Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 44

B000

A000

R000

B000
A000
B000

Level 1
A000
B000
A000 C000
D000
E000
R000
U000
Description
Process Area
Building Area
Common Area (Road, Ditch, Fence)
Electrical Cable ISBL
Instrument Cable ISBL
Existing Pipe Rack Area
Underground for All Area
B200

B300

A400
A100

R000

A300

B100
A200
Level 2 Description
A100 Process Area 1 - Compressor, LP Condensate, CO2 Cooling and Stripping Area
A200 Process Area 2 - Reformer, Fuel, Demin Water, Condensate, Methanator and Feed / Effluent Area
A300 Process Area 3 - Ammonia Synth Area
A400 Process Area 4 - Air Compressor and AWU Area
B100 Electrical Building Area
B200 Electrical Control Room and Main Office (Existing)
B300 Siwtchgear SWGR-11 (Existing)
C000 Common Area (Road, Ditch, Fence)
D000 Electrical Cable ISBL
E000 Instrument Cable ISBL
R000 Existing Pipe Rack Area
U000 Underground for All Area
B300

B100

PCWBS FWBS Discipline EWP Doc.


PILING
A100 38 3138 9832-CWP-3138-A100
A200 38 3138 9832-CWP-3138-A200
A300 38 3138 9832-CWP-3138-A300
A400 38 3138 9832-CWP-3138-A400
B000 38 3138 9832-CWP-3138-B000
R000 38 3138 9832-CWP-3138-R000
GENERAL CIVIL - BUILDING AREA (Temporary Chemical Shelter, Operation Shelter Alternative Relocat
B100 47 3147 9832-EWP-3147-B100
B100 65 3165 9832-EWP-3165-B100
B100 65 3165 9832-EWP-3165-B100
B100 65 3165 9832-EWP-3165-B100
B100 65 3165 9832-EWP-3165-B100
B100 C 31C 9832-EWP-31C-B100
B100 F 31F 9832-EWP-31F-B100
GENERAL CIVIL - BUILDING AREA (Temporary Chemical Shelter, Operation Shelter Alternative Relocat
B100 6B 316B
B100 6B 316B
B300

R000

A300

A200

BQ Duration
CWP Doc. Description Actual UOM (days)

9832-CWP-3138-A100 Piling 01 63 EA 30
9832-CWP-3138-A200 Piling 02 54 EA 35
9832-CWP-3138-A300 Piling 03 6 EA 6
9832-CWP-3138-A400 Piling 04 5 EA 8
9832-CWP-3138-B000 Piling 05 61 EA 14
9832-CWP-3138-R000 Piling 06 88 EA -
emporary Chemical Shelter, Operation Shelter Alternative Relocation, New Electrical Room, Trafo Yard)
9832-CWP-3147-B100-Substructure Substructure m2
9832-CWP-3165-B100-Superstructure Superstructure m2
9832-CWP-3165-B100-Steel Structure Steel Structure m2
9832-CWP-3165-B100-Exterior Finishing Exterior Finishing m2
9832-CWP-3165-B100-Interior Finishing Interior Finishing m2
9832-CWP-31C-B100-Plumbing & Sanitary Plumbing & Sanitary m2
9832-CWP-31F-B100-Electrical Electrical m2
emporary Chemical Shelter, Operation Shelter Alternative Relocation, New Electrical Room, Trafo Yard)
Transformer Yard
Furniture & Equipment
Lanscaping
Start Date End Date

