Installation Manual
Amendment Record
It is a requirement that you shall read carefully and comprehend each item in this manual before any
installation, operation, maintenance and usage of the elevator. If you have any trouble in fully understanding the
literal content, diagrams or pictures in this manual, please contact TK Elevator (China) for necessary technical
support. Please note that any incorrect installation, operation or maintenance may lead to potential abnormal
operation of the elevator and then possible loss of property or injury of persons.
1. The installation and maintenance personnel of elevator must have obtained relevant legal operating
certificate, and shall strictly observe the national and local regulations on safety, installation and maintenance
during operation. If the national or local regulations on safety, installation and maintenance are inconsistent with
this manual, please contact TK Elevator (China) for clarification beforehand.
2. The installation and maintenance personnel of elevator shall be professionally trained and instructed by TK
Elevator (China). If unfamiliar with the relevant knowledge on installation or maintenance of TK Elevator, they shall
immediately contact TK Elevator (China) for obtaining relevant information and instructions.
3. If inconsistency is found between any product mentioned in this manual and the actual one on the jobsite,
be sure not to carry out any installation, operation or maintenance without authorization, and meanwhile
immediately contact TK Elevator (China) for obtaining relevant information and instructions.
4. This manual has been scrutinized in technical details, and shall be immune from any prosecution for
incomplete information.
5. TK Elevator (China) will be exempted from any liabilities to the damage or losses arising from
nonobservance to this manual.
6. TK Elevator (China) expressly reserves the sole right to make changes to and update this manual at any
time without opinion inquiry or prior notice. Please obtain the up-to-date product information, data and operation
manuals via the official website mentioned below.
7. TK Elevator (China) reserves all the intellectual property rights and exclusive rights on this manual. Any
copying or distribution of any part of this manual in any form which is not authorized by TK Elevator (China) with
the express written approval is strictly forbidden.
8. Obtain the up-to-date product information, data and instructions of TK Elevator via the following ways:
Contents
1 Overview ...................................................................................................................................................... 1
2 Overall Structural Diagram of the Shaft .................................................................................................2
3 Installation Position of Component at Top Landing and Installation of Guide Rail ........................3
3.1 Installation of Guide Rail .......................................................................................................................... 4
3.2 Installation of Guide Rail Bracket ............................................................................................................5
4 Installation of Traction Machine, Machine Beam Assembly and Traction Sheave Cover ..............8
4.1 Installation of Traction Machine and Machine Beam ...........................................................................8
4.2 Installation of Traction Sheave Cover .................................................................................................... 9
5 Installation of Overspeed Governor and Governor Beam Assembly ............................................... 10
5.1 Installation of Overspeed Governor Beam ........................................................................................... 10
5.2 Installation of Overspeed Governor ....................................................................................................... 11
5.3 Installation of Tensioning Device ........................................................................................................... 12
5.4 Installation of Overspeed Governor Rope ............................................................................................ 13
5.5 Installation of Rope Clamp ..................................................................................................................... 14
6 Installation of the Rope ........................................................................................................................... 15
6.1 Reeving Method of the Rope ................................................................................................................. 15
6.2 Installation of Rope Hitch and Bracket of Load-weighing Device ................................................... 16
7 Installation of Counterweight Buffer, Counterweight Frame and Counterweight Filler.............. 17
7.1 Installation of Counterweight Buffer .................................................................................................... 17
7.2 Installation of Counterweight Frame .................................................................................................... 18
7.2.1 Installation of Counterweight Pulley ..................................................................................................... 18
7.2.2 Installation of Roller Guide Shoe ........................................................................................................... 19
7.3 Adding Counterweight Filler into Counterweight Frame ................................................................. 20
7.4 Adjustment of Buffer .............................................................................................................................. 22
7.5 Adjusting Anti-rebound Device of Rope ............................................................................................. 22
7.6 Installing Protective Cover for Counterweight Pulley ....................................................................... 23
7.7 Installing Counterweight Guard............................................................................................................ 24
8 Installation of Lock Lift Plate and Blocking Device ........................................................................... 25
8.1 Installation of Lock Lift Plate and Baffle Block Assembly ............................................................... 25
8.2 Installation Position of Lock Lift Plate and Baffle Block Assembly................................................ 26
8.3 Installation of Lower Blocking Device.................................................................................................. 27
9 Installation of Electrical Equipment in the Shaft ............................................................................... 28
9.1 Installation of Traveling Cable ............................................................................................................... 28
