Professional Documents
Culture Documents
Lecture W10 - Delay of Works, EOT and LAD
Lecture W10 - Delay of Works, EOT and LAD
Lecture W10 - Delay of Works, EOT and LAD
Liquidated
Ascertained
1 Damages
Implication for 2
non-completion
3
Extension of
Time
Completion of Work
What are the Contractor’s
main roles?
In project management book, clients want certainty as to time, cost and quality.
Without any specific completion date, there can be no provision for Liquidated and
Ascertained Damages as time is considered at large situation.
It is very common to state the date by which the completion is required. In PWD 203A
and PAM 2018, the date of completion is inserted in the Appendix Section.
Date of Completion
There is no requirement for Contractors to state the completion date when tendering
for the works.
Instead, they are required to insert the construction period in the tender form.
The date for completion is then calculated by the Contract Administrator from the date
of Site Possession stated in the Letter of Acceptance.
Extension of Time
When time overruns and the employer allows the contractor to continue
without asserting that time is of the essence, then:
Provision - mitigation
Clause 23.10
Architect’s power to review
What happened if there are delay?
If delay caused by Employer and Employer does not extend the time, time
becomes at large.
Contractor only required to complete within reasonable time, not contracted time.
But contractor can be liable for general damages for not completing within
reasonable time.
Definition of Extension of Time
“Is a time which reimbursed by one of the contract sides to the other as
compensation for project events and conditions, prevented that side from execute
portion of project work.”
It is always the Contractor who must prove the need for EOT with the support of documents.
Administrator must communicate his decision within the contractual time (or
within a reasonable time if no contractual time), otherwise extension can be
deemed approved.
Condition Certifying
Time to apply Procedure
precedent person
Relevant Certificate of
Mitigation
events EOT
Time to Apply
If in the opinion of the said officer named in Appendix the completion of the Works
is likely lo be delayed or has been delayed beyond the Date for Completion stated
in Appendix or beyond any extended Date for Completion previously fixed under
this Clause due to any or more of the following events:
43.0 DELAY AND EXTENSION OF TIME
d) directions given by the S.O., consequential upon disputes with neighbouring owners
provided the same is not due to any act, negligence or default of the Contractor or any
sub-contractor, nominated or otherwise;
e) S.O.'s instructions issued under clause 5 hereof, PROVIDED THAT such instructions are
not issued due to any act, negligence, default or breach of this Contract by the Contractor
or any sub-contractor, nominated or otherwise;
43.0 DELAY AND EXTENSION OF TIME
f) the Contractor not having received in due time instructions in regard to the nomination of
sub-contractors and/or suppliers provided in this Contract,
necessary instructions, drawings or levels for the execution of the Works from the S.O. due to
any negligence or default of the S.O.
PROVIDED THAT the Contractor shall have specifically applied in writing on a date which having
regard to the Date for Completion stated in Appendix or to any extension of time then fixed under
this clause, was neither unreasonably distant from nor unreasonably close to the date on
which it was necessary for him to receive the same
g) the Contractor's progress of works being adversely affected by the delay on the part of the
Government to effect interim payments which are due to the Contractor in accordance with
the Contract PROVIDED THAT the Contractor had given written notice to the S.O. of any such
delay which affects the progress of his work;
h) delay in giving possession of the Site as provided under clause 38.4 hereof other than claim
in effecting insurance and Performance Bond
43.0 DELAY AND EXTENSION OF TIME
then the officer named in Appendix may if he is of the opinion that the extension of
time should be granted, so soon as he_ is able to estimate the length of the delay
beyond the date or time aforesaid issue a Certificate of Delay and Extension of Time
giving a fair reasonable extension of time for completion of-the Works.
PROVIDED THAT all such delays —are not due to any act, negligence, default or
breach of contract by the Nominated Sub-contractor and/or Nominated Supplier and/or
the Contractor, or any of the servants-or agents of such Nominated Sub-contractor or
Nominated Supplier or the Contractor.
PROVIDED ALWAYS that the Contractor has taken all reasonable steps to avoid or
reduce such delay and shall do all that may reasonably be required to the satisfaction
of the S.O. to proceed with the Works.
PROVIDED FURTHER that the Contractor shall not be entitled to any extension of time
where the instructions or acts of the S.O. are necessitated by or intended to remedy any
default of or breach of contract by the Contractor.
Issues
Example:
In construction main contracts, Contractors may be entitled to claim
from Employers, direct loss and expenses in the event the
Employers causes delays to the progress of the works
(unliquidated damages)
Equitable
Damages
Remedies
Dunlop Pneumatic Tyre Ltd. v. New Garage & Motor Ltd. [1915] AC 79
Stipulated sum is extravagant and unconscionable in comparison with the greatest lost
conceivable.
Clydebank Engineering & Shipping Co. Ltd. v. Don Jose Ramos [1905] AC 6, at p.10
If the breach is in relation to paying a sum of money, the Liquidated Damages is greater
than the sum to be paid.
Ford Motor Co. v. Armstrong [1915], 31 TLR 267
A presumption – it is a penalty when the Liquidated Damages is compensation for breach
of contract for various events some of them are serious and others are trifling.
Difficulty of estimation of the loss is no bar to maintain that the Liquidated Damages is
genuine pre-estimate.
