EPCIC MIDSTREAM PT.

LNG Page 1 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49

LNG MIDSTREAM 1036 10-Jun-24 29-May-28

MILESTONES 1036 10-Jun-24 29-May-28


Engineering Milestones 267 10-Jun-24 17-Jun-25
A5510 Commencement of DED (Engineering Kick-off and 0 10-Jun-24
MOM issued)
A6140 Completion of P&I D 0 18-Apr-25
A6130 Completion of Model Review 0 08-May-25
A6170 Completion of HAZOP & HAZID 0 16-May-25
A5560 Completion of Plot Plan 0 30-May-25
A6150 Completion of Isometric Diagram 0 13-Jun-25
A6160 Completion of final MTO 0 17-Jun-25
Procurement Milestones 626 17-Oct-24 12-Mar-27
A5570 90% Piping Bulk Materials MR (Piping, Fitting & 0 17-Oct-24
Flanges) PO Issued
A5580 PO issuance for Primary Steel Structures (1st order) 0 17-Oct-24

A5520 Commencement of PO issuance for LLI Items 0 17-Feb-25


A5530 Completion of PO issuance for LLI Items 0 30-Jun-25
A5600 All Structural Steel Arrive at Site 0 08-Apr-26
A5610 All Tagged Items LLI Arrive at Site 0 12-Mar-27
Construction Milestones 424 03-Feb-26 20-Sep-27
A5990 Complete Piling Work 0 03-Feb-26
A6000 Complete Structure Work 0 29-Sep-26
A6010 Complete Mechanical Erection 0 10-May-27
A6060 Completion Onshore Pipeline 0 25-Jun-27
A6020 Complete Piping Works 0 23-Jul-27
A6070 Completion Offshore Pipeline 0 23-Jul-27
A6030 Complete E&I Works 0 18-Aug-27
A6080 Completion Condensate Handling & Fuel Storage Area 0 18-Aug-27

A6040 Start Pre-Com Activity 0 13-Sep-27


A6050 Completion PCC Area 0 20-Sep-27
Commissioning Milestones 180 20-Sep-27 29-May-28
A6090 Complete Energize Power Generation 0 20-Sep-27
A6100 Complete Commisioning and Integration Works 0 10-Apr-28
A6110 Complete Start-up 0 22-May-28
A6120 Provisional Acceptance 0 29-May-28
ENGINEERING 291 10-Jun-24 21-Jul-25
Process 225 10-Jun-24 18-Apr-25
A4770 Design Basis /Philosophies 90 10-Jun-24 11-Oct-24
A4830 Calculations & Reports 90 22-Jul-24 22-Nov-24
A4840 List (Equipment list, Line list) 90 02-Sep-24 03-Jan-25
A4850 datasheets 90 20-Sep-24 23-Jan-25
A4810 PFDs 120 23-Sep-24 07-Mar-25
A4820 P&IDs 120 04-Nov-24 18-Apr-25
Process Safety 215 22-Jul-24 16-May-25
A4960 Design Basis /Philosophies 90 22-Jul-24 22-Nov-24
A4980 Calculations & Reports 90 02-Sep-24 03-Jan-25
A4970 datasheets 90 02-Dec-24 04-Apr-25
A5000 drawing & layouts 90 02-Dec-24 04-Apr-25
A5030 HAZOP, HAZID, SIL 120 02-Dec-24 16-May-25
A5050 FERA 90 02-Dec-24 04-Apr-25
Mechanical 217 08-Jul-24 06-May-25
A5060 Design Basis 60 08-Jul-24 27-Sep-24
A5070 Specifications 60 30-Sep-24 20-Dec-24
A5080 Calculations & Reports 60 20-Dec-24 13-Mar-25
A5090 Drawing 60 03-Jan-25 27-Mar-25
A5100 Datasheets 60 09-Jan-25 02-Apr-25
A5120 Requisition 10 03-Apr-25 16-Apr-25
A5130 Technical Bid Evaluation 14 17-Apr-25 06-May-25
Piping 269 08-Jul-24 17-Jul-25
A5140 Design Basis 60 08-Jul-24 27-Sep-24
A5150 Specifications 60 30-Sep-24 20-Dec-24