5/30/2024 6/29/2024
6/29/2024 8/3/2024
8/17/2024 8/23/2024
8/23/2024 8/31/2024
8/3/2024 8/17/2024
N/A N/A

9832-000-1330-MTO-0001 MATERIAL TAKE OFF FOR BUILDING


9832-000-1330-MTO-0002 MATERIAL TAKE OFF FOR GENERAL CIVIL
9832-B10-136C-DWG-0001 ARCHITECTURAL PLAN, ELEVATION AND DETAIL DRAW
9832-B10-136C-DWG-0002 FOUNDATION PLAN, SECTION AND DETAIL DRAWING F
9832-B10-136C-DWG-0003 CONCRETE STRUCTURE PLAN, SECTION AND DETAIL D
9832-B10-136Z-DWG-0001 ARCHITECTURE PLAN, ELEVATION AND DETAIL DRAW
9832-B10-136Z-DWG-0002 CONCRETE STRUCTURE PLAN, ELEVATION AND DETAIL
9832-B10-136Z-DWG-0003 FOUNDATION PLAN, ELEVATION AND DETAIL DRAWIN
ENERAL CIVIL
VATION AND DETAIL DRAWING FOR NEW SUBSTATION FOR ELECTRICAL BUILDING
N AND DETAIL DRAWING FOR NEW SUBSTATION FOR ELECTRICAL BUILDING
N, SECTION AND DETAIL DRAWING FOR NEW SUBSTATION FOR ELECTRICAL BUILDING
ATION AND DETAIL DRAWING FOR OPERATOR SHELTER
N, ELEVATION AND DETAIL FRAMING DRAWING FOR OPERATOR SHELTER
TION AND DETAIL DRAWING FOR OPERATOR SHELTER
No. ITEM PCWBS STATUS FWIP QTY P&ID

Column1 Column2 Column3 Column33 Column32 Column4 Column5

1 111-CB A100 Change Layout FIWP 01 1 PDI-0005


2 1102-E A100 Change Layout FIWP 01 1 PDI-0007
3 Pipe Support A100 Waiting design from Eng FIWP 01
4 160-C - 106C A100 Waiting design from Eng FIWP 02 1 PDI-0011
5 Pipe Support A100 Waiting design from Eng FIWP 02
6 1102-JA/JB A100 Shallow Foundation FIWP 00 2 PDI-0002

7 Pipe Support A100 Waiting design from Eng FIWP 03


8 Pipe Support A100 Waiting design from Eng FIWP 03
9 1106-C A100 Waiting design from Eng FIWP 04 1 PDI-0011
10 1103-E A100 FIWP 01 FIWP 04 1 PDI-0011
11 1103-JA/JB A100 Shallow Foundation FIWP 00 2 PDI-0011
12 Pipe Support A100 Waiting design from Eng FIWP 04
13 108-JA/JB A100 Shallow Foundation FIWP 05 2 PDI-0008
14 108-JAT/JBT A100 Shallow Foundation FIWP 00 2 PDI-0020
15 1109-JA/JB A100 Shallow Foundation FIWP 00 2 PDI-0007
16 Pipe Support A100 Waiting design from Eng FIWP 05
17 1102-F A100 FIWP 01 FIWP 06 1 PDI-0007
18 1106-J & Aux A100 FIWP 02 FIWP 06
19 Pipe Support A100 Waiting design from Eng FIWP 06
20 1104-E A200 FIWP 01 FIWP 01 1 PDI-0022
21 1101-E A200 FIWP 01 FIWP 01 1 PDI-0002
22 1101-C A200 FIWP 01 FIWP 01 1 PDI-0002
23 1104-JA/JB A200 Shallow Foundation FIWP 00 2 PDI-0022
24 1102-C A/B A200 FIWP 02 FIWP 02 2 PDI-0002

25 1103-C A200 FIWP 02 FIWP 02 1 PDI-0022


26 1104-CA/CB A200 FIWP 02 FIWP 02 2 PDI-0022
27 1107-C A200 FIWP 02 FIWP 02 1 PDI-0002
28 Pipe Support A200 Waiting design from Eng FIWP 03
29 1101-JA/JB A200 Shallow Foundation FIWP 00 2 PDI-0002
30 1105-C A200 Waiting design from Eng FIWP 03 1 PDI-0002