9.2 Protective Part of Traveling Cable ........................................................................................................ 30
10 Installation of Cam ................................................................................................................................... 31
11 Installation of Car .................................................................................................................................... 32
11.1 Installation of Buffer ............................................................................................................................... 32
11.2 Installation of Car .................................................................................................................................... 33
11.2.1 Installing Car Bottom.............................................................................................................................. 33
11.2.2 Installing Upright and Lower Guide Shoe ........................................................................................... 34
11.2.3 Installing Car Panel ................................................................................................................................. 35
11.2.3.1 Installing Door-side Car Panel ............................................................................................................... 38
11.2.3.2 Installing Car Roof................................................................................................................................... 39
11.2.3.3 Installation of Door Lintel....................................................................................................................... 40
11.2.3.4 Installing Car-roof Toe Guard Plate ....................................................................................................... 41
12 Installation of Glass Car ......................................................................................................................... 42
Copyright as per GB/T 19827 I/II Product Design Center (China)
R100005259E Ver: A
12.1 Unpacking Check .................................................................................................................................... 42
12.2 Relevant Installation Work Required to Be Completed .................................................................... 42
12.3 Installing Glass Car ................................................................................................................................. 42
12.3.1 Process Flow of Installation................................................................................................................... 42
12.3.2 Car Mounting Sequence of Square Panoramic Elevator .................................................................. 42
12.3.3 Instructions on Applying Sealant to Glass .......................................................................................... 50
12.3.4 Inspection after the Completion of Installation ................................................................................. 52
13 Installation of Top Beam Assembly ...................................................................................................... 53
13.1 Installation of Upper Guide Shoe .......................................................................................................... 54
13.2 Installing Car-roof Pulley........................................................................................................................ 55
13.3 Installing the Latch ................................................................................................................................. 56
13.4 Installing Top Beam................................................................................................................................. 57
13.5 Connection of Safety Gear and Pulling Device .................................................................................. 58
13.6 Inspection of Safety Switch .................................................................................................................. 59
13.7 Installation of Rope Fixing Beam and Protective Cover ................................................................... 60
13.8 Installing Top Beam Cover ...................................................................................................................... 61
13.9 Installing Lower Guide Shoe.................................................................................................................. 62
13.10 Adjustment of Roller Guide Shoe and Guide Rail .............................................................................. 63
13.11 Installing the Car Roof Protection Balustrade .................................................................................... 64
1 Overview
1.1 Introduction
This manual applies to the installation of machine-room-less (hereinafter referred to as MRL) elevators.
This manual only describes the assembly relations and assembly requirements of the relevant components,
and please refer to the corresponding documents from TKE for the relevant installation technology.
The installation work is closely related to the customers. With a view to successfully carrying out the work
and improving the efficiency, the installation personnel must maintain good communication with the customers
and try to gain as much support as possible from the customers for the installation work.
Note: This manual concerns the methods of installation with scaffold. For the methods of installation
without scaffold, please refer to the materials relevant to installation without scaffold from the Installation
Department.
Traction
machine
Overspeed Controller
governor
Traveling cable
Counterweight
guide rail
Lower blocking
device
Car
Overspeed governor
tensioning device
Rail
M12 × 25 Bolt
1
2
2 1
Detailed components:
1. M10 anchor bolt; 2. Counterweight-rail clip assembly; 3. Car-rail clip assembly;
Installation instructions:
1. Each guide rail shall be provided with at least two sets of rail brackets with a distance not more than 2.5 m in
between.
2. The positions of the rail brackets shall take into account the positions of the fishplates. The rail brackets shall
not interfere with the fishplates and they shall be mutually staggered. The distance between each rail bracket
and rail joints shall be at least 300 mm.
3. The specific installation positions of rail brackets shall be determined in accordance with relevant
requirements in the construction layout drawing of the elevator shaft.
M8 × 30 Bolt
2
M10 × 30 Bolt
M10 × 30 Bolt
Detailed components:
1. M10 anchor bolt; 2. Counterweight-rail clip assembly; 3. Car-rail clip assembly; 4. Attachment bracket;
Installation instructions:
1. The specific installation positions of top combined-type rail brackets shall be determined in accordance with
relevant requirements in the construction layout drawing of the elevator shaft.
