HBRC Comments.
Pipes and its accessory’s should be HG-UPVC Same brand
LEGEND, routing details (exposed or embedded) and heights should be mentioned at dwg
Contractor. To apply wire Color (R, Y, B) at S.D for approval and consider phase Balance
Contractor to coordinate with other systems at Ceiling to avoid any conflict at execution
Separate Switch & power outlet should be provided for Exhaust fans
Last Arch approved should be considered (Doors opening & Toilets) location for switches coordination
V.D calculation & panel schedule should be submitted for final approval
Cable size and no of fixtures for every circuit subject to V.D Calculation Balanced panel Loads.
Emergency switch should be separate circuit not merged with two gang switch
Final pipe and cable Tray Size Subject to approved filling ratio calculation
Latest arch approved reflects on type for lighting fixture and accessories used.