Project Baseline Bar Baseline Milestone Doc No: 4429-PZ-PG-00000000001


Actual Work BL_Critical Milestone Date Revision Checked Approved
08-Apr-24 ISSUE FOR PROPOSAL
Remaining Work Milestone Rem
Critical Milestones Milestone Act
Critical Remaining Work
EPCIC MIDSTREAM PT. LNG Page 2 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A5190 3D Model 120 22-Nov-24 08-May-25
A5180 Plot Plan 120 16-Dec-24 30-May-25
A5160 Calculations & Reports 90 27-Jan-25 30-May-25
A5170 Isometrics Drawings 100 27-Jan-25 13-Jun-25
A5200 Material Takeoff 20 19-May-25 13-Jun-25
A5210 Requisition 10 16-Jun-25 27-Jun-25
A5220 Technical Bid Evaluation 14 30-Jun-25 17-Jul-25
Civil & Structure 271 08-Jul-24 21-Jul-25
A5250 Design Basis 60 08-Jul-24 27-Sep-24
A5260 Specifications 60 30-Sep-24 20-Dec-24
A5270 Study and Report 60 23-Dec-24 14-Mar-25
A5280 Calculations 70 29-Jan-25 06-May-25
A5290 Drawing 60 12-Mar-25 03-Jun-25
A5300 Material Takeoff 20 21-May-25 17-Jun-25
A5310 Requisition 10 18-Jun-25 01-Jul-25
A5320 Technical Bid Evaluation 14 02-Jul-25 21-Jul-25
Electrical 266 08-Jul-24 14-Jul-25
A5330 Design Basis 60 08-Jul-24 27-Sep-24
A5340 Specifications 60 30-Sep-24 20-Dec-24
A5350 Load List & Sing Line Diagram 90 16-Dec-24 18-Apr-25
A5360 Calculations 60 27-Jan-25 18-Apr-25
A5370 Drawing 60 27-Jan-25 18-Apr-25
A5380 Datasheets 60 10-Mar-25 30-May-25
A5390 Material Takeoff 20 14-May-25 10-Jun-25
A5400 Requisition 10 11-Jun-25 24-Jun-25
A5410 Technical Bid Evaluation 14 25-Jun-25 14-Jul-25
Instrumentation 264 08-Jul-24 10-Jul-25
A5420 Design Basis 60 08-Jul-24 27-Sep-24
A5430 Specifications 60 30-Sep-24 20-Dec-24
A5450 Calculations 70 16-Dec-24 21-Mar-25
A5460 Drawing 60 27-Jan-25 18-Apr-25
A5440 Cause and Effect Diagram 70 10-Feb-25 16-May-25
A5470 Datasheets 60 17-Feb-25 09-May-25
A5480 Material Takeoff 20 12-May-25 06-Jun-25
A5490 Requisition 10 09-Jun-25 20-Jun-25
A5500 Technical Bid Evaluation 14 23-Jun-25 10-Jul-25
PROCUREMENT 640 30-Sep-24 12-Mar-27
Bulk Material 398 30-Sep-24 08-Apr-26
Steel Structure 398 30-Sep-24 08-Apr-26
A2370 Issue for Quotation & Bid Receipt 14 30-Sep-24 17-Oct-24
A2380 Technical Bid Evaluation 14 18-Oct-24 06-Nov-24
A2390 Negotiation & Issue LOI/PO 10 07-Nov-24 20-Nov-24
A2400 Fabrication/Manufacturing 300 21-Nov-24 14-Jan-26
A2410 Transport & Receipt at Site 60 15-Jan-26 08-Apr-26
Pipiing Bulk 298 30-Sep-24 19-Nov-25
A2420 Issue for Quotation & Bid Receipt 14 30-Sep-24 17-Oct-24
A2430 Technical Bid Evaluation 14 18-Oct-24 06-Nov-24
A2440 Negotiation & Issue LOI/PO 10 07-Nov-24 20-Nov-24
A2450 Fabrication/Manufacturing 200 21-Nov-24 27-Aug-25
A2460 Transport & Receipt at Site 60 28-Aug-25 19-Nov-25
Electrical Bulk 338 30-Sep-24 14-Jan-26
A2470 Issue for Quotation & Bid Receipt 14 30-Sep-24 17-Oct-24
A2480 Technical Bid Evaluation 14 18-Oct-24 06-Nov-24
A2490 Negotiation & Issue LOI/PO 10 07-Nov-24 20-Nov-24
A2500 Fabrication/Manufacturing 240 21-Nov-24 22-Oct-25
A2510 Transport & Receipt at Site 60 23-Oct-25 14-Jan-26
Instrumentation Bulk 338 30-Sep-24 14-Jan-26
A2520 Issue for Quotation & Bid Receipt 14 30-Sep-24 17-Oct-24
A2530 Technical Bid Evaluation 14 18-Oct-24 06-Nov-24
A2540 Negotiation & Issue LOI/PO 10 07-Nov-24 20-Nov-24
A2550 Fabrication/Manufacturing 240 21-Nov-24 22-Oct-25
A2560 Transport & Receipt at Site 60 23-Oct-25 14-Jan-26
Civil Bulk 178 30-Sep-24 04-Jun-25
A2570 Issue for Quotation & Bid Receipt 14 30-Sep-24 17-Oct-24
A2580 Technical Bid Evaluation 14 18-Oct-24 06-Nov-24
A2590 Negotiation & Issue LOI/PO 10 07-Nov-24 20-Nov-24
A2600 Fabrication/Manufacturing 80 21-Nov-24 12-Mar-25
A2610 Transport & Receipt at Site 60 13-Mar-25 04-Jun-25
Itemized 581 20-Dec-24 12-Mar-27
Process Safety 458 20-Dec-24 22-Sep-26
Fire Fighting Equipment 458 20-Dec-24 22-Sep-26
A2620 Issue for Quotation & Bid Receipt 14 20-Dec-24 08-Jan-25
A2630 Technical Bid Evaluation 14 09-Jan-25 28-Jan-25