2. It is required to hoist in place the machine beam before connecting and installing the attachment bracket for
top combined-type rail brackets.
3. It is required to complete the position adjustment of machine beam before securing the fasteners of the
attachment bracket for top combined-type rail brackets.
2 1 3
2 4
3
1
Detailed components:
1. Car rail; 2. Car rail bracket; 3. Counterweight rail; 4. Top common rail bracket; 5. Governor beam assembly; 6.
Machine beam assembly
For the specific layout, see the relevant GAD of the project.
Sheave Cover
Washer 70 × 55
Washer 90 × 75
M8 × 30 Bolt
M12 × 35 Bolt
Detailed components:
1. Traction machine; 2. Machine beam assembly; 3. Counterweight rail; 4. Car rail
Installation instructions:
Traction machine, machine beam assembly and controller have been assembled in factory; hoist them to their
installation positions, fix them to counterweight rail and car rail after confirming that the height difference
between the top surfaces of car rail and counterweight rail is within ±5 mm, then make adjustment with shims;
upon completion of the adjustment, the height difference in a horizontal plane shall be within ±1 mm. Make the
top of guide rail press against the baseplate of machine beam assembly, and secure the bolts after proper
adjustment.
M6 × 18 Hexagon
socket bolt
Detailed components:
1. Traction machine; 2. Machine beam assembly; 3. Traction sheave cover; 4. Acrylic sheet
Note: Controller is hidden from the view for the convenience of illustration.
2
3
M12 × 45 Bolt
M12 × 45 Bolt
Detailed components:
1. Governor beam; 2. Connecting plate; 3. Governor bracket
M10 × 30 Bolt
Detailed components:
Overspeed governor; 2. Governor beam
Installation instructions:
Please read the accompanying installation instructions for overspeed governor before installation.
a) Prior to using overspeed governor, all of its moving parts must be checked to ensure their flexible
movement and make sure all the contact switches are at normal state.
b) The client is not allowed to dismantle or adjust the overspeed governor at will, and collision is forbidden
during transport.
c) It is strictly forbidden to apply lubricant to the overspeed governor rope.
d) The overspeed governor shall be kept clean to a certain degree; mud, foreign matters and too much
dust may affect its performance.
Installation instructions:
1. Installation height H = 500 ± 10 mm
Overspeed Tensioning
governor rope device
Overspeed Overspeed
governor governor rope
Installation instructions:
Hang the overspeed governor rope with its upper end hanging on the governor pulley and its lower end
wrapping around the tension pulley. Both ends of the rope are connected to the rope hitch plate of the
safety-gear pulling mechanism on the car frame.
(35 mm)
Pulling mechanism of
safety gear
Overspeed
governor rope
U-bolt
clamping the
final segment
of the rope
Clamping plate
clutching the
working
segment of the
rope
Installation instructions:
1. Three sets of rope clamps are needed for each connecting position. The distance (A) between every
two rope clamps is approximately 36 mm.
2. Make sure that the clamping plate clutches the working segment of the rope and the U-shape bolt
secures its final segment.
3.Rational force of every rope clamp shall be taken into consideration while fixing the clamp. Rope clamp
that is the farthest away from safety lifting assembly shall not be fixed alone at first; rope clamp (i.e., the
first rope clamp) that is the closest to safety lifting assembly shall be as close to the assembly as possible.
At the same time, assure the rope clamp be correctly tightened without damaging outer steel wire of the
rope.
1 2 3 4
Rope hitch on
counterweight
side
Counterweight
pulley
Traction sheave
Car-roof pulley
Car-roof pulley
Rope hitch
on car side
1 2 3 4
Installation instructions:
The rope used by anti-twist device shall be the redundant rope on site.
1 2
Detailed components:
1. M12 Nut; 2. Rope clamp; 3. Bracket of load-weighing device
Installation instructions:
1. Bracket of load-weighing device is required to be installed between the two sets of nuts.
2. The rope hitch at overspeed governor side is equipped with springs, while the rope hitch at the machine
side is not equipped with them.
3. Each set of rope hitch only requires one rope clamp assembly; make sure that the clamping plate
clutches the working segment of the rope and the U-shape bolt secures its final segment.
