Professional Documents
Culture Documents
O&m Kul 14 Project
O&m Kul 14 Project
O&m Kul 14 Project
MAINTENANCE FUEL
SYSTEM
Table of Contents
1. Brief System Description....................................................................................................4
1.1 Introduction.................................................................................................................4
2. List of Equipment................................................................................................................7
2.1 List of Major Equipment.............................................................................................7
3. Manufacturing Literature..................................................................................................11
4. Spare Parts List.................................................................................................................13
4.1 Spare Parts List..........................................................................................................13
5. Operating Procedures........................................................................................................15
5.1 System Operation......................................................................................................15
5.2 Emergency Operation Procedure (EOP)....................................................................22
6. Maintenance Procedures & Servicing Records.................................................................27
6.1 Sevicing & Maintenance Procedures.........................................................................27
6.2 Fuel Pump Control Panel...........................................................................................28
7. Disposal Instructions.........................................................................................................31
7.1 Disposal instructions and waste management...........................................................31
8. Factory Test Certificates, Site Testing & Commissioning Reports..................................33
8.1 Factory Test Certificates............................................................................................33
8.2 Site Testing & Commissioning Reports....................................................................40
9. Modifications....................................................................................................................43
9.1 To be furnished later upon completion of as-built drawings.....................................43
10. As built Drawings..........................................................................................................45
10.1 To be furnished later upon completion of as-built drawings.....................................45
SECTION 1
BRIEF SYSTEM DESCRIPTION
1. Brief System Description
1.1 Introduction
The fuel oil system consists of new 2 Underground Fuel Storage Tanks (UST) with 24 hours
of fuel storage capacity from adjacent side of the building, fuel transfer pump room housing
two fuel transfer pump sets (N+N), pump control panel, 1000L fuel storage Day tank in each
generator container, fuel distribution pipe system.
The UST is completed with filling station, vent point and fuel level content gauge for ease of
refilling of fuel.
Each filling station shall be provided with dedicated main fill line connecting to individual
fuel underground storage tank. The fuel fill port assembly shall be complete with powder
coated steel enclosure, control panel complete with fuel management and inventory system
level, gauges, and meter, camlock hose connection, isolation valve, and a strainer.
An underground concrete chamber outside the building that is buried below the service
road is provided for each UST. Each will be provided with sump to allow a portable sump
pump to be dropped below this sump to drain in case of water accumulation.
Each UST has two (2) nos. of access hatches to house associated tanks accessories such as
the interstitial leak detection cable, level switch, level sensor, valves, etc. In addition, each
UST is provided with its own fill port, complete with camlock, dedicated fill line to the UST,
and fuel management and inventory system. All fuel fill points are located centrally and
housed in a secured room outside the building.
Using transfer tank system, the fuel pump system will provide fuel distribution to the Day
tank of each individual Generator Set. In the fuel pump room, bund wall is constructed to
cover full pump room for the safe operations and maintenance of the system and a point
leak detection system will be provided in the pump room.
Fuel oil supply pipe of UST is routed underground and rise above ground within the fuel
pump room where it connects to the fuel transfer pump suction ring header with isolation
valve and strainer. Two fuel transfer pumps (N+N) are within the fuel pump room. Both
pumps are connected in parallel to the suction header and supply two fuel supply risers
feeding day tanks, complete with sectionalizing valves.
Each generator double walled Day tank has a 1000L of installed capacity, dedicated fuel
level controllers, two fuel inlet pipes, two motorized isolation valves, a drain (dump) pipe
with fusible link valve and leak detection sensor provided by the generator manufacturer.
Each Day tank has dual feeds from the fuel transfer risers for concurrently maintainability. A
manual isolation valve is located at each fuel feed line. Under normal condition both manual
ball valves will remain open. If a leak is noticed in either supply pipe the operator can
manually isolate the leaking pipe by closing the manual isolation valves.
The Day tank motorized fill including its level switches & sensors, shall be monitored, and
controlled by the Day tank control panel provided by the generator manufacturer which
shall communicate, via open communication protocol (Modbus TCP / BACNET TP/IP), with
the generator control panel and fuel oil system controller.