EPCIC MIDSTREAM PT. LNG Page 3 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A2640 Negotiation & Issue LOI/PO 10 29-Jan-25 11-Feb-25
A2650 Fabrication/Manufacturing 360 12-Feb-25 30-Jun-26
A2660 Transport & Receipt at Site 60 01-Jul-26 22-Sep-26
Water Spray 458 20-Dec-24 22-Sep-26
A2670 Issue for Quotation & Bid Receipt 14 20-Dec-24 08-Jan-25
A2680 Technical Bid Evaluation 14 09-Jan-25 28-Jan-25
A2690 Negotiation & Issue LOI/PO 10 29-Jan-25 11-Feb-25
A2700 Fabrication/Manufacturing 360 12-Feb-25 30-Jun-26
A2710 Transport & Receipt at Site 60 01-Jul-26 22-Sep-26
Fire Extinghuising 458 20-Dec-24 22-Sep-26
A2720 Issue for Quotation & Bid Receipt 14 20-Dec-24 08-Jan-25
A2730 Technical Bid Evaluation 14 09-Jan-25 28-Jan-25
A2740 Negotiation & Issue LOI/PO 10 29-Jan-25 11-Feb-25
A2750 Fabrication/Manufacturing 360 12-Feb-25 30-Jun-26
A2760 Transport & Receipt at Site 60 01-Jul-26 22-Sep-26
Mechancial Rotating 428 29-Jan-25 18-Sep-26
Acid Gas Removal Unit 428 29-Jan-25 18-Sep-26
A2820 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A2830 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A2840 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A2850 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A2860 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Dehydration Unit 428 29-Jan-25 18-Sep-26
A2870 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A2880 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A2890 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A2900 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A2910 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Hydrocarbon Dew Point Control Unit 428 29-Jan-25 18-Sep-26
A2920 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A2930 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A2940 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A2950 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A2960 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Heavy Hydrocarbon Removal Unit 428 29-Jan-25 18-Sep-26
A2970 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A2980 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A2990 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3000 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3010 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Gas Turbine Generator / Gas Engine 428 29-Jan-25 18-Sep-26
A3020 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3030 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3040 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3050 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3060 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Thermal Oxidizer and Fired Heater 428 29-Jan-25 18-Sep-26
A3070 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3080 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3090 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3100 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3110 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Gas Compressors 428 29-Jan-25 18-Sep-26
A3120 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3130 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3140 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3150 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3160 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Transfer Pump and Facilities 428 29-Jan-25 18-Sep-26
A3170 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3180 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3190 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3200 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3210 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
General Services Pumps and Facilities 428 29-Jan-25 18-Sep-26
A3220 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3230 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3240 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3250 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3260 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Fire Water Pump and Facilities 428 29-Jan-25 18-Sep-26
