Date of Update: 8-Oct-2023

Project Name : INTERCONNECTION OF HEET WATER TREATMENT SUBSTATION 7723 WITH SUBSTATION 8719 IN AL-KHARJ AREA.

Project Manager Name : ENG. Ahmed Omer Mohamed


Link Name : Substation 8719 TO SS 7723
Subcontractor Name : Keir International
Sit engineer Name : ENG. Safnas ENG. Safnas
Foreman Name : MR. Abdellah Zahra MR. Abdellah Zahra
Number of Groups : 1 1
Total of Manpower : 12 12

Percentage of Incremental
Daily Basis Work done
Progress

Total
Estimated Total
Description UOM 5-Oct-2023 7-Oct-2023 Cumulative 5-Oct-2023 7-Oct-2023 Percentage of Progress
Work
Work done
Safety Aarrangment 20078 m 1220 0.00% 0.00% 6.08%
Trench Excavation 20078 m 1220 0.00% 0.00% 6.08%
Manhole Excavation 5 Nos 0 0.00% 0.00% 0.00%
Handhole Excavation 65 Nos 2 6 0.00% 3.08% 9.23%

Trench sweet sand/Fine sand bedding 20078 m 1220 0.00% 0.00% 6.08%
Power cable pulling 40156 m 1000 1000 2000 2.49% 2.49% 4.98%
Fiber optic duct laying 20078 m 440 290 730 2.19% 1.44% 3.64%
Power Cable joints 78 Nos 0 0.00% 0.00% 0.00%
Fiber Optic Cable joint closures 3 Nos 0 0.00% 0.00% 0.00%
fine sand placement on top of cable
inside trench 20078 m 0 0.00% 0.00% 0.00%
Protection Tile laying 20078 m 0 0.00% 0.00% 0.00%
first phase of back filling 20078 m 0 0.00% 0.00% 0.00%
Warning tape laying 20078 m 0 0.00% 0.00% 0.00%
backfilling and compaction 20078 m 0 0.00% 0.00% 0.00%
Manhole installation 5 Nos 0 0.00% 0.00% 0.00%
Handhole installation 65 Nos 0 0.00% 0.00% 0.00%
Aspault work 40 Nos 0 0.00% 0.00% 0.00%
Fiber optic cable pulling 20078 m 0 0.00% 0.00% 0.00%
Daily Basis % of Completion 0.54% 0.81%
Cummulative % of Completion 2.37% 3.18% 3.18%