The fuel oil system controller shall be provided with primary and redundant Programmable
Logic Controllers (PLCs). The fuel oil system controller shall communicate with the fuel
management and inventory system, generator day tank control panels, and the fuel transfer
pump control panels via open communication protocol (Modbus TCP / BACNET TP/IP).
Equipment Underground
Storage Tank
No. Descriptions Brand Model
1 Underground Storage Tank AllTank T106
TTK Leak
Detection FG-NET
2 Interstitial Leak Detector
Systems
Rochester
T/LL70 Series
3 Level Switches Sensors
4 Level Transmitter
TTK Leak
Detection FG-NET
5 Tank Sump Leak Detector
Systems
Fuel System
No. Descriptions Brand Model
1 Motorize valve Thinktank BN008,BN020,BN040,BN010
Daytank
TTK Leak
Detection FG-NET
2 Leak Detector
Systems
Rochester
T/LL70 Series
3 Level Switches Sensors
4 Level Transmitter
TT42C150P/R
6 Pressure relief valve Thinktank
Underground Storage
Tank
No. Descriptions Brand Model
1 Underground Storage Tank AllTank T106
TTK Leak
Detection FG-NET
2 Interstitial Leak Detector
Systems
Rochester
T/LL70 Series
3 Level Switches Sensors
4 Level Transmitter
TTK Leak
Detection FG-NET
5 Tank Sump Leak Detector
Systems
Rochester
T/LL70 Series
3 Level Switches Sensors
4 Level Transmitter
10 Y strainer
11 Side entry float switches
SCENARIO 2: Low fuel level (50%) (If faulty situation on level sensor & no flow)
When fuel “Low Level” alarm is initiated – whereby pump Start level sensor faulty or
insufficient flow detected
“Low Level” alarm will be triggered on the fuel pump control panel with pre-emptive
warning alarms, but fuel transfer pump will not start
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
If pump failure or ‘No Flow’ fuel in the pipe system alarm will be triggered on the fuel pump
control panel with warning alarms,
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
The system will changeover to standby system B including the Pump and Motorized
Valves Operator/crew to attend: - to acknowledge alarm and attend the faulty
When “Low Low Level” (Lag fill request – “Level Alarm”) is initiated – whereby pump Start
“level sensor” are faulty or insufficient flow detected
When the “Low Low Level” alarm triggered, the alarm not affected/interrupted the operation
of generator during the auto power fail or manual operation.
Lag fill request – “Level Alarm” will be triggered, both system (A) and (B) take over and lead
fuel transfer pump and motorized valves will run and open to fill the day tank.
If one of the day tank reaches “Low Level” the respective motorized valve system (B) will close.
The others day tank that has not reach “Low Level” will remain open for both motorized valve
system (A) and (B).
The standby system (B) will stop when all the day tank reaches “Low level” but the duty system
(A) will continue running until filling process completed.
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
If pump failure or ‘No Flow’ fuel in the pipe system alarm will be triggered on the fuel pump
control panel with warning alarms,
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
The system will changeover to standby system B including the Pump and Motorized
Valves. Operator/crew to attend: - to acknowledge alarm and attend the faulty
When “Critical Low Low Level” (Level Alarm) is initiated – whereby low fuel level and lag fill
request sensor faulty or insufficient flow detected
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
Lag fill request – “Level Alarm” will be triggered, both system (A) and (B) take over and lead fuel
transfer pump and motorized valves will run and open to fill the day tank.
If one of the day tank reaches “Low Level” the respective motorized valve system (B) will close.
The others day tank that has not reach “Low Level” will remain open for both motorized valve
system (A) and (B).
The standby system (B) will stop when all the day tank reaches “Low level” but the duty system
(A) will continue running until filling process completed.
If pump failure or ‘No Flow’ fuel in the pipe system alarm will be triggered on the fuel pump
control panel with warning alarms,
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
The system will changeover to standby system B including the Pump and Motorized
Valves Operator/crew to attend: - to acknowledge alarm and attend the fault / manually reset
Fuel transfer pump fail to stop due to lead fill request level switch malfunction; “High High Level”
alarm will be activated, and motorized valve will cut-off and stop supply for the affected day
tank only.
