Professional Documents
Culture Documents
Nhsscotland Bim Asset Lifecycle Process Map
Nhsscotland Bim Asset Lifecycle Process Map
Nhsscotland Bim Asset Lifecycle Process Map
0 Strategic
1 Preparation
2 Concept
3 Developed
4 Technical
5 Construction
6 Handover &
7 In Use
RIBA Design Design Design Close Out
Definition & Brief
POW2013
Plan of A B C D E F J K L
RIBA POW2007
Works
Appraisal Design Concept Design Technical Production Mobilisation Construction to Practical Completion Post Practical Completion
Brief Deveopment Design Information
Maps to OGC Maps to OGC Maps to OGC Maps to OGC Maps to OGC Maps to OGC
OGC Phase 0 Phase 1 Phase 2 – Procurement Strategy Phase 3 – Investment decision Phase 4 – Go Live Phase 5 – Benefits Realisation
Gateways Gateway 0 Gateway 1
business
Written by Health Board
Sanctioned or justification
terminated by CIG
Phase 0 Phase 1 Economic case (part 2) Economic case Progress Report Dashboard: Cash Flow Programme Export data to
Strategic Case Consideration of Determining value for money Procure the VFM Solution CAFM and AMS
Financial, Commercial &
Management Cases. 1st
Ascertain Draft of Economic Case Commercial case Commercial case Change management / Early Warning Internal and external audit
Scottish Capital Strategic Fit Preparing the potential deal Contracting for the deal
Investment Manual
Establish: Prepare the Financial case Management case Manage Risk Register Benefits register
Business Case Guide Current arrangements initial agreement Ascertain affordability & Funding Requirements Ensuring successful delivery
The need for change
The benefits gained
Benefits link to NHS Explore the preferred Management case Post project evaluation User Evaluation
Scotland’s Strategy way forward Planning for delivery Achievement of benefits
The Solution being
considered to deliver these
benefits Evaluation of existing
provision
Design Development
Design development WP design
The attainment of
Statutory Approvals Statutory Approvals
maybe staged to meet
programme requirements
KEY DESIGN 1 2 3 4 5
INFORMTION
EXCHANGES
Early Early Late Late Prior to
in I / A in OBC in OBC in FBC Operation
INFORMATION
GROWTH OVER Project Information Model (PIM) Asset Information Model (AIM)
PIM AND AIM
Level of definition established on a project basis set out in MIDP + BIM Proto-
col
Documentation
Inforamation Model
Handover
Non-Graphical Data
Graphical Model
Project Costs
Initial project budget Feasibility cost plan Commitment Cost Contract Sum/ Contract Sum/ Final account
Plan Target Price/ Target Price/
Order of cost estimate Feasibility whole life cost Agreed Maximum Agreed Maximum Price
plan Contractor’s first Price
stage bid submission Pre-construction whole life
Pre-construction cost plan
Detailed whole life whole life cost plan
cost plan
Domain + Federated Model (s) Creation + Management Export Data to AMS / CAFM
0 Strategic
1 Preparation
2 Concept
3 Developed
4 Technical
5 Construction
6 Handover &
7 In Use
RIBA Design Design Design Close Out
Definition & Brief
POW2013
Plan of A B C D E F J K L
RIBA POW2007
Works
Appraisal Design Concept Design Technical Production Mobilisation Construction to Practical Completion Post Practical Completion
Brief Deveopment Design Information
KEY DESIGN INFORMATION EXCHANGE KEY DESIGN INFORMATION EXCHANGE KEY DESIGN INFORMATION EXCHANGE
INITIAL ASSESSMENT (IA) OUTLINE BUSINESS CASE (OBC) OUTLINE BUSINESS CASE (OBC)
STAGE: Late in the IA process when a capital investment STAGE : Early in the OBC process an informal consulta- STAGE: Late in the development of the OBC, when the design is becoming formed but is still open to influence –
project appears to be a serious possibility. tion on site selection and strategic briefing considering: consultation and response to use in Business Case Stage.