A3270 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3280 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
EPCIC MIDSTREAM PT. LNG Page 4 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A3290 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3300 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3310 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Mechanical Static 428 29-Jan-25 18-Sep-26
Condensate Storage Tank Material 428 29-Jan-25 18-Sep-26
A3470 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3480 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3490 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3500 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3510 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Fuel Tank Material 428 29-Jan-25 18-Sep-26
A3520 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3530 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3540 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3550 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3560 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Fire Water Tank Material 428 29-Jan-25 18-Sep-26
A3620 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3630 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3640 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3650 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3660 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Nitrogen Generator Package 428 29-Jan-25 18-Sep-26
A3670 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3680 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3690 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3700 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3710 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Custody Transfer Metering Package 428 29-Jan-25 18-Sep-26
A3720 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3730 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3740 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3750 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3760 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
AGRU Package 428 29-Jan-25 18-Sep-26
A3770 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3780 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3790 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3800 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3810 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Treated Gas Booster Compressor Package 428 29-Jan-25 18-Sep-26
A3820 Issue for Quotation & Bid Receipt 14 29-Jan-25 17-Feb-25
A3830 Technical Bid Evaluation 14 18-Feb-25 07-Mar-25
A3840 Negotiation & Issue LOI/PO 10 10-Mar-25 21-Mar-25
A3850 Fabrication/Manufacturing 330 24-Mar-25 26-Jun-26
A3860 Transport & Receipt at Site 60 29-Jun-26 18-Sep-26
Electrical 458 11-Jun-25 12-Mar-27
SCADA 458 11-Jun-25 12-Mar-27
A3970 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
A3980 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A3990 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4000 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4010 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Neutral Grounding Resistance 458 11-Jun-25 12-Mar-27
A4020 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
A4030 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A4040 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4050 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4060 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Cathodic Protection Equipment 458 11-Jun-25 12-Mar-27
A4070 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