Fuel transfer operation will not affect any fuel supply to other remaining day tanks.
Fuel transfer pump (system A & B) will stop when fuel level reaches to “High Level” (lead fill
“Stop Level” sensor) in the day tank.
An alarm status will send to control panel/HMI with warning alarm transmit to BMS
In the event of “High High Level” (Level Alarm) switch faulty, and the pump none stop
pumping transfer the fuel, the overflow fuel from day tank will flow back to bulk fuel storage
tank.
An alarm status will send to control panel/HMI with warning alarm transmit to
BMS Operator/crew to attend: - to acknowledge alarm and attend the fault / manually
reset
If any fuel leak is detected in the containment tank (drip pan for each day tank inside bund wall).
The leak sensor will be activated, a warning alarm will send to control panel/HMI with alarm
transmit to BMS. Operator/crew to conduct the physical inspection to check leakage occurred.
During the pump running, if the surrounded drip pans of the respective day tank fuel leak
detection activated, the respective supply pipe’ motorized valve will close and cut off fuel
supply.
At the same time any other day tank demanded the fuel, the pump will start and continue to top
up the fuel into the respective day tank.
Fuel transfer system operation will not affect the fuel supply to other remaining day tanks.
If the transfers fuel pipeline detected fuel leaking during the critical time where the day tank
demand fuel, the respective fuel line motorize valve will be closed, and then system will initiates
command the secondary fuel transfer pump (B) to take over the duty with continue refilling fuel
from storage tank to respective day tank without interrupted the fuel transfer system above.
If a particular day tank leak is detected, that day tank will close the motorized valves both
system (A) and (B) and stop filling. The others day tank which are not affected will continue the
filling sequence. No changeover to system (B) for the day tank leakage.
An alarm status will send to control panel/HMI with warning alarm transmit to
Operator/crew to attend: - to acknowledge alarm and attend the fault / manually reset
If System (A) lead fuel transfer pump overload or trips, an alarm status will send to control panel
/HMI with warning alarm transmit to BMS.
Hence, lag fuel transfer pump (B) will take over duty automatically
Operator/crew to attend: - to acknowledge alarm and attend the fault & manually reset
If lead fuel transfer pump (A) starts but flow switch detected no fuel inside the fuel pipe within 1
minute, alarm will send to control panel/HMI with warning alarm transmit to BMS where system
(A) lead pump will stop.
Hence, lag fuel transfer pump (B) will take over duty automatically.
If suddenly “no flow’’ occurs in any day tank primary fuel pipe due to pipe clogged, the fuel
transfer pump (A) will stop, and system will initiates start the fuel transfer pump (B) to take over
the duty and continue refilling fuel from storage tank to respective day tank without interrupted
the fuel transfer system above.
Operator/crew to attend: - to acknowledge alarm and attend the fault & manually reset
SCENARIO 9: Fuel Transfer Pump (A) Power Loss, Fuel Transfer Pump (B) take over (Change
over)
If System (A) fuel pump control main incoming power loss (failure of pump control panel main
supply) An alarm status will send to control panel/HMI with alarm transmit to BMS.
Hence, System (B) fuel transfer pump will take over to transfer fuel when fuel level reaches to
Low Level (Lead fill request Level)
Operator/crew to attend: - to acknowledge alarm and attend the fault & manually reset
If fuel supply line motorized valve fails to close within 1 minute in system A,
An alarm status will send to control panel/HMI with alarm transmit to BMS, to check the alarm
on pump control panel and to rectify the valve
System (B) fuel transfer pump will take over and start transfer fuel when fuel level reaches (Lag
fill request – Level) in day tank
If fuel storage tank No.1 or No.2 suction & return’ motorized valve fails to open within 1 minute
in system (A), the system will changeover to system (B) including the Day tank motorized valve
and pump.
An alarm status will send to control panel/HMI with alarm transmit to BMS
If air lock/trap in pipeline where result the pump (A) is not operating or pressure relief valve
malfunction during the critical time
An alarm status will send to control panel/HMI with alarm transmit to BMS, Crew to check the
alarm status on pump control panel, check the valve and pipeline condition with rectify the
issues
System (B) fuel transfer pump will take over and start transfer fuel when fuel level reaches (Lag
fill request – Level) in day tank.