31 Pipe Support A200 Reallocate FIWP 03

32 Pipe Support A200 Waiting design from Eng FIWP 03


33 Pipe Support A200 Waiting design from Eng FIWP 03
34 104-C A200 existing 1 PDI-0004
35 103-D A200 existing 1 PDI-0003
36 104-DA A200 existing 1 PDI-0004
37 104-DB A200 existing 1 PDI-0004
38 101-B A200 existing 1 PDI-0001

Pipe Support A300 Waiting design from Eng FIWP 01


39
40 1105-L A300 FIWP 01 FIWP 01 1 PDI-0015
41 105-D A300 existing 1 PDI-0014

Pipe Support A400 Waiting design from Eng FIWP 01


42
43 1105-F A400 FIWP 01 FIWP 01 1 PDI-0013
44 101-J A400 N/A 1
45 101-JT A400 N/A 1

46 103-J A400 N/A 1 PDI-0012


47 103-JT A400 N/A 1 PDI-0012
48 105-J A400 N/A 1
49 105-JT A400 N/A 1

1103-L N/A N/A 1 PDI-0013


50

1130-L N/A N/A 1 PDI-0005


51

110-CA R000 N/A 1 PDI-0010


52

N/A
53

54 110-CB R000 N/A 1 PDI-0010

B000 Shallow Foundation


55
PILING PILING
DESCRIPTION Days Total CONCRETE (m3)
(20m) (27m)
Column
Column6 Column102 20 27 Column11
103
CO2 Stripper Steam Reboiler 1 2 0 2 43
CO2 LP Regenerator 2 4 0 4 85
Pipe Support 3 6 6 0 95
CO2 Water Chiller 3 6 6 0 95
Pipe Support 1 2 2 0 32
Saturator Feed Pumps 7 14 10 4 242
Pipe Support 2 3 3 0 48
Pipe Support 2 4 4 0 63
CO2 Water Chiller 1 2 0 2 43
CO2 Cooling Column 2 3 0 3 64
CO2 Chilling Pumps 1 2 2 0 32
Pipe Support 6 11 11 0 173
Lean Solution Pumps 1 2 0 2 43
Steam Turbines for 108-JA/JB 1 2 0 2 4
Low Pressure Condensate Pumps 1 2 2 0 32
Pipe Support 4 7 7 0 110
LP CO2 Condensate Separator 2 3 0 3 64
CO2 Booster Compressor 3 6 0 6 128
Pipe Support 4 8 8 0 126
Process Condensate Stripper 5 9 0 9 191
Natural Gas Saturator 4 8 0 8 170
Saturator NG Feed/Eff. Exchanger 2 3 3 0 48
Proc. Cond. Stripper Feed Pumps 2 4 4 0 63
Saturator Water Feed/Eff. Exchanger 3 5 0 5 106
DM Water Preheater 2 3 3 0 48
PC Stripper Feed/Eff. Exchanger 3 5 0 5 106
Stripped Condensate Cooler 1 2 0 2 43
2 3 3 0 75360
Saturator Cond. Recycle Pumps 1 2 2 0 32
NG Fuel Preheater 1 2 2 0 32
3 6 6 0 150720
3 6 6 0 150720
4 8 8 0 200960
Methanator Feed Preheater 0 0 0 0 0
Secondary Refomer 0 0 0 0 0
HTS Converter 0 0 0 0 0
LTS Converter 0 0 0 0 0
Primary Reformer Example Service 0 0 0 0 0
2 4 4 0 100480
Syngas Filter 2 3 3 0 75360
Ammonia Synthesis Converter 0 0 0
4 8 8 0 200960
AWU Separator 2 4 4 0 100480
Process Air Compressor 0 0 0
Process Air Compressor Turbine 0 0 0
Synthesis Gas Compressor 0 0 0
Synthesis Gas Compressor Turbine 0 0 0
Refrigerant Compressor 0 0 0
Refrigerant Compressor Turbine 0 0 0

