YEAR CLIENT PROJECT SCOPE OF WORK

Mechanical Completion
LNG Carrier "Castillo Villalba"" 087 Technical assistance to Commissioning department
2002 Shipyard IZAR Puerto Real Factory
NAVIERA ELCANO Creation of Commissioning Activities Data Base
Commissioning Procedures and Protocols

2003 Shipyard IZAR Puerto Real Factory LNG Carrier C/105 – NAVIERA TAPIAS Commissioning / Operation & Maintenance / Mechanical Completion

2004 Shipyard IZAR Puerto Real Factory LNG Carrier C/103 – NAVIERA KNUTSEN Commissioning / Operation & Maintenance / Mechanical Completion

LNG plant Offshore "SNOHVIT" F&G Installation and Commissioning


2004 - 2005 Dragados Offshore
HAMMERFEST- STATOIL Hydrostatic Pressure Test Engineering and Execution

Combat Supply Vessel C/107 BAC Hydraulic Pressure test and piping cleaning engineering and execution/
Shipyard Navantia San Fernando /
2008-2010 "Cantabria" Mechanical Completion Engineering and Execution/ Precommissioning/
Puerto Real
Spanish Army Commissioning: Electrical, intrumentation and mechanical complete

Coastal Patrol Vessel (BVL) C/501 Mechanical Completion Engineering / Mechanical Completion Execution / Mass
2008-2010 Shipyard Navantia San Fernando "Guicamacuto (GC-21)" instalation/ Turnkey of Electrical Commissioning/ Assistance during Guarantee
Venezuelan Navy in Venezuela

Coastal Patrol Vessel (BVL) C/502 Mechanical Completion Engineering / Mechanical Completion Execution / Mass
2008-2010 Shipyard Navantia San Fernando "Yavire (GC-22)" instalation/ Turnkey of Electrical Commissioning/ Assistance during Guarantee
Venezuelan Navy in Venezuela

Coastal Patrol Vessel (BVL) C/504 Mechanical Completion Engineering / Mechanical Completion Execution / Mass
2008-2011 Shipyard Navantia San Fernando "Naigueta (GC-22)" instalation/ Turnkey of Electrical Commissioning/ Assistance during Guarantee
Venezuelan Navy in Venezuela

Ocean Surveillance Patrol boat (POV) 505 Mechanical Completion Engineering / Mechanical Completion Execution / Mass
2008-2011 Shipyard Navantia Puerto Real "Guaiquerí" instalation/ Turnkey of Electrical Commissioning / Pipping mark-up/ Modification
Venezuelan Navy systems G.I.E.

Hydraulic Test Engineering and Execution/ Mechanical Completion Engineering


Ocean Surveillance Patrol boat (POV) 506 / Mechanical Completion Execution / Verification and control valves identification
2008-2011 Shipyard Navantia Puerto Real "Warao" plate/ Installation indentification plates Doors/ Valves certification/ Chemical
Venezuelan Navy Cleaning fuel MM.PP. / Turnkey of Electrical Commissioning / Pipping mark-up/
Modification systems G.I.E.

www.pine.es 1
YEAR CLIENT PROJECT SCOPE OF WORK
Ocean Surveillance Patrol boat (POV) 507
Mechanical Completion Engineering / Mechanical Completion Execution / Piping
2008-2011 Shipyard Navantia Puerto Real "Yecuana"
Mark-up/ Modification systems G.I.E.
Venezuelan Navy

Hydraulic Test Engineering and Execution/ Mechanical Completion Engineering


Ocean Surveillance Patrol boat (POV) 508 / Mechanical Completion Execution / Verification and control valves identification
2008-2011 Navantia Puerto Real "Kariña" plate/ Installation indentification plates Doors/ Valves certification/ Chemical
Venezuelan Navy Cleaning fuel MM.PP. / Turnkey of Electrical Commissioning / Pipping mark-up/
Modification systems G.I.E.

RO-RO C/509 "José María Entrecanales" Mechanical Completion Engineering / Mechanical Completion Execution / Piping
2008-2009 Shipyard Navantia Puerto Real
Acciona Transmediterránea checks and Mark-up

Hydraulic test and piping cleaning engineering / Precommissioning execution /


RO-RO C/510 "Superfast Baleares"
2008-2010 Shipyard Navantia Puerto Real Mechanical Completion engineering / Mechanical Completion execution /
Acciona Transmediterránea
Verification and control identification plates / piping checks and mark- up

Maritime Action Vessel (BAM) C/511


2009-2011 Shipyard Navantia San Fernando "Meteoro P41" Mechanical Completion Engineering/ Mechanical Completion execution
Spanish Army
Maritime Action Vessel (BAM) C/512
Mechanical Completion Engineering/ Mechanical Completion execution /
2009-2011 Shipyard Navantia Puerto Real "Rayo P42"
Turnkey Electrical, Instrumentation and Mechanical Commissioning
Spanish Army
Maritime Action Vessel (BAM) C/513
2009-2012 Shipyard Navantia San Fernando "Relámpago P43" Mechanical Completion Engineering/ Mechanical Completion execution
Spanish Army
Maritime Action Vessel (BAM) C/514
2009-2012 Shipyard Navantia San Fernando "Tornado P44" Mechanical Completion Engineering/ Mechanical Completion execution
Spanish Army

Thermosolar Power Plant "Palma del Río II" Mechanical Completion Engineering / Mechanical Completion execution /
2009-2010 Ingeteam Power Plants Córdoba Electrical, instrumentation and mechanical Commissioning Turnkey / Turbine oil
Acciona Energía piping cleaning engineering and execution

www.pine.es 2
YEAR CLIENT PROJECT SCOPE OF WORK

Thermosolar Power Plant "Palma del Río I"


Mechanical Completion Engineering / Mechanical Completion / Electrical,
2011 Ingeteam Power Plants Córdoba
Instrumentation and Mechanical Commissioning Turnkey
Acciona Energía

Wellhead Platforms (2) and Jackets(2)


Hydraulic PressureTest and piping cleaning engineering and execution/
2011-2012 Dragados Offshore S.A. Offshore "South Arne Phase III"
Mechanical Completion / Torking and Tensioning
HESS

Wellhead Platforms (2) and Riser Platforms


2013 Dragados Offshore S.A. (2) Offshore "Jasmine Judith" Mechanical Completion
Conocophillips

2010-2013 Shipyard NAVANTIA Three(3) BVL and four (4) POV Guarantee and Maintenance Contract for 7 Military Vessels

Thermosolar Plant "Termosol II"


2013 SENER Badajoz Instrument installation
NextEra Energy, Inc.

Coastal Patrol Vessel (BVL)


Electrical installation supervision, Mechanical Completion and Hydraulic
2013-2016 DIANCA "Comandante Eterno Hugo Chávez"
Pressure Test in Venezuela
Venezuelan Navy

Commissioning Onshore and Offshore Engineering: protocols and planning


OSS WIKINGER: 400MW Electrical
Maintenance Onshore y Offshore Engineering
2015-2016 NAVANTIA Substation Wind Farm Offshore (Germany)
Commissioning Turnkey Onshore complete and Maintenance Onshore on
IBERDROLA
Mechanical, Electrical and Instrumentation

OSS WIKINGER: 400MW Electrical


Turnkey offshore Commissioning and Maintenance in Germany on Mechanical,
2016 NAVANTIA Substation Wind Farm Offshore (Germany)
Electrical and Intrumentation
IBERDROLA

2015-2020 OHL Several Projects Mechanical Completion / Commissioning / Operation & Maintenance

www.pine.es 3