In the event when happened the air lock/trap, the pressure air increases in the pipe fuel line.
PRV will function to opening high pressure air out and recloses when the pressure drops below
the opening pressure (operation pressure).
Operator/ crew to attend: - to acknowledge alarm and attend the defect & manually reset
When there is a fire, the fuel transfer system will not be affected.
SCENARIO 13: System(A) PLC Failure, Backup System (B) Take Over
There are standalone of independence PLC system in Control Logic integrate with respective
pump set.
If fuel pump control panel (A) PLC “Failure” due to power loss or interruption
An alarm status will send to control panel/HMI with alarm transmit to BMS
Hence, System (B) fuel pump will take over duty, start transfer when fuel level reaches (lag fill
request – “Level Sensor”) in the day tank
Operator/crew to attend: - to acknowledge alarm and attend the fault & manually reset
SCENARIO 14: To Cut-In Next Fuel Storage Tank 25% (Low Low Level)- Change over
between FST 1 & 2
During fuel transfer operation where bulk fuel storage tank 1 fuel level drops to “Low Low
Level” which is (25% of bulk tank capacity).
“Low Low Level” alarm initiated to alert both system fuel transfer pump control panel and lead
pump were continuous pumping.
Bulk fuel storage tank 2 suction and return motorized valve will open before Bulk fuel storage
tank 1 suction and return motorized valve will close. (To ensure set to Auto mode for both
panel)
Fuel transfer pump will continue operation transferred from bulk fuel storage tank 2 and fuel
storage tank 1 will lock out (HMI screen at Panel will indicate lock out when bulk storage is
below 25%)
Operator/crew to attend: - to acknowledge alarm and attend the fault & manually reset
During fuel transfer operation, where fuel demanded day tank’ motorized valve fail/unable to
open at system (A)
It will result the suction pipeline pressure increase over the designed suction head pressure.
However, external pressure relief valve setting has been set 10% higher than the
designed suction head pressure.
Fuel external pressure relief valve will open when pressure is 10% higher than the designed
suction head pressure. The supply fuel will release and flow back to bulk tank.
Fuel external pressure relief valve pipe fuel flow switch will activate the alarm (10sec time delay).
And alarm status will send to control panel/HMI with alarm transmit to BMS
The affected lead fuel transfer pump (system A) will stop immediately, and switch to lag
fuel pump (system B) shall take over the duty.
The affected fuel external pressure relief valve pipe fuel flow switch alarm will auto normalize
after faulty devices being rectified.
If the motorized valve in system (A) failure, the system (B) will take over.
Lead (system A) fuel transfer pump and motorized valves will resume back duty after the
affected day tank motorized valve being rectified (the faulty parts require to rectify / replaced
prior back on duty), the system will continue on system (B) until the next cycle process.
Fuel transfer operation should not affect any of the fuel supply to other remaining day tanks.
SCENARIO 16: Manual Mode
The fuel polishing system is to remove water, microbiological growth and other
contaminants from diesel to maintain the fuel quality at all times. The fuel polishing pump
2(N) will operate alternately (take turn basic) to complete a cycle of the entire tank volume
for storage period 7days basic (weekly). Two units of proposed fuel polishing pump (take
turn basic) able to carry out the fuel polishing through fuel suction pipe with foot valve to
be installed closer to the bottom of the storage tank for suction. The fuel return from the
polishing pump will be discharged horizontally into the fuel tank.
The fuel polishing system is designed for each underground fuel storage tank, and the
system capable to polish and maintain the fuel quality. After the fuel is polished, the
polished fuel will release flow back to another underground fuel tank through fuel polish
return pipe that connected with common return pipe. The system can be operated
automatically/ manually to maintain the fuel quality. The fuel polishing system control is
integrated with fuel transfer pump control panel at pump room. When fuel transfer pumps
start, fuel polishing pumps shall cease operations and shut down the polishing cycle.
Besides, the said polish pump able to transfer the fuel within the underground tank 1 with
underground tank 2 for fuel balancing purpose.