A4080 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A4090 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4100 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4110 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Switchgear 458 11-Jun-25 12-Mar-27
A4170 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
A4180 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A4190 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4200 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4210 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Transformer 458 11-Jun-25 12-Mar-27
A4220 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
EPCIC MIDSTREAM PT. LNG Page 5 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A4230 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A4240 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4250 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4260 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Explosion-proof System 458 11-Jun-25 12-Mar-27
A4270 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
A4280 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A4290 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4300 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4310 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Diesel Engine Generator Package 458 11-Jun-25 12-Mar-27
A4320 Issue for Quotation & Bid Receipt 14 11-Jun-25 30-Jun-25
A4330 Technical Bid Evaluation 14 01-Jul-25 18-Jul-25
A4340 Negotiation & Issue LOI/PO 10 21-Jul-25 01-Aug-25
A4350 Fabrication/Manufacturing 360 04-Aug-25 18-Dec-26
A4360 Transport & Receipt at Site 60 21-Dec-26 12-Mar-27
Instrumentation 458 09-Jun-25 10-Mar-27
Pipeline Leak Detection System 458 09-Jun-25 10-Mar-27
A4420 Issue for Quotation & Bid Receipt 14 09-Jun-25 26-Jun-25
A4430 Technical Bid Evaluation 14 27-Jun-25 16-Jul-25
A4440 Negotiation & Issue LOI/PO 10 17-Jul-25 30-Jul-25
A4450 Fabrication/Manufacturing 360 31-Jul-25 16-Dec-26
A4460 Transport & Receipt at Site 60 17-Dec-26 10-Mar-27
Central Control System 458 09-Jun-25 10-Mar-27
A4470 Issue for Quotation & Bid Receipt 14 09-Jun-25 26-Jun-25
A4480 Technical Bid Evaluation 14 27-Jun-25 16-Jul-25
A4490 Negotiation & Issue LOI/PO 10 17-Jul-25 30-Jul-25
A4500 Fabrication/Manufacturing 360 31-Jul-25 16-Dec-26
A4510 Transport & Receipt at Site 60 17-Dec-26 10-Mar-27
Field Instrument 458 09-Jun-25 10-Mar-27
A4520 Issue for Quotation & Bid Receipt 14 09-Jun-25 26-Jun-25
A4530 Technical Bid Evaluation 14 27-Jun-25 16-Jul-25
A4540 Negotiation & Issue LOI/PO 10 17-Jul-25 30-Jul-25
A4550 Fabrication/Manufacturing 360 31-Jul-25 16-Dec-26
A4560 Transport & Receipt at Site 60 17-Dec-26 10-Mar-27
Fire Alarm System 458 09-Jun-25 10-Mar-27
A4570 Issue for Quotation & Bid Receipt 14 09-Jun-25 26-Jun-25
A4580 Technical Bid Evaluation 14 27-Jun-25 16-Jul-25
A4590 Negotiation & Issue LOI/PO 10 17-Jul-25 30-Jul-25
A4600 Fabrication/Manufacturing 360 31-Jul-25 16-Dec-26
A4610 Transport & Receipt at Site 60 17-Dec-26 10-Mar-27
Gas Detector 458 09-Jun-25 10-Mar-27
A4620 Issue for Quotation & Bid Receipt 14 09-Jun-25 26-Jun-25
A4630 Technical Bid Evaluation 14 27-Jun-25 16-Jul-25
A4640 Negotiation & Issue LOI/PO 10 17-Jul-25 30-Jul-25
A4650 Fabrication/Manufacturing 360 31-Jul-25 16-Dec-26
A4660 Transport & Receipt at Site 60 17-Dec-26 10-Mar-27
Telecommunication System 458 09-Jun-25 10-Mar-27
A4670 Issue for Quotation & Bid Receipt 14 09-Jun-25 26-Jun-25
A4680 Technical Bid Evaluation 14 27-Jun-25 16-Jul-25
A4690 Negotiation & Issue LOI/PO 10 17-Jul-25 30-Jul-25
A4700 Fabrication/Manufacturing 360 31-Jul-25 16-Dec-26
A4710 Transport & Receipt at Site 60 17-Dec-26 10-Mar-27
HVAC 458 03-Apr-25 04-Jan-27
Air Conditioning & Ex-Haust 458 03-Apr-25 04-Jan-27
A4720 Issue for Quotation & Bid Receipt 14 03-Apr-25 22-Apr-25
A4730 Technical Bid Evaluation 14 23-Apr-25 12-May-25
A4740 Negotiation & Issue LOI/PO 10 13-May-25 26-May-25
A4750 Fabrication/Manufacturing 360 27-May-25 12-Oct-26
A4760 Transport & Receipt at Site 60 13-Oct-26 04-Jan-27
