the approved
shop drawings?
12

Have the exothermic welding process been adopted on site?


(without any external source of heat and current)
13

Have the supplier provided the earth meshes of bare copper


Conductor 120mm2 in rolls?
14

Have the earth mesh been laid as per the approved design and shop
drawings?
15

Has the earth mesh been feasibly executed to allow for proper
connection with the next section of earthing system?
16

Page 1 of 16
INSPECTION & TEST PLAN FOR GRID EARTHING AND BONDING
Has the supplier provided special tools to carry out
17
Exothermic welding?

Have the graphite mould been used to connect the


18
Exothermic welding?

Have the same exothermic welding procedures been adopted for


19
the connection between earth meshes & rods?

Have the earth rods been made up of low carbon steel with
20
copper molecularly bonded?

Have the earth rod thickness been checked to be minimum


21
0.25mm?

Has the location of the earth rod been checked as per the Shop
22
drawings?

Have the length and diameter of the earth rod been


23
Checked as per approved drawings ?

Has the earth pit been executed of minimum internal


24 diameter ? Earth pit type precast: is it square or circular?

Are the risers running vertically throughout the base slab Within
25 PVC pipe sleeve of adequate diameter and length?

Page 2 of 16
INSPECTION & TEST PLAN FOR GRID EARTHING AND BONDING

Page 3 of 16

You might also like