The fuel polishing system is consisting of the following:
Polishing pump
Filter at the outlet to the pump
Deferential pressure gauge
Flow meter
Water detection Automatic Tank Gauging (ATG).
High Level interface is provided for the BMS to monitor the following:
Fuel polishing pump Start/ Stop
Fuel polishing pump Auto/Manual
Fuel polishing pump Trip Alarm.
Fuel polishing pump Power Loss-Status
Fuel polishing pump flow status
Water detection alarm
SCENARIO 17: Auto Mode
The Fuel Monitoring Control Panel was to monitor the fuel level for underground
tank and day tank, as well as for monitoring of fuel and water leak at tank
chamber area.
The Fuel Monitoring Control Panel consist of a main monitoring module,
ProGauge Maglink LX4 with a touch screen display and capable to interface with
32 level sensor probes.
The Maglink LX console was propriety and robust design with Linux base
software for a reliable and stability for used in oil and gas industrial. Hence, the
fuel system design was with a primary Fuel Monitoring Control Panel in the
services line and a secondary system in manual operation for backup in case of
primary unit fail.
5.2 Emergency Operation Procedure (EOP)
Manual Mode
2. Check UG Tank 1 level. Put mode selector switch for UG Tank 1 Supply MOV to
Manual
3. Put mode selector switch for Day Tank 1 and 2 Supply MOV to Manual. Put
command switch to Open
4. Put mode selector switch for Transfer Pump A to Manual
5. Press Pump Start button and confirm pump is running. put UG Tank 1 MOV
command switch to Open
6. Confirm there is flow in the line by hearing the line being filled and observe at Day Tank 1
and that level is increasing. WHEN LEVEL REACH HIGH LEVEL, be ready to close
Day Tank 1 Supply MOV and Stop the Pump. CRITICAL POINT : PLEASE BEWARE
7. WHEN LEVEL REACH HIGH LEVEL, put Day Tank 1 Supply MOV command switch to
Close
8. After Day Tank 1 Supply MOV have been closed, immediately switch UG Tank 1
Supply MOV to Close. Then immediately press Stop for Transfer Pump A. [Immediate
close UG Tank 1 Supply MOV and Stop Transfer Pump after last Day Tank MOV is
closed to prevent overpressure in the line]
Emergency Shutdown
The fuel transfer system can be shut off anytime by pressing emergency stop button at both system
panel. Any panel in emergency lock out mode will lockthe system until both of emergency button is
released. System won’t run if any panel in lock out mode.
SECTION 6
MAINTENANCE PROCEDURES &
SERVICING RECORDS
6. Maintenance Procedures & Servicing Records
Tanks
Valves
Check all valve flow for any accumulated oil. Clean it if necessary
Motorized valve - Check visual operation
Check voltage supply plug, contact plug and auto / manual declutching
Check automatic indoor temperature control
Check 360 visual position indicator well function
Check drain valve well functioned
Fuel Transfer Pump
Make sure internal gear pump well function
Check if rotor motor pump can run
Check diesel from between the gear and discharge port. Clean if necessary
Make sure diesel constant smooth flow with no pulsations
Filtration
Check filter housing for any oil accumulation. Clean the filter
Check and clean in out pipe before and after filter
Check filter absorbs. Replace if necessary
CORRUGATED PIPE
MAINHOLE COVER
TEST REPORT
Cover
The cover supplied is a round FL100 and of composite construction. (See photo.
1) No. on cover –
Photo. 1
-1-
Test Rig
The test rig consists of a ‘giant mecanno’ frame bolted to the floor and supporting the
Enerpac 50 tonne hydraulic cylinder. (Photo 2)
Photo. 2
The cover and frame were sat on steel channels and plates with steel shims to pack
and level.
Test
The test was carried out in accordance with BS EN 124, Class D400.
The load was applied to the cover through a 250mm diameter by 45mm thick steel
block with a 250mm diameter by 25mm rubber pad between the block and cover.
The load was measured using a 1000kN load cell (serial no. 3243N) and digital
load indicator (serial no. D.I.B.1).
The deflection was measured at the centre on the underside of the cover using a dial
indicator.
The cover was loaded to 2/3 of the test load and then released. This was repeated five
times. It was then loaded to try and achieve the test load.
