2.

PROGRESS REPORT
Gabion Contruction Work

Project Title : Gabion Construction Work


Location : Lubuk Gaung, Dumai
PO No. : 8500001845 / PT Semesta Alam Permai
Month : September 2022

Progress Claim

Last Month This Month Cumulative


Weight Plan
No Item Description Unit Qty. Unit Rate (IDR) Amount (IDR) Remarks
(%)
Overall Ammount in IDR Overall Ammount in IDR Overall
Qty Actual Ammount in IDR (Actual) Qty Actual Qty Actual
Percentage (%) (Actual) Percentage (%) (Actual) Percentage (%)

1.0 Gabion Construction


a Site Preparation

- Site Clearing & Grubbing inclusive of


m2 2,231.0 5,000.00 11,155,000 0.21% 2,231.00 11,155,000.00 0.21% - - 0.00% 2,231.00 11,155,000 0.21% -
levelling and Site preparation

b Foundation Shore Protection

Timber pile dia. 5", length 4 m, every 50 cm ea 2,337.0 54,000.00 126,198,000 2.37% 1,562.00 84,348,000.00 1.58% 500.50 27,027,000 0.51% 2,062.50 111,375,000 2.09% 274.50

Timber matress, 3 layers of timber dia. 5",


ea 13,221.0 55,000.00 727,155,000 13.63% 8,520.00 468,600,000.00 8.78% 2,730.00 150,150,000 2.81% 11,250.00 618,750,000 11.60% 1,971.00
length 4 m

Geotextile non woven, tensile strength 40


m2 7,518.3 5,000.00 37,591,321 0.70% 1,128.90 5,644,500.00 0.11% 1,308.60 6,543,000 0.12% 2,437.50 12,187,500 0.23% 5,080.76
kN/m
Upper Stone layer, dia. 0.6m or 250 kg (see
m3 5,754.0 746,420.00 4,294,900,680 80.50% 1,557.61 1,162,631,256.20 21.79% 1,857.70 1,386,626,300 25.99% 3,415.31 2,549,257,556 47.78% 2,338.69
detail)

Total 5,197,000,001 97.41% 1,732,378,756.20 32.47% 1,570,346,300 29.43% 3,302,725,056 61.91%

PREPARED BY CHECKED BY APPROVED BY


PT. SWADAYA ABDI MANUNGGAL PT. SARI DUMAI OLEO PT. SARI DUMAI OLEO

Aep Supriatna Nasruddin Yudi Darmansyah Bernedi Nasution Ng Yik Choon


Project Manager Site Engineer QS Engineer Construction Manager Senior Project Manager