Tentative Timeline (Daily) - Template

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Year 2023 Year 2024

TENTATIVE SCHEDULE October November December January


30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
Letter of Intent PCJ-3571-CA
Effective Date

PRE-OPERATION
Pre-Operation Workshop (JKT)

Mobilization Start-Up
- Early Induction
to Party Chief & Team
- Basecamp Set-Up
- Induction Crews
[Main Contractor]
- Field Camp Set-Up
- Induction Crews
[Sub-Contractors]
- Radio/Repeaters Set-Up

Local Socialization Campaign


Preparations
1st District
2nd District
3rd District
4th District
5th District

Benchmark GPS
Crews Induction
Equipment Inspection
3D Ketemu Area
- Installment
- Measurement

2D Eastern Area
- Installment
- Measurement

2D Western Area
- Installment
- Measurement

CSMS Pre-Job Activity


- Bridging HSSE Plan
- Administration CheckList
- Final Inspection

Kick Off Meeting [Jambi City]

OPERATION
Topography 3D Ketemu
- Line Surveying
- Line Clearing
- Bridging

TEST PARAMETERS
(APL, 3 Location)
- Preparations
- 3D Ketemu
start Landowner Sos
start Line Surveying
start Shothole Drilling
start Layout Cable
start Check Trace
The D Day Partest
Evaluation
Result

- 2D Eastern
start Landowner Sos
start Line Surveying
start Shothole Drilling
start Layout Cable
start Check Trace
The D Day Partest
Evaluation
Result

- 2D Western
start Landowner Sos
start Line Surveying
start Shothole Drilling
start Layout Cable
start Check Trace
The D Day Partest
Evaluation
Result

DRILLING & PRELOADING


• Crews Induction
• Equipments Inspection
3D Ketemu (12,572 SPs)
Start Drilling Production 3D

RECORDING
• Crews Induction
• Equipments Inspection
3D Ketemu (12,572 SPs)
Start Recording 3D Production

DATA INVENTORY
Parameter Test Location :
3D Ketemu
2D Eastern
2D Western

Production :
3D Ketemu

QUALITY CONTROL