-2-
Results
-3-
400 (20 34.46
seconds)
400 (30 34.55
seconds)
0 2.41
400 35.12
420 37.52 Louder cracking.
440 39.89 Loud
cracking/tearing
noises.
442 41.25 Lou bang! – failure.
360 42.75
.
250
200
150
100
50
0
0 5 10 15 20 25 30 35 40 45
Deflection (mm)
-4-
FL100 EN124 D400 Test
500
450
400
350
300
250
200
Load
150
100
50
0
The cover held the test load of 400kN for the required 30 seconds so therefore passed the EN124 D40
In accordance with EN124 Clause 8.3.1 the permanent set of the cover was 1.21mm which is within th
After the cover had passed the EN124 D400 test, the load was released from the
400kN and after waiting two minutes for the cover to settle, the permanent set was
recorded at 2.41mm
The cover was then removed from the test rig and inspected for damage.
-5-
On the top surface there was a large crack running from the outside edge of the
cover towards the centre. (Photo.3)
Photo.3
There were no signs of any cracking to the bottom surface of the cover or any damage
to the frame.
M.A.Salisbury
Senior Technician
-6-
STAINLESS STEEL PIPE
BALL VALVE
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn.
PO 00009566 Date: 30th Aug, 2023 Model Q941F-150LB-080
Bhd. (913886-A)
No.:
Chemical Component (%) Mechanical Properties
Parts Product Name Material Material QTY δb δs Stat
C Si Mn P S Cr Ni Mo Cu V (Mpa) (Mpa)
δ% Ψ% HB e
Body WCB 0.20 0.42 0.84 0.018 0.018 0.039 0.046 0.008 0.018 0.002 288 501 26 / /
Motorized Ball Valve-DN80 6
Ball CF8M 0.070 0.66 0.99 0.030 0.010 18.30 9.00 2.10 / / 264 518 38 / /
Body WCB 0.23 0.058 0.9 0.031 0.041 0.46 0.48 0.18 / 0.027 250 485 35 / /
Manual 2 Pieces Ball Valve-
8
Ball DN15 CF8 0.055 0.84 1.29 0.034 0.008 18.15 8.310 0.12 / / 205 485 35 / /
Body WCB 0.23 0.058 0.9 0.031 0.041 0.46 0.48 0.18 / 0.027 250 485 35 / /
Manual 2 Pieces Ball Valve-
40
Ball DN40 CF8 0.055 0.84 1.29 0.034 0.008 18.15 8.310 0.12 / / 205 485 35 / /
Performance Test
Inspection Item Shell Test(MPa) Leakage Seal Test(MPa) Air Seal Test(MPa)
Motorized Ball
1
Valve
Inspector 郑浩忠
Test Result Conformity
Approved By 王雪涛
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn. Bhd.
PO 00009566 Date: 30th Aug, Model Q41F-1000WOG-015
(913886-A)
No.: 2023
Parts Item Photos
Manual 2
1 Pieces Ball
Valve
Inspector 郑浩忠
Test Result Conformity
Approved By 王雪涛
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn.
PO 00009566 Date: 30th Aug, Model Q41F-150LB-040
Bhd. (913886-A)
No.: 2023
Parts Item Photos
Manual 2
1 Pieces Ball
Valve
Inspector 郑浩忠
Test Result Conformity
Approved By 王雪涛
FLAME ARRESTOR WITH VENT DN80
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn. Bhd.
PO No.: 00009566 Date: 26th Aug, 2023 Model 7110+FA-S-080
(913886-A)
Chemical Component (%) Mechanical Properties
Parts Product Name Material QTY T.S. Y.S. State
C Si Mn P S Cr Ni / / EL% HB /
(Mpa) (MPa)
Body SS304 0.054 0.475 1.480 0.026 0.002 17.520 8.140 / / 650.0 / 55.0 85.0 /
Flame Arrestor With Vent-
2
DN80
Trim SS316 0.046 0.410 1.077 0.025 0.011 18.090 14.020 / / 780.0 / 75.0 87.0 /
Result Conformity
Flame Arrestor
1 With Vent-
DN80
Inspector 郑浩忠
Result Conformity
Approved By 王雪涛
PRESSURE RELIEF VALVE
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn. Bhd. (913886-A) PO 00009566 Date: 30th Aug, 2023 Model TTA42C-150LB-C-080
No.:
Chemical Component (%) Mechanical Properties
Hea
Parts Product Name Material QTY δb δs State
t C Si Mn P S Cr Ni V MO
(Mpa) (Mpa)
δ% Ψ% HB
No.
