METHOD STATEMENT

FOR SUPPORT AND HANGER

1. Pre-Planning
Make sure all the necessary shop drawing layouts and determine the actual position to
commence installation with the mobilisation of required work force, tools and equipment.
Determine the method and material of support to be used according to location and load of items
to be supported. Supports or hangers are allowed to be secured to roof structure trusses or purlins.
Upon delivery, person in-charge shall check for any defect of damage and according to delivery
order.
2. Constructions
2.1 Fabrication
Iiron supports and hanger rods shall be cut to required length at the ground before
being hoisted up for installation. For support mounted on truss or purlins, a flat bar with a
hanger rod welded to it shall be used to secure around the cross section of the truss or
purlins and fixed with bolt and double nut.
For installing equipment, pipe or duct we have kind of support which is used
depend on condition, material and load for detail used any area referred to approval shop
drawing.
a. Clamp Support
Clamp support shall be used where ducting is to be suspended from building steel, we
selected type on the basis to be supported like beam and purlins, this detail kind of
clamp support we used in this project
METHOD STATEMENT
FOR SUPPORT AND HANGER

b. Steel Frame Support


Steel frame support we used for fixed support installed at civil column or beam
with dyna bolt for installed support. In this support case installation, bottom of beam is
prohibited for installed support.
Same with clamp support we have a kind support to use in this project.
METHOD STATEMENT
FOR SUPPORT AND HANGER

2.2 Installation
Check location and routing for obstruction by other services. Erect scaffolding,
lifter or rolling tower to required height and barricade surrounding area for safety
purposes. Safety officer shall check for proper erection of scaffolding. For support
mounted on soffit of slab, the hanger rod shall be secured to an anchor bolt fixed into a
drilled hole on the soffit. Ensure the supports and hangers are in a straight line and the
spacing in between each support is consistent and according to specification. Check that
all supports are properly secured to the soffit of slab or purlins and the angle iron supports
are secured to the base of equipment, pipe or duct.
Distance for all support referred to design support distance suggested in this
project,

3. Testing and Commissioning


During the start up, minimal vibration caused by the equipments connected will transmit
throughout the support or hanger length. Check for rigidness of support and ensure bolts and nuts
are tighten.
3.1 Procedure for Nut and Bolt Tightening
a. Heck bolts and nut for rust and lubrication install nut and washer with marking up
washer, if installed, must be under the turned element.
b. Tighten bolt to snug tight condition having all faying surfaces in tight contact.
c. Check the tightening and mach with torque set tightening as the same size.
d. Mach mark bolt tip, nut and base steel.
METHOD STATEMENT
FOR SUPPORT AND HANGER

Flow Chart for Bolt Tightening