Definition of Liquidated Damages
Selva Kumar A/L Murugiah v. Thiagarajah A/L Retnasamy [1995] 1 MLJ 817
Setegap Bhd (in creditors’ voluntary winding up) v. Ranhill Engineers and
Constructors Sdn Bhd [2011] 6 MLJ 684
Look at this case
1. Affirms the rule on acts of prevention setting time at large. The following
passage appears on p. 9 of the report:
In the absence of an express provision, the consequences of the
occurrence of an act of prevention…was that the entire extension of time,
completion date and liquidated and ascertained damages code was
displaced by a general contractual duty to complete the works within what
in all the circumstances was a reasonable time from the date of the act of
prevention … failing which the contractors would be liable for unliquidated
damages for breach of contract in failing to complete within a reasonable
time.
And this case too
Two Principles
Peak Construction was the main contractor, Liverpool Corporation was the employer and McKinney
Foundation was the nominated piling subcontractor.
The piling NSC did not do a good work - the piles were defective; stop work order issued.
Due dilatoriness of Liverpool Corporations, the stop work lasted 58 weeks although the remedial work
took only 6 weeks.
The Contract Administrator issued no Extension of Time and the Employer claimed Liquidated
Damages against the Main Contractor.
The MC brought action against the piling NSC to recover the LAD paid to the employer.
The court held that the Liquidated Damages clause should be strictly construed contra proferentem.
Thus, the Employer was not entitled to Liquidated Damages for delays which they were substantially
responsible.
Damages
It is a form of compensation payable to the innocent party who would have
Definition
suffered (translated into monetary value) as a result of the breach
of Damages
committed by the guilty party.
This remedy is always available under the contract for construction. Unlike the remedy for
termination which is only available in cases of serious breach of contract.
It is the normal mechanism for claiming General Damages, most contracts include the
provision for Liquidated Damages or popularly known as Liquidated and Ascertain
Damages.
LAD provisions are in principle perfectly acceptable in the construction contract and
should be encouraged.
It will enable the parties (the Employer and the Contractor) to know from the start as
much as possible about the risk they bear if they commit a breach of contract.
It will save both parties the time and money on arbitration or litigation to claim for
general damages when the breach occur.
Penalty
However, the problem is that, as the law always recognised that they are capable of
operating rather harshly in cases where the amount to be paid of forfeited is
GREATLY IN EXCESS of the actual loss caused by the breach of the Contract.
The most important aspects of the courts’ control of the LADs is their insistence that
a PENALTY CLAUSE (which means an attempt to terrorise the Contractor into
completing on time) is unconscionable and wholly unenforceable.
In our case, it is important for the Employer to prove his actual loss before he can
claim for damages due to the delay on the part of the contractor.
The terms used in the contract are not conclusive, though they may be persuasive.
In deciding into which category a particular contract term falls, account must be
taken of circumstances at the time of making the contract, not at the time of
breach.
Penalty
The most notable guidelines on distinguishing between liquidated damages and
penalties which have long been accepted are as follows (given by Lord Dunedin
in 1915):
40.1 If the Contractor fails to complete the Works by the "Date for Completion"
stated in the Appendix or within any extended time under Clause 43 hereof,
the S.O. shall issue a Certificate of Non-Completion** to the Contractor.
** It is very important for the S.O to issue this certificate to inform the Contractor
that he has failed to complete the project on time. It is also important procedure
for imposing the liquidated and ascertain damages.
JKR 203A Standard Form of Contract
Damages for Non-Completion
the S.O shall issue a notice to the Contractor informing the Contractor the
intention of the Government to impose LIQUIDATED AND ASCERTAINED
DAMAGES (LAD) to the Contractor if the Contractor fails to complete the
Works by the Date for Completion or within any extended time granted.
JKR 203A Standard Form of Contract
Damages for Non-Completion
the Government shall be entitled to recover from the Contractor the Liquidated
and Ascertained Damages (LAD) calculated at the rate stated in the
Appendix from the period (date) of the issuance of the Certificate of Non-
completion to the date of the issuance of the Certificate of Practical
Completion** or the Date of Termination of This Contract.
** It is also very important for the S.O to state in the Certificate of Non-
completion of the new date for completion. If not “time will be at large” and the
entitlement to LAD will cease to operate”
JKR 203A Standard Form of Contract
Damages for Non-Completion
The S.O may deduct such damages from any money due to or
become due to the Contractor failing which such damages shall be
recovered from the Performance Bond or as debt due from the
Contractor.
If the Contractor fails to complete the Works by the Completion Date, and the
Architect is of the opinion the same ought reasonably so to have been
completed, the Architect shall issue a CERTIFICATE OF NON-COMPLETION
(CNC)
The Employer may recover such sum from any monies due or to become due to
the Contractor under the Contract or the Employer may recover such sum from
the Performance Bond.
The Employer shall inform the Contractor in writing of such deduction or such
debt due from the Contractor.
The imposition of the Liquidated Damages by the Employer shall not be taken
into account by the Architect in the issuance of payment certificates and Final
Certificate and is not subjected to the set-off procedures under Clause 30.4.
PAM 2018 Standard Form of Contract
Date for Completion and Damages for Non-Completion
The parties agree that by entering into the Contract, the Contractor shall pay
to the Employer the said amount, if it becomes due without the need for the
Employer to prove his loss and/or damage unless contrary is proven by
the Contractor.
PAM 2018 Standard Form of Contract
Date for Completion and Damages for Non-Completion
The Employer shall then revise the amount of the Liquidated Damages he is
entitled to retain.
In the event the amount of Liquidated Damages exceeds the amount the
Employer entitled to retain; he shall repay the surplus amount to the
Contractor within the Period of Honouring Certificates from the date of the
latest Certificate of Extension of Time.
PAM 2018 Standard Form of Contract
Date for Completion and Damages for Non-Completion