Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

RIBA stages 2020


Civil Engineering
(https://civilsguide.com/c
ategory/general/)
September 6, 2020

(https://ww
What is the RIBA stages 2020 plan of works w.instagram

Table of Contents  .com/)


1. What is the RIBA stages 2020 plan of works
2. Key Changes between RIBA stages 2020 and 2013 plan of work
3. RIBA Stage 0 – Strategic Definition
4. RIBA Stage 1-Preparation of Brief
5. RIBA Stage 2 – Concept Design
6. RIBA Stage 3 – Spatial Coordination
7. RIBA Stage 4 – Technical Design
8. Prescriptive information vs Descriptive information
9. RIBA Stage 5 – Manufacturing and Construction
10. RIBA Stage 6 – Handover
11. RIBA Stage 7 – Use

Established by Royal Institute of British Architects (RIBA).


Originally launched in 1963 in a simple matrix format which has been continually updated since.
RIBA 2013 was originally designed to be a interactive web-based resource but the matrix was often
used instead of the website.
Tool to organise process of designing, delivering, maintaining, operating a building into 8 stages.
Used by all disciplines involved in project (i.e, structural (/civil-engineering-2)& civil engineers (/civil-
engineering-2), architects, MEP, etc.)
Used as a guidance tool for preparation of professional services and building contracts


RIBA 2020 Stages of Work

Key Changes between RIBA stages 2020 and 2013 plan of work

Changes has occurred to help designers use the plan of works more effectively and clear any
misconceptions/mistakes being made. Stage 3 and Stage 5 Names change from Developed design (old
stage 3) and Construction (old stage 5).

RIBA Stage 0 – Strategic Definition

Client develops strategic Brief.


At this stage, there shouldn’t be any design (i.e, no engineers/architects undertaking designs but
limited involvement may happen by providing technical advice etc)
Client led stage where requirements are listed and assessed, risk and costing assessed
Building may not be the answer (no need to progress with RIBA plan of works)
Client figuring out how to achieve objective.
Stage 0 could be a 1-3 year process before stage 1.

Core Tasks:

Designers contribute to client requirements (limited involvement to no involvement)


Sustainability – strategic plan in relation to client requirements (developing existing buildings or
extending as opposed to demolition or maybe a new structure is not required)

RIBA Stage 1-Preparation of Brief

Preparation of Initial Project Brief with a record for the detailed requirements. Design tasks do not
happen at this stage.
Client team develops responsibility matrix. (Ensure relevant disciplines and tasks allocated). Important
for engineers to know what tasks they are required and what they are responsible for)
Obtain site information and site surveys (UXO, buried services, asbestos).
Project execution plan to be developed (client time frame)
Feasibility study to be carried out to identify whether the site can accommodate the client’s needs.
Architect’s and structural engineers can get involved but this is not considered as design phase which
starts at stage 2.

Stage Outputs:

Initial project brief


Site information
Structural constraints 
Structural survey reports
Structural survey reports
Climate change impact statements


RIBA Stage 2 – Concept Design

Architect’s expression/concept applied to brief (achieve client’s vision, budget).

Too much detail at this stage can derail design effort’s from setting the best strategy, but too little
detail can affect stage 3.
Structural engineering designs based on rule of thumb (i.e, hand calcs, sketches, advice on grids, initial
calculations). No 3D models/detailed models required for this stage.
Determine project strategies (does design impact architect’s concept, or structure too costly for the
project).
At this stage, various design options should be gone through (especially if you want to hit BREEAM
credits), and to determine which kind of structure is sustainable and within client’s budget.
Develop and contribute to the BIM execution plan.

Stage 2 Outputs/Deliverable:

Develop basis of design (i.e. define structural standards, loadings, fire resistance, serviceability criteria,
etc) – technical interpretation of project brief.
Identify whether specialist subcontracts are required in basis of design.
Develop a foundation strategy.
Deliverables list (define what needs to be delivered at each stage).
Design programme to be developed by lead designer and agreed with client and all other designers.
Structural sustainability report (can be included in basis of design – how will sustainability targets be
achieved).
Initial structural drawings (i.e. sketches of grids, no BIM required by engineers). However, this needs to
be confirmed by the project team and client if 2D or 3D models are required.
There is a risk on progressing too much with a detailed 3D structural model due to later changes at
stage 3 of RIBA stages 2020.


