Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

2011GM0875 1

Update on IEEE 1547 Series of Standards for


Distributed Resources Interconnection
Bob Saint, Senior Member, IEEE

Abstract—The IEEE 1547 Series of Standards are a key II. IEEE 1547 – STANDARD FOR INTERCONNECTING
reference for Distributed Resources Interconnection. This paper DISTRIBUTED RESOURCES WITH ELECTRIC POWER SYSTEMS
discusses the Scope and Purpose; current status; and a short
description of the content and limitations of each of the A. Scope
documents.
This standard establishes criteria and requirements for
Index Terms—Distributed Resources Interconnection, IEEE interconnection of distributed resources (DR) with electric
1547, Distributed Generation Interconnection. power systems (EPS).
B. Purpose
I. INTRODUCTION
This standard provides a uniform standard for

T HIS paper describes the IEEE 1547 series of standards


and their applicability for electric distribution system
designers and planners; distributed resource manufacturers
interconnection of distributed resources with electric power
systems. It provides requirements relevant to the performance,
operation, testing, safety considerations, and maintenance of
and developers; and regulators and policy makers. The IEEE the interconnection.
series of standards is administrated by Standards Coordinating The requirements shall be met at the point of common
Committee (SCC) 21, Standards Coordinating Committee on coupling (PCC), although the devices used to meet these
Fuel Cells, Photovoltaics, Dispersed Generation, and Energy requirements can be located elsewhere. This standard applies
Storage. Information about all the standards coordinated by to interconnection based on the aggregate rating of all the DR
SCC 21 can be found at the SCC 21 web site: units that are within the Local EPS. The functions of the
http://grouper.ieee.org/groups/scc21/. interconnection system hardware and software that affect the
The IEEE 1547 series of standards are often misused. It is Area EPS are required to meet this standard regardless of their
important to understand the limitations and applicability of location on the EPS.
The stated specifications and requirements, both technical
each of the standards in the series. In general the IEEE 1547
and testing, are universally needed for interconnection of DR,
series of standards deals with the interconnection of
including synchronous machines, induction machines, or
distributed generation or storage of less than 10 MW to utility power inverters/converters, and will be sufficient for most
distribution systems (defined as Area Electric Power Systems, installations.1
or Area EPS). The IEEE 1547 series of standards is not
generation technology specific. It applies to the C. Limitations and Application
interconnection to the Area EPS equally for all generation The criteria and requirements in this document are
technologies, including reciprocating engines, variable applicable to all distributed resource technologies, with
supplies such as wind and solar generation as well as vehicle aggregate capacity of 10 MVA or less at the PCC,
technology interconnection in the vehicle-to-grid mode. interconnected to EPSs at typical primary and/or secondary
The remainder of this paper describes each of the standards distribution voltages. Installation of DR on radial primary and
in the IEEE 1547 series; the scope and purpose; the limitations secondary distribution systems is the main emphasis of this
and applicability; and the status of completion. standard, although installation of DR on primary and
secondary network distribution systems is considered. This
standard is written considering that the DR is a 60 Hz source.
• This standard does not define the maximum DR
capacity for a particular installation that may be
interconnected to a single PCC or connected to a
given feeder.
• This standard does not prescribe DR self-protection or
all operating requirements for DR units.

Bob Saint is with the National Rural Electric Cooperative Association and
1
is the current Chair of the IEEE P1547.7 Working Group and was the Chair of Additional technical requirements and/or tests may be necessary for some
the IEEE P1547.2 Working Group when that standard was completed. limited situations.

978-1-4577-1002-5/11/$26.00 ©2011 IEEE


Authorized licensed use limited to: AECOM Technical Services Inc. Downloaded on February 19,2024 at 22:58:40 UTC from IEEE Xplore. Restrictions apply.
2011GM0875 2