4. The distance H between the rope hitch top at the machine side and the upper surface of the machine
beam is approximately 40 mm.
Counterweight Filler
Socket
M16 × 40 Hexagon
socket screw
Detailed components:
1 Counterweight frame; 2 Counterweight buffer
Installation instructions:
The counterweight buffer shall be installed to the underneath of counterweight frame, where the two shims
are not required to be removed during the installation of buffer; the fixing bolt of buffer shall be fixed
temporarily without being fastened, and secure the bolt after the adjustment to buffer is completed.
Rope fixing
beam
M12 × 30 Bolt
Detailed components:
1. Counterweight frame; 2. Counterweight pulley
Installation instructions:
After installing counterweight deflection pulley onto the counterweight frame, slightly loosen the bolts for
rope guard plate and rope fixing beam of the rope pulley and do not tighten them for the moment; make
adjustment upon installation of the rope.
Adjusting shim
M10 × 30
Hexagon socket bolt
2
1
Adjusting shim
2
1
M10 × 30
Hexagon socket bolt
Adjusting
shim
Middle
CWT
filler
The bottom
1
two CWT fillers
Detailed components: 1. Counterweight frame; 2. Counterweight filler; 3. Counterweight filler fixing plate
Installation instructions: Installation of the fillers is a link being most vulnerable to accidents and thus it is
required that the installation personnel carry out the installation in strict accordance with the relevant process
documents from our company; the elevator balance coefficient shall reach 40% to 50% upon installation.
Copyright as per GB/T 19827 20/65 Product Design Center (China)
R100005259E Ver: A
b) Installation Diagram of Counterweight Filler (Compound CWT Filler + Cast-iron CWT filler Mixed Together)
The top
one cast-iron
CWT filler
3
Two compound
CWT fillers
(15 kg per filler)
Compound
CWT filler
Cast-iron
CWT Filler
Detailed components: 1. Counterweight frame; 2. Counterweight filler; 3. Counterweight filler fixing plate
Installation instructions: 1. In the case that the counterweight fillers are composed of compound counterweight
fillers mixed with cast-iron counterweight fillers, one cast-iron filler shall be installed at the top, and the rest
cast-iron fillers shall be installed to the lower position as shown in the diagram above; 2. The other installation
requirements are the same as those in a) specified above.
Adjustment of Buffer
1 2 3
1
2
2
This component is
transparentized for
illustrative purposes.
Detailed components:
1. Rope; 2. Anti-rebound device (in three positions)
Instructions on adjustment:
Upon installation of the traction rope on the counterweight pulley, its anti-rebound device of the rope must be
adjusted. The distance between the anti-bound device and the rope is required to be within 3 mm.
Copyright as per GB/T 19827 22/65 Product Design Center (China)
R100005259E Ver: A
M5 × 10 Hexagon socket
screw 3
Detailed components:
1. Protective cover assembly for counterweight pulley; 2. Counterweight frame; 3. Counterweight pulley
Installation instructions:
When installing protective cover of counterweight pulley onto counterweight frame, be sure to keep the
distance unchanged between the two upper anti-rebound devices and the ropes.
Detailed components:
1. Counterweight guard
Installation instructions:
There are four guard plates in all for the upper, lower, front and rear sides of counterweight; pay attention
to the clearance between guard plate and car guide rail during the installation, and too small clearance
will lead to the interference and friction between moving counterweight and car rail, which shall be
avoided.
M10 × 40 Bolt
4
M10 × 40 Bolt
Detailed components:
1. Baffle block assembly; 2. Lock lift plate; 3.Rail clip assembly; 4. Rubber block
Installation instructions:
1. Install lock lift plate and baffle block assembly onto the top rail (at the same side of lock lift device).
2. Please refer to 13.3 Installation of Latch for the installation of lock lift device.
3. Baffle block assembly can be installed symmetrically according to the actual situation.
8.2 Installation Position of Lock Lift Plate and Baffle Block Assembly
Top of shaft
L1
L2
Installation instructions:
1. The distance between bottom of baffle block assembly and top of rail: L1= 1000 mm;
2. The distance between center of lock lift plate and bottom of baffle block assembly: L2 = 500 mm.
Inactive state:
M10 × 40 Bolt
Active state:
Installation instructions:
1. When the blocking device is in active state, the distance (H) between square bar and the pit floor shall be
approximately 1.5 m.