Valve body WCB 0.21 0.51 0.4 0.017 0.023 0.1 0.06 0.01 0.03 505 260 25 42 / /
Trim Pressure Relief Valve SS304 3123 2 0.07 0.8 1.6 0.044 0.025 18.5 9 / / 540 230 36 / / /
Spring 50CrVA 0.48 0.25 0.51 0.017 0.025 1 0.2 0.1 / 1305 1130 13 21 / /
Seq. Inspection Item Requirements Result Product Type TTA42C Nominal Pressure 2.0 Mpa
1 Major part material By the rules of ASTM A351/A351M-2000 Measure up Nominal Diameter 2”x2” Pressure Level 0.25-4 Mpa
Thread precision &
2 roughness By confirmed drawing Measure up Set Pressure 0.3 Mpa Lifting Height 8 mm
3 Main connection size Comply API 526 Standard Measure up Runner Diameter 32 mm Discharge Coefficient 0.7
4 Spring Proceeding of fatigue test and stiffness inspection Measure up Discharge Pressure 0.33 Mpa Return Pressure 0.26 Mpa
5 Strength test 1.5PN(Testing medium:water) Measure up Service Temperature 300°C, Applicable medium:Water, oil, Steam
b'
Z'-
6 Cap WCB
5 Spring 50CrVa
4 Bonnet WCB
D
D
N
2
'
3 Disc SS304
L
2 Seat SS304
f'
1 Body WCB
b
Z-Ød
f
DN
No. Name Material
D2
D1
D
L
Pressure Relief Valve DRAWING
Size: DN5
Pressure Rating: 150LB
50 150 120.7 92 18 2 4-Ø18 50 150 120.7 92 18 2 4-Ø18 135 120
DN D D1 D2 b t Z-Ød DN' D' D1' D2' b' t' Z'-Ød L L1
Model: TTA42C-150LB-C-050
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn. Bhd. (913886-A) PO 00009566 Date: 30th Aug, 2023 Model TTA42C-150LB-C-080
No.:
Inspector 郑浩忠
Test Result Conformity
Approved By 王雪涛
SINGLE DISC SWING CHECK VALVE
& WAFER CHECK VALVE
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn. Bhd.
PO 00009566 Date: 29th Aug, 2023
(913886-A)
No.:
Chemical Component (%) Mechanical Properties
Parts Product Name Size Material QTY δb δs State
C Si Mn P S Cr Ni Mo Cu V (Mpa) (Mpa)
δ% Ψ% HB
Body Y Strainer Valve DN80 WCB 4 0.253 0.041 0.810 0.350 0.031 0.310 0.420 0.210 0.350 0.021 495 290 30 / /
Body Wafer Check Valve DN50 WCB 4 0.252 0.042 0.810 0.350 0.031 0.300 0.420 0.220 0.350 0.021 495 290 30 / /
Performance Test
Inspection Item Shell Test(MPa) Leakage Test(MPa) Low Pressure Seal Test (MPa)
Single Disc
Swing Check
1
Valve & Wafer
Check Valve
Inspector 郑浩忠
Test Result Conformity
Approved By 王雪涛
Y-STRAINER
Shanghai Thinktank Process Management Co,.Ltd
TEST & INSPECTION REPORT
Customer: EI Power Technologies Sdn. Bhd.
PO 00009566 Date: 29th Aug, 2023
(913886-A)
No.:
Parts Item Valve's Photo and Packing Photo
1 Y-Strainer
Inspector 郑浩忠
Test Result Conformity
Approved By 王雪涛
TRANSFER PUMP
8.2 Site Testing & Commissioning Reports
To be furnished later upon completion of testing CX1-CX5
SECTION 9
MODIFICATIONS
9. Modifications