MUG Washing Ejector 0 0 0

Steam Ejector 0 0 0

CO2 Stripper Condenser 0 0 0

0 0 0

CO2 LP Regenerator Condenser 0 0 0

Pipe Support 0 0 0
A100 FIWP 01
111-CB,1102-E,Pipe Support,160-C - 106C,Pipe Support,1102-JA/JB,Pipe Support,Pipe Support,1106-C,1103-E,1103-JA/JB,Pipe Sup
#VALUE!
PCWBS FWBS Disc. Required Doc CWP Doc. FIWP Doc

PILING
A100 38 3138 9832-EWP-1338-A100 9832-CWP-3138-A100
ENG FIWP 01
- Piling layout FIWP 02
- Design spec FIWP 03
- MTO
FIWP 04
- Typical Piling
CONS FIWP 05
- Method Statement FIWP 06
A200 38 3138 9832-EWP-1338-A200 9832-CWP-3138-A200
ENG FIWP 01
- Piling layout FIWP 02
- Design spec FIWP 03
- MTO
- Typical Piling
CONS
- Method Statement
- JSA, JRA, Lifting Plan
QC
- ITP

A300 38 3138 9832-EWP-1338-A300 9832-CWP-3138-A300


ENG FIWP 01
- Piling layout
- Design spec
- MTO
- Typical Piling
CONS
- Method Statement
- JSA, JRA, Lifting Plan
QC
- ITP

A400 38 3138 9832-EWP-1338-A400 9832-CWP-3138-A400


ENG FIWP 01
- Piling layout FIWP 02
- Design spec
- MTO
- Typical Piling
CONS
- Method Statement
- JSA, JRA, Lifting Plan
QC
- ITP

B000 38 3138 9832-EWP-1338-B000 9832-CWP-3138-B000


ENG FIWP 01
- Piling layout FIWP 02
- Design spec
- MTO
- Typical Piling
CONS
- Method Statement
ENG
- Piling layout
- Design spec
- MTO
- Typical Piling
CONS
- Method Statement
- JSA, JRA, Lifting Plan
QC
- ITP

R000 38 3138 9832-EWP-1338-R000 9832-CWP-3138-R000


ENG
- Piling layout
- Design spec
- MTO
- Typical Piling
CONS
- Method Statement
- JSA, JRA, Lifting Plan
QC
- ITP
BQ Depth
Description
Equipment
(Equipment)
Actual 20 (m) 27 (m)

Piling 01 67
111-CB,1102-E,Pipe Support 12 6 6
160-C - 106C,Pipe Support,1102-JA/JB 8 8 0
1102-JA/JB,Pipe Support 21 17 4
1106-C,1103-E,1103-JA/JB,Pipe Support 18 13 5
110x JA/JB, 108-JA/JB, Pipe Support 13 9 4
1102-F,1106-J & Aux,Pipe Support 17 8 9
Piling Rig 1 Piling 02 54
1104-E,1101-E,1101-C 20 3 17
1102-C A/B,1103-C,1104-CA/CB,1107-C 15 4 0
Pipe Support 19 16 12

Piling 03 7
Piling Rig 1 1105-L,Pipe Support 7 7 0

Piling 04 12
Piling Rig 1 1105-F,Pipe Support 12 12 0
Piling Rig 1 Pipe Support 0 0 0

Piling 05 24
Building 0 0 0
Building 0 0 0
Piling 06 88
Start Date End Date Note:
Duration Due Date Productivity = 1
UOM PMS
(days) CWP Piling Rig : 2 uni
PMS Propose PMS Propose