• This standard does not address planning, designing, IV. IEEE 1547.3 - GUIDE FOR MONITORING, INFORMATION
operating, or maintaining the Area EPS. EXCHANGE AND CONTROL OF DISTRIBUTED RESOURCES
• This standard does not apply to automatic transfer INTERCONNECTED WITH ELECTRIC POWER SYSTEMS
schemes in which load is transferred between the DR
and the EPS in a momentary make-before-break A. Scope
operation provided the duration of paralleling This document provides guidelines for monitoring,
information exchange, and control of distributed resources
D. Status
(DR) interconnected with electric power systems (EPSs).
This is the Standard that defines the terms and provides
the technical requirements for the interconnection of B. Purpose
distributed resources to the utility distribution system (Area This document provides guidelines to facilitate the
EPS). This Standard was originally completed in 2003 and interoperability of one or more DR interconnected with EPSs.
reaffirmed in 2008 without any changes. According to It describes functionality, parameters, and methodologies for
IEEE procedures, this Standard will be in effect for five MIC of DR interconnected with or associated with EPSs. DR
years, or until 2013. This document is relatively small, just technologies include fuel cells, photovoltaics, wind turbines,
16 pages including the informative Annex A Bibliography, microturbines, and other distributed generators as well as
with the actual technical requirements taking only five distributed energy storage systems.
pages. Therefore, additional guidance is necessary to apply This guide documents alternatives for sound practice based
these technical requirements to the Electrical Power System on current practice and includes both legacy and new MIC
(EPS). systems.
C. Limitations and Application
III. IEEE 1547.1 – STANDARD CONFORMANCE TEST
PROCEDURES FOR EQUIPMENT INTERCONNECTING This guide is primarily concerned with MIC between DR
DISTRIBUTED RESOURCES WITH ELECTRIC POWER SYSTEMS units and the outside world. It is not intended for MIC within
a device or among the components that make up a DR unit.
A. Scope The data exchanges between the distributed resource
This standard specifies the type, production, and controller and equipment or entities internal to the local
commissioning tests that shall be performed to demonstrate electric power system are not addressed in this guide. Refer to
1.7 for clarification. The many potential paths of data
that the interconnection functions and equipment of the
exchanges among individual stakeholders are also beyond the
distributed resources (DR) conform to IEEE Std 1547.
focus of this document. This guide does not establish
B. Purpose requirements for interconnection, protection, safety, or local
Interconnection equipment that connects DR to an electric and area EPS operation functions.
power system (EPS) must meet the requirements specified in D. Status
IEEE Std 1547. Standardized test procedures are necessary to Many of the information identified in this guide for data
establish and verify compliance with those requirements. exchange has been included in IEC 61850. This guide was
These test procedures must provide both repeatable results, completed in 2007. It comes due for reaffirmation in 2012.
independent of test location, and flexibility to accommodate
the variety of DR technologies.
V. IEEE 1547.4 – GUIDE FOR DESIGN, OPERATION, AND
C. Limitations and Application INTEGRATION OF DISTRIBUTED RESOURCE ISLAND SYSTEMS
This standard does not cover testing for safety. Although WITH ELECTRIC POWER SYSTEMS
this standard does not define a certification process, these tests
A. Scope
may be used as part of such a process.
T his document provides alternative approaches and good
D. Status practices for the design, operation, and integration of
This standard covers the testing procedures to determine if distributed resource (DR) island systems with electric power
the interconnection meets the requirements of IEEE 1547. systems (EPS). This includes the ability to separate from and
Underwriters Laboratories (UL) 1741 - Standard for Safety reconnect to part of the area EPS while providing power to the
Inverters, Converters, Controllers and Interconnection System islanded EPSs. This guide includes the distributed resources,
Equipment for Use With Distributed Energy Resources interconnection systems, and participating electric power
describes the process that Underwriters Laboratories uses to systems.
certify DR Interconnection systems.. UL 1741 is consistent
B. Purpose
with IEEE 1547.1 and therefore, UL1741 certified systems are
IEEE 1547 compliant. This Standard was completed in 2005. This guide is intended to be used by EPS designers,
It is currently being balloted for reaffirmation. The status of operators, system integrators, and equipment manufacturers.
the ballot is unknown at this time. The document is intended to provide an introduction overview
and address engineering concerns of DR island systems. It is
relevant to the design, operation, and integration of DR Island

Authorized licensed use limited to: AECOM Technical Services Inc. Downloaded on February 19,2024 at 22:58:40 UTC from IEEE Xplore. Restrictions apply.
2011GM0875 3