2. During pit maintenance, the blocking device shall be manually switched to active state, while during normal
operation of elevator, it shall be under inactive state.
Top of
shaft
535
Traveling
cable
Pit depth
Installation instructions:
Determine the position configured for the traveling cable in the shaft according to the requirements in the
construction layout drawing of the elevator and the relevant configuration in the attachment.
M12 × 40 Bolt
M6 × 25 Bolt
2 3
M16 × 40 Bolt
Detailed components:
1. Shaft cable bracket; 2. Car-bottom cable bracket; 3. Upright cable bracket; 4. Protective steel wire
Installation instructions:
Firstly install the seat of shaft cable bracket onto shaft wall, then fix the traveling cable into cable bracket
via bracket clamping plate; afterwards, install car-bottom cable bracket and upright cable bracket in
place, and fasten the traveling cable into car-bottom cable bracket via clamping plate.
Steel wire
Common
rail bracket
Electrical
tape
Installation instructions:
1. Steel wire shall be installed from the bottom rail bracket, and the number of the rail brackets covered is "(total
number of rail brackets + 1) / 2", which shall be rounded up to an integer.
2. Firstly fix the steel wire to the top rail bracket, then straighten the steel wire and fix it to the bottom rail
bracket.
3. Upon winding the wire onto the rail brackets at the two ends, it is required to cut off the excessive wire, and
wrap electrical tape around the wire end to prevent scratches.
10 Installation of Cam
Upper cam
Overspeed
governor beam
M8 × 30 Bolt
M6 × 14 Bolt
Lower cam
M6 × 14 Bolt
M10 × 30 Bolt
Detailed components:
1. Bracket of upper cam; 2. Bracket of lower cam; 3.Striking block; 4. Shim
Installation instructions:
Cam shall be used together with final limit switch, and please refer to Installation Manual of MC2-E Positioning
System for the specific installation position and adjusting method.
11 Installation of Car
2 3
Detailed components:
1. Car bottom; 2. Shim; 3. Buffer
Installation instructions:
Pre-install the buffers. Install four buffers onto the car bottom and secure them. Insert shims between
buffer and car bottom, and five shims shall be provided in advance for the clearance between each buffer and
the car bottom. After completing the adjustment regarding the elevator installation, in the case of elevator
leveling at the bottom landing, ensure that the distance is 10 mm between the bottom of buffer and the impact
area of the buffer on the pit floor by changing the number of shims.
Installation instructions:
Hoist the car bottom into the shaft, put it in place with the distance between the left / right side of the car
bottom to the corresponding guide rail being identical each, and adjust the distance between the car bottom
and the door plumb line. Adjust the car bottom with shim(s) so that its horizontal and lengthwise levelness is
not greater than 2/1000.
1
M12 × 40 Bolt
|A1-A2|≤1mm;
|B1-B2|≤1mm;
|C1-C2|≤1mm.
Detailed components:
1. Upright; 2. Car bottom; 3. Lower guide shoe
Installation instructions:
Connect the uprights and lower guide shoes to the car bottom via bolt assemblies. Upright and lower guide
shoe shall be secured with the same bolt assembly.
The verticality of the upright shall not exceed 1 mm without twisting. If the requirements cannot be met,
use thin shim(s) to carry out the adjustment between the upright and the connecting faces of bottom beam,
and the total thickness of the adjusting shim(s) for each connecting face shall not exceed 1 mm.
Take the car guide rail as the measuring datum, use the steel ruler to carry out measurement, and make
sure that the clearance between each side of the upright top and the corresponding side blade of guide rail shall
be identical, that the clearance between each side of the upright bottom and the corresponding side blade of
guide rail shall be identical, and that the clearance between the front face of upright and the end face of guide
rail shall be identical vertically. Upon the adjustment, tighten the connecting bolts.
Table 3-1 Dimensions of Car Panel for the Car with the Load of 320 kg or 400 kg
Load (kg) CW (mm) CD (mm) DW (mm) A (mm) B (mm) C (mm) E (mm) F (mm)
320 900 1100 700 1100 950 1100 125 125
400 1100 1100 800 1100 1150 1100 125 225
400 1100 1100 800 1100 1150 1100 225 125
400 1100 1100 800 1100 1150 1100 175 175
Door height ± 1 mm
Door width ± 1 mm Door width ± 1 mm
Top view of car panel Front view of car panel Elevation view of car panel
|A1 - A2| 0.5 mm, |B1 - B2| 1 mm, |C1 - C2| 1 mm, |D1 - D2| 1 mm.
