PROYEK PEMBANGUNAN BENDUNGAN LEUWIKERIS PAKET 5 -

WASKITA-ADHI (KSO)
GROUTING CEMENT MIX

PROJECT : Leuwikeris Multipurpose Dam Project GROUT PLANT No. : 02


LOCATION : TUNNEL 2 DATE : 30 Juni 2021
LOG No : SHEET :
GROUTING
Stage DEPTH (m) TIME PRESSURE MIX CEMENT
Prepared Injected Wasted
Hole ID REMARKS
From To Net Batch Volume Volume Volume Prepared Injected Wasted
No. From To kg/cm2 C:W
(h:m) (h:m) (h:m) (Liter) (Liter) (Liter) (Kg) (Kg) (Kg)
BG.TP2.R349A 0.00 0.00 13:17 13:20 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
13:25 13:28 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
13:32 13:35 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
13:41 13:44 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
13:48 13:51 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
13:54 13:57 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
14:01 14:04 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
14:09 14:12 0:03 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
14:16 14:26 0:10 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
14:24 14:34 0:10 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00
14:33 14:43 0:10 4 1:1 1 131.75 131.75 0.00 100.00 100.00 0.00 SISA DI BUANG
14:40 14:50 0:10 4 1:1 1 131.75 42.98 88.77 100.00 32.63 67.37
14:50 15:00 0:10 4 1:1 35.82 52.95 27.19 40.19
15:00 15:10 0:10 4 1:1 23.88 29.07 18.13 22.06
15:10 15:20 0:10 4 1:1 4.78 24.29 3.63 18.44
15:20 15:30 0:10 4 1:1 0.00 24.29 0.00 18.44

TOTAL 1:44 12 1581.00 1556.71 24.29 1200.00 1181.56 18.44

EMPLOYER CONSULTANT CONTRACTOR


Acknowledge by : Check by : Inspector Prepared by : Field Drilling Grouting Coordinator

( ) ( )
( Reja Kusnandar ) Accepted by : Drilling Grouting Engineer Submitted by : Drilling Grouting Engineer
Direksi

Date/Time : ( )
Date/Time : Date/Time : ( Ir. Akmal Bainnudin )