STEP BY STEP Risk Risk
Hazards & Risks Score Controls Required Score Responsibility
Assess the
Break the activity into sequential risk Assess the Identify who is
Identify what controls will be implemented to manage the hazard / risk,
steps and identify the potential presented risk after responsible for
Refer to Hierarchy Of Controls eg Design out, Eliminate, Substitute, Engineer out, Isolate,
hazards and/or risks associated by the applying implementing the
Administration, PPE
with each step hazard controls controls
Crane Crew unsure of 7 All members of the Crane Crew will need to be: 2 Crane Operator
site procedures site inducted; All Crew
trained in this SWMS;
involved in the site-specific risk assessment for the work;
Make sure you are aware of the site’s emergency procedures.
If at any time you are unsure or have questions – Speak Up & ask your
Supervisor and/or site manager for advice.
Pre Job Risk Assessment 9 You must inspect the site and complete the Site-Specific Pre-Job Risk 2 Crane Operator
Assessment form before commencing work activity. All Crew
Do not commence work until you are satisfied the job is safe!
Unsure of scope of work 7 Confirm with the Client the details of the job including scope of work, 2 Crane Operator
Request information on any specific hazards/risk that may affect the
team and work activity.
Toolbox Talks 9 You must conduct a toolbox talk prior to carrying out the work and 2 Crane Operator
record topics discussed on a Toolbox form. All Crew
Crane not suitable for 8 Operators “know your crane” eg charts, indicators, limitations, 2 Crane Operator
task at hand controls. If work required from the Client does not equal the work that
is actually required, advise the Client. Do not ever attempt to operate
the crane outside its capacity (WLL).
Personnel not 8 All workers involved in this activity have been assessed as competent to do 2 Crane Operator
qualified for task so. All workers have been provided with the required training & hold an All Crew
appropriate licence eg: riggers, , crane operator.
Trainees will be under direct supervision at all times and will hold a
Log Book.
Page 7 of 15
Chemical spills eg. 8 Cranes to carry an effective spill kit cif required. Crane crew to follow 2 Crane Operator
hydraulic oil, diesel, spill kits instructions. All Crew
coolant
No identification of site 8 As a team, the Crane Crew will look up down and around to identify 3 Crane Operator
specific hazards potential hazards and will do this throughout the works, if site conditions All Crew
change conduct another site specific risk assessment.
Consider the proximity of * overheads, * structures, * people, * plant, *
traffic, * underground services, * visibility, * noise.
Assess the risks and control. If unsure speak to the Client to resolve. You
are the expert - Do not accept pressure from others to work unsafely –
contact Capital Cranes Management if you need assistance.
Lifting gear fails during lift 8 Rigger to assess the load and to determine the slinging method. 2 Crane Operator
causing load to fail Lifting gear is to be selected, inspected before use and rigged by a trained, Rigger
striking a person or qualified and competent Rigger.
causing damage Lifting gear will be within current test and will be rated and rigged to suit the
load.
Use edge protection for synthetic slings if they might become damaged.
Load falls apart during lift 9 Rigger to assess the load and to determine the slinging method. If 2 Crane Operator
causing load to fall necessary reduce split the load to reduce mass. Rigger
Only lift loads from approved lifting points. If unsure request the certified
lifting certificate for the load from the Client.
Crane operator to lift load 100mm for the Rigger to inspect.
Always inspect lifting points before use & do not assume all lifting points are
the same type / size - especially on pre-cast concrete units.
All loads must be secure;
If a load falls, stop work immediately, make safe, notify LCH
Management and do not use the crane again until it has been inspected &
cleared.
A load will not be left suspended.
STEP 6 – TRAVELLING LOAD
SWMS for General Lifting - July 2016
Crane fails when 7 Only travel with load if the crane is designed to do this. Suspension locks 2 Crane Operator
travelling with load to be used if fitted. Keep the load clear from the ground but as low as
causing person to be possible.
struck or damage to Crane to travel at slow speed eg walking pace.
the crane or structures
Load moves 7 Inspect the path of travel for trip, slip or fall hazards and arrange for them to 2 Crane Operator
uncontrollably when load be eliminated. Rigger
is being walked Control the movements of vehicles or other traffic by isolating the area or by
using spotters.
Use tag lines to secure and control the load. Franna crane to travel at
walking pace.
Person crushed 8 Communication between Rigger and Crane Operator to be clear and 3 Crane Operator
under load when it is concise; All other workers to keep clear of the load until it is landed, stable All Crew
being landed and secure.
Manual handling 7 Change position and/or location to eliminate overreaching when removing 3 Crane Operator
injury when removing lifting gear. All Crew
lifting gear
Workers struck by 7 Isolations maintained until immediately prior to crane being moved out. 2 Crane Operator
site traffic causing All Crew
serious injury
Fall from height when 7 Use the rails and steps on the crane when embarking or disembarking. 3 Crane Operator
accessing crane or Three point contact to be maintained at all times. Inspect for mud or All Crew
climbing in and out of anything else that could make surfaces slippery and remove the hazard.
crane
STEP 12 – LEAVING SITE
Changes to site 7 If you have reason to believe site conditions have changed while you have 2 Crane Operator
conditions results in been working pre-inspect the route on foot first. All Crew
additional hazards
Hazard created to site 7 Advise the Client of impending departure so that traffic controls can be put 3 Crane Operator
and public traffic when in place. Crane to have all hazard lights and headlights on prior to All Crew
the crane leaves site departure.
Left over materials and 7 Remove all materials and equipment from the work area before leaving. 2 Crane Operator
equipment cause All Crew
hazard to others