Professional Documents
Culture Documents
Hydrotest Failure Investigation Reports
Hydrotest Failure Investigation Reports
Introduction
Material supplier
Witnessed QC assurance Inspection
Lloyds Certification
All the arrived pipes were stacked in designated location, prior to executing the
work all the pipes are visually inspected and defective materials itemized and
separated , during the inspection both parties were involved (AOO & AOS) .in
addition all the damaged pipes are segregated, which required more in-depth
inspection , each pipe is checked ensuring the physical condition in addition it
was agreed to carried out visual internal and external inspection, Internal gauge
test on the ovality, bevel and dent inspection prior to sending pipe to site, all
anomalies are categorized in the below reports highlighting detailed defects ,
pipe numbers and heat numbers
All the work has been executed at site with Inspected and accepted pipe from
both parties, all construction activities have been performed as per the approved
procedure and specifications
About above subject, Investigation on the subsection -B 18” pipe line hydrotest
failure that occurred on March 23,2023
As shown below table attached, the hydrotest failed at a pressure point of 93.36
bar (1354psi) after 5 hours from starting pressurization, before reaching the 3rd
increment hold point as per procedure 105 brag.
The causes of the hydrotest failure was base metal fracture CRACK as shown in
Fig 1&2 Below) That was discovered.4.17km from B-Field towards D-Field
For more clarification see below attached annex (figures, Curve, Table)
FIRST
HOLD POINT
SECOND
HOLD POINT
+`
PRESSURE
DROP OUT POINT
Conclusion
Prepared by
Construction lead inspector
Anees v Thaha
24/03/2023