Systems. Implementation of this guide will expand the B. Purpose


benefits of using DR by targeting improved reliability and The purpose of this project is to provide technical
build upon the interconnection requirements of IEEE Std information and guidance to all parties involved in the
1547. interconnection of dispatchable electric power sources to a
C. Limitations and Application transmission grid about the various considerations needed to
This document applies only to situations in which the area be evaluated for establishing acceptable parameters such that
EPS operator has agreed to participate in intentional island the interconnection is technically correct.
operation. The criteria and requirements are applicable to the C. Status
DR and the portion of the area EPS that are to be incorporated
The Project Authorization Request (PAR) for this guide
into a planned island. Planned area EPS islands use portions
was issued in 2004 and has been extended until December 31,
of radial distribution systems, both primary and secondary.
2011. There has been little work on the guide accomplished
• This guide does not establish DR reserve levels for a
so far. If there is no work completed by the time the PAR
specific planned island.
extension expires, then the working group assigned to this
• The aggregate generating capacity within the DR project will probably be disbanded. Because of the
island system is not restricted by this document. increasingly importance of filling this gap in the standards,
• Each individual point of common coupling (PCC) is hopefully a new PAR will then be established and a new,
limited to 10 MVA (per IEEE Std 1547). more active, working group formed.
• This guide does not presume that an area EPS operator
desires to establish planned islands on any portion of VII. IEEE 1547.6 - RECOMMENDED PRACTICE FOR
the area EPS that is normally connected to the INTERCONNECTING DISTRIBUTED RESOURCES WITH ELECTRIC
balance of the area EPS. POWER SYSTEMS DISTRIBUTION SECONDARY NETWORKS
• This guide does not presume that all DR located within A. Scope
an area EPS operator’s planned island wish to or
must participate. This standard builds upon IEEE Standard 1547 for the
• This guide does not provide operational procedures for interconnection of distributed resources (DR) to distribution
establishing and operating a planned island. secondary network systems. This standard establishes
recommended criteria, requirements and tests, and provides
• This guide does not cover all possible contingencies guidance for interconnection of distribution secondary
(e.g., loss of control communications back to the area network system types of area electric power systems (Area
EPS) that may result in the cessation of planned EPS) with distributed resources (DR) providing electric power
island operations. generation in local electric power systems (Local EPS).
• This guide does not cover contractual or regulatory
considerations. B. Purpose
D. Status This standard focuses on the technical issues associated
This guide is currently in the balloting process. A task with the interconnection of Area EPS distribution secondary
force has addressed all the comments and as of this writing, networks with a Local EPS having DR generation. The
a recirculation of the ballot is forthcoming that addresses standard provides recommendations relevant to the
the comments received. The balloting pool will have a performance, operation, testing, safety considerations, and
chance to change their vote and/or make comments based maintenance of the interconnection. In this standard
on the changes made to the guide. It is projected that this consideration is given to the needs of the Local EPS to be able
guide be approved and published by IEEE before the end of to provide enhanced service to the DR owner loads as well as
2011. to other loads served by the network. Equally, the standard
addresses the technical concerns and issues of the Area EPS.
VI. IEEE 1547.5 - TECHNICAL GUIDELINES FOR Further, this standard identifies communication and control
INTERCONNECTION OF ELECTRIC POWER SOURCES GREATER recommendations and provides guidance on considerations
THAN 10 MVA TO THE POWER TRANSMISSION GRID that will have to be addressed for such DR interconnections.

A. Scope C. Status
This document provides guidelines regarding the technical This guide is currently in the balloting process. A task
requirements, including design construction, commissioning force has addressed all the comments and as of this writing,
acceptance testing and maintenance/performance a recirculation of the ballot is forthcoming that addresses
requirements, for interconnecting dispatchable electric power the comments received. The balloting pool will have a
sources with a capacity of more than 10 MVA to a bulk power chance to change their vote and/or make comments based
on the changes made to the guide. It is projected that this
transmission grid.
guide be approved and published by IEEE before the end of
2011.

Authorized licensed use limited to: AECOM Technical Services Inc. Downloaded on February 19,2024 at 22:58:40 UTC from IEEE Xplore. Restrictions apply.
2011GM0875 4

VIII. IEEE P1547.7 - DRAFT GUIDE TO CONDUCTING B. Purpose


DISTRIBUTION IMPACT STUDIES FOR DISTRIBUTED RESOURCE
INTERCONNECTION The purpose of the methods and procedures provided in this
recommended practice is to provide more flexibility in
A. Scope determining the design and processes used in expanding the
implementation strategies used for interconnecting distributed
This guide describes criteria, scope, and extent for resources with electric power systems. Further, based on IEEE
engineering studies of the impact on area electric power Std 1547 requirements, the purpose of this recommended
systems of a distributed resource or aggregate distributed practice is to provide the knowledge base, experience, and
resource interconnected to an area electric power distribution opportunities for greater utilization of the interconnection and
system. its applications.