2 3
M6 × 20 Bolt
M6 × 20 Bolt
Detailed components:
1. Car bottom; 2. Side panel; 3. Rear panel
Installation instructions:
The enclosure panels shall be installed in the way of stacking layers inside the car. To be specific, installers
inside the car firstly fix the rear panel and side panels of the bottom layer onto the car bottom via hexagon
socket bolts and shim(s), then they install the rear panel and side panels of the upper layer until the whole
enclosure panels are completely installed. Only hexagon socket bolt assemblies are used for the connection
between car panels.
Note: Check the light proof sponge in the seams between car panels.
Installation instructions:
1. Door-side car panels shall be connected to side panels via M6 × 20 hexagon socket bolt assemblies.
2. Connect the door-side car panels and the car bottom via M6 hexagon socket bolts that are reserved on car
bottom.
M6 × 12 Bolt
1
M12 × 40 Bolt
Detailed components:
1. Car roof; 2. Upright
Installation instructions:
Firstly hoist car roof onto the predetermined position: Fasten the two ends of the belt to the front part of
car roof to hoist the car roof into the shaft, adjust the car roof to the right position (namely the decorative
surface of car roof faces towards the landing door entrance), then slowly place the car roof under the top beam
of car frame by using the chain hoist right above door entrance. Use the other chain hoist and belt to pull the
rear edge of car roof, and coordinate the two chain hoists to make the car roof horizontally rest above the
upright.
Lower the car roof that has been hoisted to the predetermined position for connecting to the car panels
via hexagon socket bolt assemblies, and for connecting to the uprights via bolt assemblies reserved on uprights.
Use tape to measure the diagonal lines of door entrance, and the difference between them shall not be greater
than 5 mm. Finally secure all the connection bolts.
Note: Before installing the top beam, it is required to install COP cables in advance.
M6 × 12 Bolt M6 × 12 Bolt
Detailed components:
1. Car roof; 2. Door lintel; 3. Door-side car panel
Installation instructions:
Both the connection of door lintel and door-side car panel and the connection of door lintel and car roof
shall use hexagon socket bolt assemblies.
2
1
Detailed components:
1. Car-roof toe guard plate; 2. Car roof
Installation instructions:
Toe guard plate shall be connected to car roof via M4 self-tapping screw. During the installation, note the
distance from toe guard plate to top beam and to door header, and avoid the interference.
Prior to unpacking, ensure that the workplace shall be spacious, tidy and free from water.
Only the car components corresponding to the elevator number can be used for installation,
and the car components for other elevator number shall not be borrowed and used.
If the quality of the product is detected to be abnormal, it shall not be installed forcibly.
Be sure to report it to the project manager immediately and then obtain the handling suggestions from the
factory.
Prior to the installation of glass car, the relevant corresponding installation work is required to be completed
for the elevator.
1) Installation of shaft components such as guide rails, rail brackets, etc. shall be completed.
2) Assembly of car bottom, which is supported at a certain height above the pit according to the safe
buffering distance, shall be completed.
3) Other necessary installation shall be completed.
Here the panoramic elevator car is taken as an example for introducing the installation process of three-
side glass car, which can be used as reference for one-side glass elevator car.
Preparations→installing car bottom→installing car panels→installing car roof→installing decorative sheet of
car bottom→installing vertical beam→installing decorative sheet of car roof→installing handrails→installing
decorative sheet of front panel→applying sealant and other tail-in work.
Installation instructions:
Before installation, remove the protective films from the connection faces of all the car panels, then install the
car bottom with M6 × 20 flat head Allen bolt so that the car bottom is connected with the rear bottom sill (note
that the one with hardy holes shall be installed inside the car). Use hammer to correct the perpendicularity of
car panels to car bottom so that it is not greater than 5 mm.
The exterior
surface that is
provided with
double faced
adhesive tape
shall be the upper
side of the car.