STAGE : Late in the development of the FBC, when the design is becoming formed but is still open to influence. Geometric models: proprietary 3D BIMs with 2D PDFs cut from the models to the above noted levels of definition / scales. Feder-
Methodology: One of the following – as advised in the NHSScotland Design Assessment Process’s response to the OBC submission: ated model in an agreed format e.g. Industry Foundation Class
• Desktop assessment based on submitted information, supplemented by conversations with project team to clarify any matters.
• Panel assessment, based on submitted information and supplemented by presentation by, and discussion with, project team including Non-graphical information to be provided in an agreed electronic format e.g. COBie as per PAS1192-4
designers.
Submission requirements
For all projects
• Completed submission pro-forma identifying key contacts and dates. Info
• Design Statement , with any updates in benchmarks highlighted. Drop 3
• Evidence of completion of self assessment on design in line with the procedures set out in your design statement.
• Extract from draft FBC detailing benefits and risks analysis (appendix 3 in SCIM).
• Completed AEDET review at current stage of design development.
• 3D models of design proposals for key spaces identified in Design Statement.
• Updated list of relevant design guidance to be followed (see section 1.1) and schedule of any derogations in relation to these.
• BREEAM Healthcare assessment (including relevant energy model information e.g. BRUKL)
• Evidence that relevant DDA, Dementia, Health Promotion and Equality requirements has been incorporated.
• Evidence that Activity Data Base (ADB) is being fully utilised during the preparation of the brief and throughout the design and KEY DESIGN INFORMATION EXCHANGE
commissioning process
HANDOVER AND CLOSE OUT
For capital investment schemes and projects likely to go through all procurement, the following information is required to allow the panel to
establish that the developed proposals are living up to the promise of the outline proposals at OBC stage and that the technical matters are Information as set out in the Employers Information Requirements (EIR)
being addressed.
• Final Design study showing developed proposals (RIBA Stage Stage 3: Developed design, plus key elements at Stage 4: Technical STAGE: Prior to operation
design; e.g. ≤1:200, majority of spaces ≤1:50, plus key elements ≤1:20 ).. Key drawings, (construction details/specs need not be
submitted) including Geometrical models, federated models and linked data e.g. operation and maintenance manuals plus
• Site layout showing wider context and landscape proposals relevant record survey (e.g. point clouds) all with agreed classification.
• Plans rendered to distinguish between use types (circulation, consult)
• Elevations/ Sections showing design in context Non-graphical data – cleansed and mapped to AMS / CAFM systems
• Building Services Report and Layouts
• Structural/ Civil Report and Layouts
• Landscape Report and Layouts Information to be provided in an electronic format:
• Specialist Report and Layouts
• 3D visualisations of the building in context – including key approaches perspectives from a human eye height Geometric models: proprietary 3D BIMs with 2D PDFs cut from the models plus federated model in an agreed format e.g. Industry
• Confirmation of Planning Permission and Building Regulation compliance. Foundation Class
For NPD schemes, the above information, should be partially submitted prior to preferred bidder status to allow an NDAP pre-assess- Non-graphical information to be provided in an agreed electronic format e.g. COBie as per PAS1192-4
ment. This may be used by client and bidders to assist in their selection process of the preferred bidder. Following selection, a FBC Associated record information eg. point cloud surveys.
assessment will be carried out on the preferred bidder’s Final Design Study. However it is anticipated, this could simply be a confirmation
or minor adjustment of the pre-assessment report.
Information to be provided in an electronic format: Info
Drop 5
Geometric models: proprietary 3D BIMs with 2D PDFs cut from the models to the above noted levels of definition / scales. Federated
model in an agreed format e.g. Industry Foundation Class
Non-graphical information to be provided in an agreed electronic format e.g. COBie as per PAS1192-4
Info
Drop 4