B. Purpose C. Status
The creation of IEEE Std 1547 "IEEE Standard for The working group for this recommended practice first met in
Interconnecting Distributed Resources with Electric Power August, 2010 and has so produced version 1 of a Resource
Systems" has led to the increased adoption of DR throughout Document as a result of that first meeting and subsequent
distribution systems. This document describes a methodology writing group’s conference calls and web conferences. This
for performing engineering studies of the potential impact of a document will be, in part, a result of a NIST Smart Grid
distributed resource interconnected to an area electric power Interoperability Panel (SGIP) Priority Action Plan (PAP) task
distribution system. Study scope and extent are described as identified to fill the gap in the IEEE 1547 Standard as a result
functions of identifiable characteristics of the distributed of a high penetration of distributed resources being installed
resource, the area electric power system, and the on distribution systems. The interconnection of distributed
interconnection. Criteria are described for determining the resources and storage on distribution systems is considered
necessity of impact mitigation. one of the characteristics of the smart grid.

Establishment of this guide allows distributed resource X. CONCLUSION


owners, interconnection contractors, area electric distribution The IEEE 1547 series of standards is an ongoing process.
power system owners and operators, and regulatory bodies to As the need becomes evident, more guidance or recommended
have a described methodology for when distribution system practice documents may be added to assure that the IEEE
impact studies are appropriate, what data is required, how they 1547 standard remains timely, relevant and useful to those that
are performed, and how the study results are evaluated. In the
interconnect all technologies of distributed resources to the
absence of such guidelines, the necessity and extent of DR
electric grid. It is important to be aware of the status of the
interconnection impact studies has been widely and
activities of the working groups within the IEEE 1547 series
inconsistently defined and applied.
of standards and also be aware of the limitations and the
C. Status applicability of each of the documents within this series. Most
of all, it is important to be involved in the working groups if
The working group for this proposed guide is very active
you have expertise or interest in the outcome of the guides,
and has been meeting 2-3 times a year face-to-face and as a
number of writing groups via conference call or web recommended practices and standards being produced.
conference since early 2009. Comments have been received
and discussed by the working group on Draft 4.1. It is XI. REFERENCES
anticipated that balloting will occur during 2011. It is [1] IEEE Std 1547™-2003 (R2008). IEEE Standard for Interconnecting
recognized that this guide will fill a vital gap in giving Distributed Resources with Electric Power Systems. Reaffirmed 25
September 2008.
information for utility distribution system planners to perform [2] IEEE Std 1547.1™-2005. IEEE Standard Conformance Test Procedures
studies to evaluate the impact of the installation of a for Equipment Interconnecting Distributed Resources with Electric
distributed resource on the distribution system. Power Systems. Approved 9 June 2005.
[3] IEEE Std 1547.2™-2008. IEEE Application Guide for IEEE Std
1547™, IEEE Standard for Interconnecting Distributed Resources with
IX. IEEE P1547.8 – RECOMMENDED PRACTICE FOR Electric Power Systems. Approved 10 December 2008.
ESTABLISHING METHODS AND PROCEDURES THAT PROVIDE [4] IEEE Std 1547.3™-2007. IEEE Guide for Monitoring, Information
SUPPLEMENTAL SUPPORT FOR IMPLEMENTATION STRATEGIES Exchange, and Control of Distributed Resources Interconnected with
FOR EXPANDED USE OF IEEE STANDARD 1547 Electric Power Systems. Approved 17 May 2007.

A. Scope
This recommended practice applies to the requirements set
forth in IEEE Std 1547 and provides recommended methods
that may expand the usefulness and uniqueness of IEEE Std
1547 through the identification of innovative designs, XII. BIOGRAPHY
processes, and operational procedures.

Authorized licensed use limited to: AECOM Technical Services Inc. Downloaded on February 19,2024 at 22:58:40 UTC from IEEE Xplore. Restrictions apply.
2011GM0875 5

Bob Saint is a Principal Distribution


Engineer in the Energy & Environmental
Policy Department at the National Rural
Electric Cooperative Association
(NRECA). Bob has been with NRECA
for over 10 years. His primary role is
technical advisor for the T&D
Engineering Committee. He works with
the System Planning Subcommittee and
the soon to be formed Smart Grid Subcommittee. He is also
the Program Manager for the MultiSpeak® Software
Integration Initiative. Bob is a member of the GridWise
Architecture Council (GWAC) and on the Governing Board
of the NIST Smart Grid Interoperability Panel (SGIP).
Bob graduated from Wichita State University in Wichita,
Kansas, with a BS degree in Electrical Engineering.
He has worked for rural electric co-ops, primarily
distribution cooperatives for over 20 years in Colorado before
coming to NRECA.
He is a Professional Engineer in Texas and Virginia and a
senior member of IEEE. He is very active in several IEEE
working groups relating to Distributed Generation
Interconnection, Smart Grid, Distribution and Power Quality.

Authorized licensed use limited to: AECOM Technical Services Inc. Downloaded on February 19,2024 at 22:58:40 UTC from IEEE Xplore. Restrictions apply.

You might also like