RIBA Stage 3 – Spatial Coordination
Concept design should be progressed and not changing at this stage for single solution that aligns

with project brief. 


Further design studies for a preferred option.
More details – detailed structural model and calculations for design solution and cost exercises.
Design solution for economy of materials through detailed analysis.
Confirm structural grids and zones.
Spatially co-ordinate structural design and integrate with other disciplines (MEP zones locations need
to be identified).
GA’s should be signed off in this stage to allow progression into stage 4 of RIBA stages 2020.
Consider construct-ability issues at this stage (Can the structure be built through conventional means
or is it a complex process)?
Risk should be highlighted at every stage of the RIBA plan of works but specific temporary works items
need to be identified and communicated to the contractor (i.e. jacking/preloading/temporary supports
or undermining)
Assist lead designer with preparation of design programme.

Stage 3 Outputs/Deliverables:

Structural drawings (2D layouts, GA’s and elevations) and 3D BIM model.
Movement and Tolerances Report (recommended)
Outline structural specification
Performance specification for contractor design items
Outline structural sustainability report outlining targets and strategies to meet them (including
embodies carbon).
Implement/develop change control procedures

RIBA Stage 4 – Technical Design

This stage is the final design stage where all design information should be fully co-ordinated and
completed to enable the manufacture of the project to be progressed.
General overlap between stage 4 and 5 but there is also a sub-stage in stage 4, which involves
specialist subcontractor design and detailing items (e.g. pile design, steelwork connection etc).
At this stage, the responsibility matrix becomes important, as it is a reference point for which task
need to be completed by whom.
Spatial arrangement should not change (i.e. MEP zones fixed, GA’s signed off, etc)
Prepare and co-ordinate specialist contractor’s information including final specifications.
Develop temporary works brief and review temporary works design at stage 4 sub-stage (stage 4.5:
production design)

Stage 4 Outputs/Deliverables:

Structural Drawings (Suitable for construction)


Finalise structural specification
Structural Sustainability Report

Temporary Works Brief


Clash detection and clash resolution
Review of specialist sub-contractor designs

Prescriptive information vs Descriptive information

Descriptive information is issued by design team to allow specialists subcontractor to prepare


manufacturing information (i.e. referred as design intent, where specific details and specification
has to be adhered to)
Prescriptive information is information used to manufacture and construct building systems b the
design team.


RIBA Stage 5 – Manufacturing and Construction

Construction on Site has begun and at this stage, we should be involved in solving site queries (who is
responsible?).
Undertake site visits and inspections.
Prepare Building Log Book, O&M Manual
There is typically an overlap between stage 4 and 5 in RIBA stages 2020.
‘As-constructed’ information to be prepared and agreed by relevant parties
Stage ends with practical completion of the project.

Stage Outputs:

Handover documentation
Completion of project from structural engineering point of view

RIBA Stage 6 - Handover

Building is officially handed over, Aftercare initiated and Building contract concluded.
Construction team rectifies any residual defects.
Project performance needs to be facilitated (Lesson learned)
Post occupancy evaluation.
Has sustainability targets been achieved ? (needs to be documented and refer to RIBA stages 2020)

RIBA Stage 7 - Use

This stage is the operation and maintenance of building over its lifetime.
Majority of team’s work completed by stage 6 and very limited input at this stage.
Potential ongoing tasks, if maintenance obligations in building contracts extend past stage 6.
Post occupancy evaluation commissioned to determine how the building is performing and used to
help inform future projects.
At the end of a buildings life, stage 0 commences again (Re-use existing building or demolish and use
RIBA stages 2020 plan of works again).

Top Posts
Volume of a Pyramid – Example Calculations (https://civilsguide.com/volume-of-a-pyramid-example-calculations/)
Read More » (https://civilsguide.com/volume-of-a-pyramid-example-calculations/) 
READ MORE » (HTTPS://CIVILSGUIDE.COM/REINFORCED-CONCRETE-DESIGN/)

ABOUT US

My goal is to provide an effective revision tool for university students on their


engineering course at university.

MENU

(htt
ps:/
(htt (htt /ww
Sps:/ A L w.li
O C I ps:/
/w /w nke
ww. ww. din.
Action on Structures
inst fac co
agr m/i
am. ebon/ci
Engineering Equations
ok.c
coConcrete
om vils-
m/c /civi gui
ivils lsgu de-
gui ide) a01
Steel Design
de/) 96b
202
Structural Timber
/)
Masonry

You might also like