Tentative Timeline (Daily) - Template
Tentative Timeline (Daily) - Template
Tentative Timeline (Daily) - Template
PRE-OPERATION
Pre-Operation Workshop (JKT)
Mobilization Start-Up
- Early Induction
to Party Chief & Team
- Basecamp Set-Up
- Induction Crews
[Main Contractor]
- Field Camp Set-Up
- Induction Crews
[Sub-Contractors]
- Radio/Repeaters Set-Up
Benchmark GPS
Crews Induction
Equipment Inspection
3D Ketemu Area
- Installment
- Measurement
2D Eastern Area
- Installment
- Measurement
2D Western Area
- Installment
- Measurement
OPERATION
Topography 3D Ketemu
- Line Surveying
- Line Clearing
- Bridging
TEST PARAMETERS
(APL, 3 Location)
- Preparations
- 3D Ketemu
start Landowner Sos
start Line Surveying
start Shothole Drilling
start Layout Cable
start Check Trace
The D Day Partest
Evaluation
Result
- 2D Eastern
start Landowner Sos
start Line Surveying
start Shothole Drilling
start Layout Cable
start Check Trace
The D Day Partest
Evaluation
Result
- 2D Western
start Landowner Sos
start Line Surveying
start Shothole Drilling
start Layout Cable
start Check Trace
The D Day Partest
Evaluation
Result
RECORDING
• Crews Induction
• Equipments Inspection
3D Ketemu (12,572 SPs)
Start Recording 3D Production
DATA INVENTORY
Parameter Test Location :
3D Ketemu
2D Eastern
2D Western
Production :
3D Ketemu
QUALITY CONTROL