Installation instructions:
Install the left and right panels in sequence. Prior to installing the left and right panels, firstly lift them up,
clip fasteners into the hardy holes in rear bottom sill, use hexagon socket bolts to fix the left and right glass
panels (note that the left and right panels are an entire pane of panel wherein the surface with double-sided
tape is the exterior side and also the top side of car panel); during transporting the panels, please note that the
rear glass is movable, which shall face upwards without bearing of any force during its transportation; pay
attention to the marking on rear glass (avoiding installing it in reverse); fix the rear glass with suction cups,
insert the glass into the long seam in the rear bottom sill , fasten the glass with rear top sill, then adjust the
positions of the three panes of glasses.
Installation instructions:
The decorative sheets for car bottom are composed of three pieces of materials, rear C-shaped enclosing
sheet, one left sheet and one right sheet. Upon confirming that they are in good condition, clip them into the
car bottom. In the later step, secure the car bottom with the self-tapping screws for car bottom cover plate.
8) Decorative sheets for car roof:
3 4 2
Detailed components:
1. Decorative sheet for car roof; 2.C-shaped decorative sheet for car roof; 3.Decorative sheet for car roof;
4.Bracket
Installation instructions:
See the diagram for the installation of decorative sheet for car roof, wherein the left and right decorative sheets
are spliced ones, which shall be inserted into the inner side of uprights for installation, and the C-shaped sheet
is integrated one. Note that check whether the decorative sheets are in good condition before removing the
sticker of the rear double-sided tape. Press the double-sided tape with force upon completion of sticking it; the
inner side of the decorative sheet shall be connected to car roof via brackets, and use ST4.2 × 16 self-tapping
screw for the connection of the brackets and car roof.
Installation instructions:
The handrails shall be installed inside the car, so it is required to fix fasteners onto left and right car panels
in advance before installation of handrail. Upon securing the fasteners, firstly fix the rear handrail, clip the
handrail into fasteners in order, then turn the bolts under the handrail with Allen key, and secure the bolts so
that the handrail will not get loose; then fix the handrail onto the left and right car panels with hexagon head
bolt.
Decorative
sheets for
front panels
Installation instructions:
Upon completion of the installation of handrails, fix decorative sheets onto left and right front panels with
(M4 × 12) cross-recessed countersunk head screws.
Installation instructions:
Upon completion of the installation of car, the cover plate for car bottom shall be installed. And also the
cover plate and the installed car-bottom decorative sheet shall be fixed to the car bottom stiffener via hexagon
socket cheese head screws (M4 × 12 flat head).
Step one: Complete the installation of the glass according to the layout position in general assembly
diagram and adjust the position of the glass between the top and bottom sills. Generally the clearance shall be
2-3 mm between the glass and the interior/exterior decorative sheets, and the clearance shall be 3-5 mm
between two pieces of glass, this is the foundational work and must be accomplished well, otherwise no
remedying work is possible after applying sealant.
Note: The adopted sealant shall be neutral transparent glass glue.
Step two: Bonding interior decorative sheets: Before bonding them, check whether the interior decorative
sheets fit the car panel to ensure appropriate assembling. Clean the bonding surface to be free from dust or
greasy dirt; apply sealant or adhesive tape onto the interior side face (or the outer surface of sill) of the interior
decorative sheet, pay attention to the top, down, left and right positions when bonding the interior decorative
sheets and bond them only after confirmation; after bonding, external force is required to be continuously
applied on them for 12 hours to strengthen the bonding, then external force can be removed.
Step four: Select the proper type of sealant opening according to different gaps for sealant.
Step six: After the sealant is scraped, remove the masking tape in the reverse direction of applying sealant;
pay special attention to protect the position of masking tape, which shall not be touched or crashed in 12 hours;
12 hours later, check whether it needs to be corrected or repaired (note that after the masking tape is removed,
do not make repair immediately, but wait for 12 hours before repairing it). The method is the same as above, i.e.,
paste masking tape before applying sealant.
Step seven: Finally, remove the protective film after confirmation (note that the protective film shall be cut
off along the bending edge of steel plate before being removed).
Overall Layout
1 2 3
Entrance/Exit
Detailed components:
1. Traction machine; 2. Latch; 3. Top beam; 4. Position of pulling point
Installation instructions:
1. Firstly install the components of top beam, guide shoe, the latch, car-roof pulley, etc. onto the top
beam, and then install them together onto the car roof.