CONSTRUCTION 782 11-Nov-24 09-Nov-27
General Works 725 11-Nov-24 20-Aug-27
Site Preparation Work 255 11-Nov-24 31-Oct-25
A1080 Site Offices ( Temp. Facil. ) 120 11-Nov-24 25-Apr-25
A1090 Camp Facilities ( Temp. Facil. ) 120 13-Jan-25 27-Jun-25
A1100 Warehouse & Storage Ficil. ( Temp. Facil. ) 120 17-Mar-25 29-Aug-25
A1110 Fabrication Facil. (Piping) ( Temp. Facil. ) 120 19-May-25 31-Oct-25
Earth Work 150 28-Apr-25 21-Nov-25
A1120 Cut & Fill 120 28-Apr-25 10-Oct-25
A1230 Leveling, etc 90 21-Jul-25 21-Nov-25
Roads Work 160 15-Jun-26 22-Jan-27
A1130 Road pavement 160 15-Jun-26 22-Jan-27
Drainage Work 160 03-Nov-25 12-Jun-26
EPCIC MIDSTREAM PT. LNG Page 6 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A1140 Drainage installation 160 03-Nov-25 12-Jun-26
Other General Works 220 19-Oct-26 20-Aug-27
A1150 Landscape work 160 19-Oct-26 28-May-27
A1160 other works 160 11-Jan-27 20-Aug-27
Permanent Camp Complex 644 02-Apr-25 20-Sep-27
Civil & Structure Work 480 02-Apr-25 02-Feb-27
A1170 Pilling work 160 02-Apr-25 11-Nov-25
A1180 Foundation/Elevetion work 180 25-Jun-25 03-Mar-26
A1190 Superstructure/RCC Work 240 17-Sep-25 18-Aug-26
A1200 Finishing Work 160 13-May-26 22-Dec-26
A1210 Paving Work Ext. 120 19-Aug-26 02-Feb-27
Mechanical Work 195 11-Feb-26 10-Nov-26
A1240 Installation of HVAC 180 11-Feb-26 20-Oct-26
A1250 Installaion of Plumbing 180 04-Mar-26 10-Nov-26
Electrical Works 210 08-Jul-26 27-Apr-27
A1260 Elec.Cable tray, Cable Laying and termination 180 08-Jul-26 16-Mar-27
A1270 Installation of Elec. Equipment/Panels 180 19-Aug-26 27-Apr-27
Instrumentation Work 194 30-Sep-26 28-Jun-27
A1280 Instrument Cable Laying and termination 180 30-Sep-26 08-Jun-27
A1290 Installation of Instruments equipment/Panels 180 20-Oct-26 28-Jun-27
Architectural Work 254 30-Sep-26 20-Sep-27
A1300 Landscape works 180 30-Sep-26 08-Jun-27
A1310 Fit out installation 180 01-Dec-26 09-Aug-27
A1320 Painting works 180 12-Jan-27 20-Sep-27
Gas Processing Plant Facilities 569 14-May-25 19-Jul-27
Civil & Structure Work 520 14-May-25 11-May-27
A1330 Pilling work 160 14-May-25 23-Dec-25
A1340 Foundation/Elevetion work 180 06-Aug-25 14-Apr-26
A1350 Superstructure/RCC Work 210 29-Oct-25 18-Aug-26
A1360 Steel Structural Erection Work 210 29-Oct-25 18-Aug-26
A1370 Paving & Other works 120 15-Apr-26 29-Sep-26
A1380 Fire proofing Work 160 19-Aug-26 30-Mar-27
A1390 Finishing Work 160 30-Sep-26 11-May-27
Mechanical Work 200 21-Jul-26 26-Apr-27
A1400 Installation/Erection/Alignment 200 21-Jul-26 26-Apr-27
Piping Work 361 15-Jan-26 03-Jun-27
A1410 Piping Pre- fabrication 210 15-Jan-26 04-Nov-26
A1420 Piperack Piping Erection 180 07-Sep-26 14-May-27
A1430 Around Equipment Piping Erection 180 07-Sep-26 14-May-27
A1440 Hydrotesting 90 29-Jan-27 03-Jun-27
Electrical Works 340 26-Feb-26 16-Jun-27
A1450 E & I Cable Tray Erection 160 26-Feb-26 07-Oct-26
A1460 Electrical Equipment Installation 160 30-Apr-26 09-Dec-26
A1470 Electrical Cable Laying 160 02-Jul-26 10-Feb-27
A1480 Earthing & lightning 160 03-Sep-26 14-Apr-27
A1490 Electrical Termination 160 05-Nov-26 16-Jun-27
Instrumentation Work 265 02-Jul-26 07-Jul-27
A1520 Instrumentation Cable Laying & Termination 160 02-Jul-26 10-Feb-27
A1510 Instruments Installations 160 13-Aug-26 24-Mar-27
A1530 Instruments Hook-ups 160 15-Oct-26 26-May-27
A1500 JB/LP Installations 160 26-Nov-26 07-Jul-27
Painting Work 291 21-May-26 01-Jul-27
A1540 Piping Shop Painting 150 21-May-26 16-Dec-26
A1550 Equipment Painting 150 10-Nov-26 07-Jun-27
A1560 Piping Painting 150 04-Dec-26 01-Jul-27
Insulation Work 162 04-Dec-26 19-Jul-27
A1580 Piping Insulation 150 04-Dec-26 01-Jul-27
A1570 Equipment Insulation 150 22-Dec-26 19-Jul-27
Onshore Pipeline 430 03-Nov-25 25-Jun-27
EPF to GPP 290 03-Nov-25 11-Dec-26
A2260 ROW Clearing & Grading 60 03-Nov-25 23-Jan-26
A2770 Pipe Haul / Transportation from Transfer Yard to Site 36 01-Dec-25 19-Jan-26

