BRP409 Mi Sheet
BRP409 Mi Sheet
installation manual
Controller
Blue
connections.
MCPCB
Blue
Red
+
Connector -
Black
All the terminals are clean, rust free and carbon free before making connections.
Black
+- Petroleum Jelly is put on the thimbles of Battery connection wire after making the
Red connections
+ -
Battery For mulitple PV connections please follow the circuit label diagram.
For mulitple Battery connections please follow the circuit label diagram.
Red
+ -
System mounted on the pole and Panel oriented as specified for your geographic
Battery
location
Measure the battery voltage and specific gravity before making the connections.
Battery voltage should be 12V & gravity should be 1.2
Circuit Diagram
(Twin Battery & Panel) In battery, cap should be replace with Waterlevel indicator/Bent plug.
PV Panel 1 PV Panel 2
- + - + Luminaire
+ Blue
MCPCB
- Blue Red
+
-
Black
JunctionBox
Battery Disposal:
Black
+- Battery contains poisonous (lead) and corrosive (electrolyte) materials. Care must be
Red
taken when disposing damaged batteries.
+ - + -
Battery-1 Battery-2
Battery usage:
Batteries must be installed within 3 months of supply, failure to do this may require
additional charging before putting the system into operation.
P
HYBRID-ADDITION
Installation Instruction
1 2
Hybrid AC Charger is a box of the sorts Take the Panel wire to the top through
the Pole and mount the Junction Box on Solar LED Street Lighting
shown below, three connectios are to
be made in the following sequence the Panel Mounting Bkt or PAAB with the
1) Battery Connection help of 2 M4 screws
2) Panel Connection SOLAR
3) Mains Connection
Junction Box shown
For safety reasonsMake the Panel mounted on the PAAB
connections in the END
Type : BRP409
3
Make the Panel Connections inside the
Junction Box as shown and after that
close back the JB cover by tightening
the screws
Voltage : 12V/24V DC (Refer individual luminaire
type label for input voltage rating)
Wire going to the Panel
8 1
P
17 18
The final assembly looks like this For Twin mounting, PAAB will change
from universal to TWIN one and rest of
the components used will be 2 in No,
Dimensions For both Top and Bottom each.
Mounted.
Also showing both type of
Battery Boxes The mounting steps to be followed are
same and have to be followed for each
Luminaire individually.
610
Provision for two glands and two
20
Installation
19 20
Mounting Position: Horizontal The final TWIN mounted assembly Cable Information
Pole Height: 4m to 7m (Varies with looks like this (Cable used by customer
Product) Unless Otherwise specified)
2 7
P
13 14 1 2
Take the battery box system to the pole
Take off the top cover of the Battery box and mount as shown below Ensure that you have received the Familiarity with the major components
using the Allen keys.
material as per the system and all the
This Battery Box can items mentioned in the invoice are 1. Luminaire
be mounted at ANY present
Height on the Pole.
Here shown for the this or any of the other three
shown on the front page
Top Mounting.
Check boxes are not open and that with cable attached
Mount at 1.2m from the items are undamaged
Ground for the Bottom
Mounting using same Check hardware count against the
process as Top Hardware List packed with the items 2. PV Panel
mounting.
Check-nuts
3. Battery
Pole
4. Battery Box GP Sheet
P
OR
Ensure the Foundations are done as
Use check-nuts and washer per recommendation and cured Polymer
as shown below. properly before installation
15 16 3 4
Take the Battery to the Battery Box and Make the Battery connections as per the
put in the Battery box as shown. color coding of wires and labels on them. Panel Mounting Arrangement
Put petroleum jelly on the terminals after Opening the Boxes gives following items
making the connections.
Luminaire mounting Sleeve
Put back the top cover of the battery box and clamp
and tighten the Allen screws
6
3
P
5 6 9 10
Take the Luminaire and pass its cable 1) Take Out Panel Wire through PAAB, Now place the C-Channel on the top the Mount the Panel on the PAAB as shown
through the luminaire mounting sleeve as use gland structure made in previous step and below using 2Nos of
shown. tighten with the help of M6 screws and M8 Bolts, nuts, washers and spring
nuts (total 8 Nos). Use washers and washers. Use a tightening torque of 8N-m
check nuts everywhere.
Angle adjustment bolt.
The Panel can be mounted at
three positions: 20 (South
India), 30 (Middle India) and 40
(North India) degrees with the
Take out the cable through horizontal. Use one of these
a hole provided here three holes accordingly.
4) Take Out the Note: If this angle structure is already Adjuct by rotating LMS
around the PAAB and by
Lumianire cable as welded together, this step would not be tighthening these screws
shown needed
7 8 11 12
Now make the Battery and Panel Lay the PV Panel upside down, place the Take the entire assembly to the top of the Fix the battery box with the fixture as
Connections. Refer circuit diagram for angle bkts and tighten using 6 Nos of M6 Pole and slide it down on the pole shown below, with the help of 4 Nos of
details. screws and nuts at the positions maked M8 bolts and nuts, use washer.
Tighten the assembly using 6 Nos of M8
by circle. Use plain washer, spring
The system looks like this after bolts. Use Check nuts as shown.
washer, rectangular washer and check
connections
nuts as depicted
Check nut
side view
Battery Connections:
Red and Black wires
(Use proper insulation at joints) Caution: Pull the panel
cable and the connectors
up, so that pole Top does
not cut the cables
Panel Connections: For Top Mounting, take out the Battery cable through
the Hole A Keep this hole on this side
Yellow and Blue wires
(Use proper insulation at joints)
4 5
P
Installation Instruction
Dimensions
BRP 409 Street Lighting Luminaire
203
45 9
416 75
92
Installation
IP Classification : IP 66
Min.60 Net Weight : 2.7kgs
O 28 O40
L N
Fix toggles
! Notice:Correct connection for polarities
Earthing is absolutely must
Front Cover
3 The front Cover will open as 4 Allow the incoming cable to pass 9 Remove the polythene over 10 Luminaire is ready for use.
shown. through the gland and tighten it front diffuser/ glass.
with spanner
Remove
5 Fix the street light over the pole 6 Cut the wire sheath as per the size 11
and tighten the bolts. with wire cutter and strip the wires !
Tightening Torque: 8Nm as recommended.
Tighten the checknuts 8 CAUTION
9
after the bolts are 1. Ensure Earthing is connected. Improper Earthing will cause Luminaire failure.
LN
tightened. 20
3. Cable Entry gland should be properly tightened.
incoming cable 4. Product should be operated between 140-270V a.c.
5. Use Surge protection (upto 10kV) to protect against surges/Use Type B+C
surge type SPD in distribution box to arrest switching and lighting surges