For 5m Depth Cushion 837-2

Existing Span 6.10 m Ext dis Prop Dis bearing width 0.31
Existing effective Span 6.41 m 7.6075 7.8125
Existing total Span 6.72 m
Proposed Span 6.50 m NO OVERLAP
Sleeper width 2.75 m RBG 25 T 300mm cushion 25 T 400 mm cushion
Ballast Cushion 0.35 m Span EUDL Span EUDL Span EUDL
Existing Fill 9.07 m 6.5 96.8 6 96.8 6 95.6
Proposed fill 9.28 m 6.72 m 98.384 6.72 m 102.272 6.72 m 101.216
C/c between track 15.77 m 7 100.4 7 104.4 7 103.4
Dry Density 1.80 T/m3
(Sleeper width+ballast cushion+
Total Dispersion Width = 15.22 m
depth of fill+Span/2)

Total Dispersion Width(Including track centre) = 30.99 m

Cushion Load = 16.695


For RBG Loading
EUDL For Span 98.38 T
Summary
Load intensity 1.060041051 RBG 25 T Both
Live load intensity 1.0600411 1.09624346 0.99363981
Total Load intensity 17.75504105 Y Total Load 17.755041 17.7912435 17.6886398

For 25T Loading


EUDL For Span 101.74 T

Load intensity 1.096243461

Total Load intensity 17.79124346 P

For total load % increase in stress 0.5767087


EUDL For Span 200.13 T

Load intensity 0.993639808

Total Load intensity 17.68863981