A2780 Stringing of Line Pipes 30 29-Dec-25 06-Feb-26


A1900 Welding & NDT 70 09-Feb-26 15-May-26
A1910 Field Joint Coating & Holiday Test 70 23-Mar-26 26-Jun-26
A2790 Trenching 40 20-Apr-26 12-Jun-26
A1920 Lowering 60 01-Jun-26 21-Aug-26
A1930 Laying FO Cable 70 29-Jun-26 02-Oct-26
A1940 Backfilling & Compacting 66 27-Jul-26 26-Oct-26
A1950 Marker Sign and Warning Sign 50 24-Aug-26 30-Oct-26
A1960 Hydrotest 30 02-Nov-26 11-Dec-26
GPP to Nearshore 390 29-Dec-25 25-Jun-27
EPCIC MIDSTREAM PT. LNG Page 7 of 7

TELUK BINTUNI, PAPUA BARAT - INDONESIA


Activity ID Activity Name Original Start Finish 2024 2025 2026 2027 2028
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A5880 ROW Clearing & Grading 120 29-Dec-25 12-Jun-26
A5890 Pipe Haul / Transportation from Transfer Yard to Site 120 26-Jan-26 10-Jul-26

A5900 Stringing of Line Pipes 120 23-Feb-26 07-Aug-26


A5910 Welding & NDT 150 20-Apr-26 13-Nov-26
A5920 Field Joint Coating & Holiday Test 150 15-Jun-26 08-Jan-27
A5930 Trenching 120 27-Jul-26 08-Jan-27
A5940 Lowering 120 07-Sep-26 19-Feb-27
A5950 Laying FO Cable 120 19-Oct-26 02-Apr-27
A5960 Backfilling & Compacting 120 30-Nov-26 14-May-27
A5970 Marker Sign and Warning Sign 90 28-Dec-26 30-Apr-27
A5980 Hydrotest 40 03-May-27 25-Jun-27
Offshore Pipeline 540 30-Jun-25 23-Jul-27
Beach Fall Point (BFP) to PLET (Include HDD) 540 30-Jun-25 23-Jul-27
A2100 Site Preparation and Survey 395 30-Jun-25 01-Jan-27
A2110 CSD-Pre Seeping 90 25-Aug-25 26-Dec-25
A2120 Pipeline HDD Installation 90 17-Nov-25 20-Mar-26
A2130 Pipeline Pulling with HDD Barge 30 09-Mar-26 17-Apr-26
A2140 Offshore Pipeline Installation 60 23-Mar-26 12-Jun-26
A2150 FOC HDD & Installation 120 18-May-26 30-Oct-26
A2160 Post Trenching 45 21-Sep-26 20-Nov-26
A2170 Backfilling and Concrete Matress Installation 120 02-Nov-26 16-Apr-27
A2180 Plet Installation 120 08-Feb-27 23-Jul-27
Condensate Handling and Fuel Storage 561 25-Jun-25 18-Aug-27
Civil & Structure Work 520 25-Jun-25 22-Jun-27
A5620 Pilling work 160 25-Jun-25 03-Feb-26
A5630 Foundation/Elevetion work 180 17-Sep-25 26-May-26