EA 34 44 2-Apr-24 2-May-24 13-Jun-24 8-Jul-24 14-Aug-24


EA 6 2-May-24 13-Jun-24 10-May-24 20-Jun-24
EA 4 5/10/2024 21-Jun-24 16-May-24 27-Jun-24
EA 11 5/16/2024 28-Jun-24 29-May-24 11-Jul-24
EA 9 5/16/2024 12-Jul-24 5/27/2024 24-Jul-24
EA 7 5/27/2024 25-Jul-24 6/5/2024 2-Aug-24
EA 9 6/5/2024 4-Aug-24 6/16/2024 14-Aug-24
EA 28 47 6-Jun-24 22-Apr-24 13-Aug-24 27-May-24 16.28571
EA 10 6-Jun-24 22-Apr-24 18-Jun-24 3-May-24
EA 8 18-Jun-24 4-May-24 28-Jun-24 14-May-24
EA 10 18-Jun-24 15-May-24 30-Jun-24 27-May-24

EA 4 32 11-Jun-24 29-May-24 27-Jul-24 2-Jun-24


EA 4 6/11/2024 6/17/2024

EA 6 56 7-May-24 4-Jun-24 29-Jul-24 11-Jun-24


EA 6 5/7/2024 5/15/2024
EA 0 5/15/2024 5/17/2024

EA 0 5 5-Mar-24 12-Mar-24
EA 0 3/5/2024 3/7/2024
EA 0 3/7/2024 3/9/2024
EA 0 N/A N/A
Note:
Productivity = 1 alat = 2 titik / hari
Piling Rig : 2 unit
EWP Doc.
PCWBS FWBS Disc.
Required Doc
BUILDING
B100 47 3147 9832-EWP-1347-B100
B100 ENG
- Piling layout drawing
- Foundation layout drawing
- Section & detail Foundation
B100

B100

B100 65 3165 9832-EWP-1365-B100


B100 ENG
- Foundation drawing
B100 65 3165 - Concrete structure drawing
- Architecture drawing
B100
B100 65 3165 9832-EWP-1365-B100
''''''''''''''''''''''' B100 - Architecture drawing
B100 - MTO

B100 65 3165 9832-EWP-1365-B100


B100 - Architecture drawing
B100

B100 65 3165 9832-EWP-1365-B100


B100 ENG
B100 - Foundation drawing
B100 - Concrete structure drawing
- Architecture drawing
B100
B100 C 31C 9832-EWP-13C-B100
ENG
- Layout
- BQ
- Vendor Drawing & Specification
- Typical Installation Drawing
- Cable Schedule
- Single Line Diagram
- Interconnection Diagram
- Vendor Drawing & Specification
- Typical Installation Drawing
- Cable Schedule
- Single Line Diagram
- Interconnection Diagram

B100 F 31F 9832-EWP-13F-B100


- Layout
- Specification
'- BQ
CWP Doc. FIWP Doc

9832-CWP-3147-B100-Substructure Substructure
FIWP 01 Electrical Building + Trafo Yard

FIWP 02 Operation Shelter

FIWP 03 Temporary Chemical Shelter

9832-CWP-3165-B100-Superstructure Superstructure
- Upper structure (column, beam) FIWP 01 Electrical Building + Trafo Yard
- Roof FIWP 02 Operation Shelter
Steel Structure
FIWP 03 Temporary Chemical Shelter
9832-CWP-3165-B100-Steel Structure Exterior Finishing
- Exterior Wall FIWP 01 Electrical Building + Trafo Yard
- Wall Finishing FIWP 02 Operation Shelter
- Painting
- Waterproofing
FIWP 03 Temporary Chemical Shelter
9832-CWP-3165-B100-Exterior Finishing Interior Finishing
#VALUE! FIWP 01 Electrical Building + Trafo Yard
FIWP 02 Operation Shelter
FIWP 03 Temporary Chemical Shelter
9832-CWP-3165-B100-Interior Finishing Interior Finishing
FIWP 01 Electrical Building + Trafo Yard
FIWP 02 Operation Shelter
FIWP 03 Temporary Chemical Shelter

