TABEL PERHITUNGAN HARGA SATUAN PEKERJAAN PLAT LANTAI KONVENSIONAL

No Pekerjaan Sat Koe Harga Jumlah Harga


a b c d e f
PEKERJAAN BETON (M3)
Air Ltr 215 Rp 55 Rp 11,825.00
Semen Porland Kg 413 Rp 1,400 Rp 578,200.00
Kerikil M3 1 Rp 270,000 Rp 275,670.00
Pasir Beton/ Cor M3 0.681 Rp 275,000 Rp 187,275.00
Pekerja OH 2 Rp 105,000 Rp 173,250.00
Tukang Batu OH 0.275 Rp 130,000 Rp 35,750.00
Kepala Tukang OH 0.028 Rp 140,000 Rp 3,920.00
Mandor OH 0.083 Rp 150,000 Rp 12,450.00
Total Harga (Rp) Rp 1,278,340.00
Overhead dan Profit (10 %) Rp 127,834.00
Harga Satuan Pekerjaan (Rp) Rp 1,406,174.00

RAB PELAT KONVENSIONAL


Vol
No Jenis Sat Harga Satuan Harga Total Jumlah
Total
Beton M3 Rp 1,406,174.00 1 Rp 1,406,174.00
1 Beugesting Lbr Rp 433,700.00 1 Rp 433,700.00 Rp 1,852,499.92
Pembesian Kg Rp 12,625.92 1 Rp 12,625.92

RAB PELAT LANTAI BONDEK


No Jenis Sat Harga Satuan Vol Harga Total Jumlah
Beton M3 Rp 1,406,174.00 1 Rp 1,406,174.00
1 Bondek M2 Rp 160,000.00 1 Rp 160,000.00 Rp 1,680,812.45
Wiremash Lbr Rp 114,638.45 1 Rp 114,638.45

Selisih Total RAB


Total RAB Pelat Konvensional - Total RAB Pelat BONDEK
= 1,852,499.92 - 1,680,812.45
= 171,687.47