A5640 Superstructure/RCC Work 210 10-Dec-25 29-Sep-26
A5650 Steel Structural Erection Work 210 10-Dec-25 29-Sep-26
A5660 Paving & Other works 120 27-May-26 10-Nov-26
A5670 Fire proofing Work 160 30-Sep-26 11-May-27
A5680 Finishing Work 160 11-Nov-26 22-Jun-27
Mechanical Work 210 21-Jul-26 10-May-27
A5690 Installation/Erection/Alignment 210 21-Jul-26 10-May-27
Piping Work 274 30-Jul-26 17-Aug-27
A5700 Piping Pre- fabrication 230 30-Jul-26 16-Jun-27
A5710 Piperack Piping Erection 200 22-Oct-26 28-Jul-27
A5720 Around Equipment Piping Erection 200 22-Oct-26 28-Jul-27
A5730 Hydrotesting 110 17-Mar-27 17-Aug-27
Electrical Works 340 09-Apr-26 28-Jul-27
A5740 E & I Cable Tray Erection 160 09-Apr-26 18-Nov-26
A5750 Electrical Equipment Installation 160 11-Jun-26 20-Jan-27
A5760 Electrical Cable Laying 160 13-Aug-26 24-Mar-27
A5770 Earthing & lightning 160 15-Oct-26 26-May-27
A5780 Electrical Termination 160 17-Dec-26 28-Jul-27
Instrumentation Work 265 13-Aug-26 18-Aug-27
A5790 Instrumentation Cable Laying & Termination 160 13-Aug-26 24-Mar-27
A5800 Instruments Installations 160 24-Sep-26 05-May-27
A5810 Instruments Hook-ups 160 05-Nov-26 16-Jun-27
A5820 JB/LP Installations 160 07-Jan-27 18-Aug-27
Painting Work 291 18-Jun-26 29-Jul-27
A5830 Piping Shop Painting 150 18-Jun-26 13-Jan-27
A5840 Equipment Painting 150 08-Dec-26 05-Jul-27
A5850 Piping Painting 150 01-Jan-27 29-Jul-27
Insulation Work 168 22-Dec-26 12-Aug-27
A5870 Equipment Insulation 150 22-Dec-26 19-Jul-27
A5860 Piping Insulation 150 15-Jan-27 12-Aug-27
Pre - Commissioning 131 11-May-27 09-Nov-27
A2280 Flushing & Blowing 90 11-May-27 13-Sep-27
A2270 Substation Energization & Test 60 29-Jun-27 20-Sep-27
A2300 Loop Test 60 29-Jun-27 20-Sep-27
A2290 Cleaning & Gauging & Dring 60 18-Aug-27 09-Nov-27
COMMISSIONING 185 14-Sep-27 29-May-28
A2310 Mechanical Completion 0 14-Sep-27 14-Sep-27
A2800 Commisioning 150 14-Sep-27 10-Apr-28
A2360 Performance Test 20 11-Apr-28 08-May-28
A2330 Start - Up Facility 10 09-May-28 22-May-28
A2350 Provisional Acceptance 5 23-May-28 29-May-28