9832-CWP-31C-B100-Plumbing & Sanitary Plumbing & Sanitary


FIWP 01 Electrical Building + Trafo Yard
FIWP 02 Operation Shelter
FIWP 03 Temporary Chemical Shelter
9832-CWP-31F-B100-Electrical Electrical
FIWP 01 Electrical Building + Trafo Yard
FIWP 02 Operation Shelter
FIWP 03 Temporary Chemical Shelter
Description
BQ
(Equipment) Duration
UOM PMS SCA Date
(days)
Plan Actual

Substructure 211 m3
Electrical Building + Trafo Yard 99 m3
Earthwork
Foundation Work
Slab
Operation Shelter 62 m3
Earthwork
Foundation Work
Slab
Temporary Chemical Shelter 49 m3
Earthwork
Foundation Work
Slab
Superstructure m2
Electrical Building + Trafo Yard 13 m2
Operation Shelter 5 ton
Steel Structure m2
Temporary Chemical Shelter 4 ton
Exterior Finishing
Electrical Building + Trafo Yard
Operation Shelter

Temporary Chemical Shelter


Interior Finishing
Electrical Building + Trafo Yard
Operation Shelter
Temporary Chemical Shelter
Interior Finishing
Electrical Building + Trafo Yard
Operation Shelter
Temporary Chemical Shelter

Plumbing & Sanitary


Electrical Building + Trafo Yard
Operation Shelter
Temporary Chemical Shelter
Electrical
Electrical Building + Trafo Yard
Operation Shelter
Temporary Chemical Shelter
4
Start Date End Date
Due Date
CWP
PMS Propose PMS Propose

Note:
Productivity = xx
FWBS Discipline EWP Doc. CWP Doc. FIWP Doc

PILING
A100 38 3138 9832-EWP-1338-A100 9832-CWP-3138-A100
FIWP 01
FIWP 02
FIWP 03
FIWP 04
FIWP 05
FIWP 06
A200 38 3138 9832-EWP-1338-A200 9832-CWP-3138-A200
FIWP 01
FIWP 02
FIWP 03
FIWP 04
A300 38 3138 9832-EWP-1338-A300 9832-CWP-3138-A300
FIWP 01
A400 38 3138 9832-EWP-1338-A400 9832-CWP-3138-A400
FIWP 01
FIWP 02
B000 38 3138 9832-EWP-1338-B000 9832-CWP-3138-B000
FIWP 01
FIWP 02
R000 38 3138 9832-EWP-1338-R000 9832-CWP-3138-R000
FOUNDATION
A100 31 9832-EWP-31-A100 9832-CWP-31-A100
FIWP 01
FIWP 02
FIWP 03
FIWP 04
FIWP 05
A200 31 9832-EWP-31-A200 9832-CWP-31-A200
FIWP 01
FIWP 02
FIWP 03
FIWP 04
FIWP 05
A300 31 9832-EWP-31-A300 9832-CWP-31-A300
FIWP 01
A400 31 9832-EWP-31-A400 9832-CWP-31-A400
FIWP 01
B000 31 9832-EWP-31-B000 9832-CWP-31-B000
FIWP 01
FIWP 02
FIWP 03
FIWP 04
FIWP 05
R000 31 9832-EWP-31-R000 9832-CWP-31-R000
Data from PMS

Description BQ Duration
Equipment UOM
(Equipment) (days)
Plan Actual

Piling 01 89 EA 46
Piling Rig 1 111-CB,1102-E,Pipe Support 15 12 EA 6
Piling Rig 1 160-C - 106C,Pipe Support,1102-JA/JB 15 8 EA 4
Piling Rig 1 1102-JA/JB,Pipe Support 15 21 EA 11
Piling Rig 1 1106-C,1103-E,1103-JA/JB,Pipe Support 15 18 EA 9
Piling Rig 1 110x JA/JB, 108-JA/JB, Pipe Support 15 13 EA 7
Piling Rig 1 1102-F,1106-J & Aux,Pipe Support 15 17 EA 9
Piling 02 66 EA 26
Piling Rig 2 1104-E,1101-E,1101-C 17 20 EA 10
Piling Rig 2 1104-JA/JB 17 4 EA 2
Piling Rig 2 1102-C A/B,1103-C,1104-CA/CB,1107-C,1101-JA/JB, 17 28 EA 14
Piling Rig 2 Pipe Support 17 14 EA 7
Piling 03 7 EA 4
Piling Rig 1 1105-L,Pipe Support 7 7 EA 4
Piling 04 12 EA 6
Piling Rig 1 1105-F,Pipe Support 6 12 EA 6
Piling Rig 1 Pipe Support 6 0 EA 0
Piling 05 24 EA 0
Building 12 0 EA 0
Building 12 0 EA 0
Piling 06 88 EA 0