2. The diagram here shows the layout of the traction machine installed on the left side, while the layout
of the traction machine installed on the right side shall be symmetrical.
Detailed components:
1. Upper guide shoe; 2. Top beam; 3. Adjusting shim
Installation instructions:
Connect the upper guide shoe to the top beam via the hexagon socket screw, spring washer and large flat
washer of top beam.
Detailed components:
1. U-bolt (M10), nut with flange, thin nut; 2. Car-roof pulley
Installation instructions:
Connect car-roof pulley to top beam via U-bolt.
6
4 3 2 1
7 8
Detailed components:
1. Latch; 2. Bracket; 3. M6 × 16 Hexagon socket screw, spring washer, flat washer; 4. Thumbscrew, spring washer,
flat washer;
5. M4 × 30 Pan head screw assembly; 6. Safety switch; 7. Bracket of switch; 8. M6 × 25 Hexagon socket bolt
assembly
Installation instructions:
Lock lift device is installed on the top beam of car frame. Please install the switch to the position as shown in
the diagram/sign.
4 3 5
Detailed components:
1. Latch bar; 2. Bracket; 3. Top beam; 4. Car roof; 5. M12 × 30 Bolt with flange
Installation instructions:
Remove latch bar and bracket before installing the top beam. Connect the top beam and car roof via flange
bolts, and the tightening torque of the bolts shall comply with the requirements in the standard. After the
bolts are secured, re-install the latch bar and bracket.
Detailed components:
1. Large washer, split pin
Installation instructions:
Connect the safety gear to the pulling mechanism and fix them with large washer and split pin.
4 2 3
Detailed components:
1. Connecting rod of the pulling mechanism; 2. Bracket of safety switch; 3. Safety switch cam; 4. Safety
switch
Inspection instructions:
Check the relative position between the safety switch and the cam. Under the released state, the safety
cam rear and the switch contact center shall be in the same plane, and safety switch shall be
disconnected in the case that the brake shoe of safety switch operates.
Before the cam operates, the switch contact shall be released, and the switch shall be connected; after
the cam operates, the switch contact shall be pressed tightly, and the switch shall be disconnected.
2 1
3 3
Detailed components:
1. Car-roof pulley; 2. Rope; 3. M6 × 16 Hexagon socket screw; 4. Protective cover; 5. Rope fixing beam
Installation instructions:
Fix the rope fixing beam onto protective cover via M6 × 16 hexagon socket screw, spring washer, and flat
washer; the protective cover is connected to the top beam with M6 × 16 hexagon socket screw, spring
washer and flat washer.
3 2
Detailed components:
1. Top beam; 2. Cover; 3. M6 × 12 Pan head screw
Installation instructions:
Install the cover onto the top beam with M6 × 12 pan head screws, spring washer and flat washer.
1 2
Detailed components:
1. Lower guide shoe; 2. Upright; 3. M12 × 40 Bolt assembly; 4. Adjusting shim; 5. Adjusting shim
Installation instructions:
Connect lower guide shoe to upright with the M12 × 40 bolt assembly of upright.
Clearance of 1-2 mm
Detailed components:
1. Upper guide shoe; 2. Lower guide shoe; 3. Adjusting shim
Installation instructions:
Adjust the clearance in accordance with the requirements in the diagram above by changing the number
of adjusting shims.
2 3 1 6
2 1
5 4
5 4
1 2
7 6
Detailed components:
1. M6 × 16 Bolt with flange, nut with flange; 2. Top beam; 3. Spring plunger; 4. M4 × 10 Slotted cheese-head
screw
5.M4 × 30 Pan head screw, nut with flange; 6. Socket, split pin; 7. M6 × 40 Bolt, flat washer, locknut
Installation instructions:
1.Connect the protection balustrade to top beam with M6 × 16 bolt with flange and nut with flange.
2. The upper protection balustrade may be moved upwards or downwards, and extended or retracted to the
highest or lowest position; use index plunger to fix the upper protection balustrade.
3. Regarding the upper balustrade and lower balustrade of the three-sided protection balustrade, they shall
be connected in the middle by socket and split pin.
4. Fix the warning sign onto the upper protection balustrade with M6 × 40 bolt, flat washer and locknut.