Foundation 01 431 m3 228


TM 01 87 m3 7
TM 02 87 m3 7
TM 03 87 m3 7
TM 04 87 m3 7
TM 05 87 m3 7
Foundation 02 457 m3 237
TM 01 92 m3 7
TM 02 92 m3 7
TM 03 92 m3 7
TM 04 92 m3 7
TM 05 92 m3 7
Foundation 03 60.3 m3 21
TM 01 92 m3 7
Foundation 04 42 m3 -
TM 01 21 m3 7
Foundation 05 550 m3 -
TM 01 110 m3 7
TM 02 110 m3 7
TM 03 110 m3 7
TM 04 110 m3 7
TM 05 110 m3 7
Foundation 06 434 m3 12
a from PMS

Note:
PMS Due Date Start Date End Date Productivity = 1 alat = 2 titik /
hari
Piling Rig : 2 unit
44 2-Apr-24 2-May-24 8-Jul-24
2-May-24 3-Jun-24
6/3/2024 6/9/2024
6/9/2024 6/22/2024
6/9/2024 6/20/2024
6/20/2024 6/29/2024
6/29/2024 7/10/2024
47 6-Jun-24 13-Aug-24
6/6/2024 6/18/2024
6/18/2024 6/22/2024
6/18/2024 7/4/2024

32 11-Jun-24 27-Jul-24
6/11/2024 6/17/2024
56 7-May-24 29-Jul-24
5/7/2024 5/15/2024
5/15/2024 5/17/2024
5 5-Mar-24 12-Mar-24
3/5/2024 3/7/2024
3/7/2024 3/9/2024
N/A N/A

6/10/2024 1/24/2025 Note:


1 TM = 30 minute untuk
6/10/2024 6/19/2024
pouring
6/19/2024 6/28/2024 Productivity = 6 titik / hari
6/28/2024 7/7/2024 1 mini = 3 m3
7/7/2024 7/16/2024 TM = 8 m3
7/16/2024 7/25/2024
7/6/2024 2/28/2025
7/6/2024 7/15/2024
7/15/2024 7/24/2024
7/24/2024 8/2/2024
8/2/2024 8/11/2024
8/11/2024 8/20/2024
8/23/2024 9/13/2024
8/23/2024 9/1/2024
N/A N/A
N/A #VALUE!
N/A N/A
N/A #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
5/30/2024 6/11/2024
No. ITEM PCWBS STATUS FWIP QTY P&ID

Column1 Column2 Column3 Column33 Column32 Column4 Column5

24 1102-C A/B A200 FIWP 01 FIWP 03 2 PDI-0002


25 1103-C A200 FIWP 01 FIWP 03 1 PDI-0022
26 1104-CA/CB A200 FIWP 01 FIWP 03 2 PDI-0022
27 1107-C A200 FIWP 01 FIWP 03 1 PDI-0002
PILING PILING CONCRETE
DESCRIPTION Days Total
(20m) (27m) (m3)

Column6 Column103 Column102 20 27 Column11

Saturator Water Feed/Eff. Exchanger 3 5 0 5 106


DM Water Preheater 2 3 3 0 48
PC Stripper Feed/Eff. Exchanger 3 5 0 5 106
Stripped Condensate Cooler 1 2 0 2 43

You might also like