Professional Documents
Culture Documents
Bridge Construction Method
Bridge Construction Method
Prepared by:
Clinton P. Pagunuran
ENGINEER II
Part I- Introduction
Part II- Classification of Bridges
COURSE OUTLINE
Part III- Construction of Bridge Foundation
A. Accessibility
B. Construction of Bridge Foundation
1. R. C. /Prestressed Concrete Piles
2. Steel Piles
3. Cofferdam
4. Bored Piles
5. Footing/Shaft/Coping
C. Construction of Bridge Superstructure
1. Reinforced Concrete Deck Girder
2. PSC Girders
3. Steel Bridges
4. Cable Stayed Bridges
5. Ach Bridges
Part IV – Common Problems in Bridge Construction
I. INTRODUCTION
a.1) Superstructure
Horizontal portion of the bridge which
spans the obstacle.
a.2) Substructure
Supports the superstructure and
transmits the dead and live loads to
the foundation. It accommodates
adequate resistance to vertical and
lateral loads.
I. INTRODUCTION
Parts of a Substructure
oFoundation
oAbutments
oPier
oBearing
I. INTRODUCTION
b) Types of Bridge Foundation
b.1)Spread Footing
Suitable for shallow foundation. Disadvantages;
inability to withstand horizontal forces/bending
moment, danger posed by scouring & difficulty for
underwater construction
footing
I. INTRODUCTION
Common Types Of Pier
Applied if working
on a wide river bed
with low level of
water flowing
Abut. "A"
occupying a narrow
area.
a.1 Construction of casting yard, either concrete or on Construction of square holes to be made of cocologs, good lumber or
timber platform. structural steel to serve as guide to maintain its verticality/alignment
a.2. Placing of cellophane, then installation of side forms. during driving. Square holes are provided at two (2) levels, 1 st at near
a.3. Proper assembly and installation of rebar (number,
ground surface and 2nd at 3 meters above its level.
spacing, hook, splicing, and concrete spacer.)
a.4. Forms at but end should be perpendicular to the
vertical axis.
a.5. For segmental piles, provision of pipe sleeves for 1st b.2. Lifting/Spotting of Piles
segment and dowels for the 2nd segment.
R. C. Piles shall be lifted or moved properly supported at the points
1. Installation of pile shoe. shown on the plans. It not shown, they shall be supported at the
2. Concreting works. quarter points.
- Used of concrete mixers, vibrators, approved
construction materials, design mix and required b.3. DRIVING OF PILES
slump.
3. Sampling of concrete.
All piles shall be driven as shown on the plans or as ordered in writing
4. Concrete curing.
5. Removal of forms (after 24 hours). by the Engineer, using appropriate equipments, materials and
methodology.
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.1 Pre-cast Concrete Piles
IMPORTANT NOTES :
d. Driving Equipment
o Drop Hammer
o Single Acting Hammer
o Double Acting Hammer
o Diesel Hammer
o Vibratory Hammer
III-B.1 Pre-cast Concrete Piles Project: Construction of Mabolo Bridge Province: Camarines Sur
Location: Naga City Hammer Used: M-23
Pile No. & Location: Pile Bent # 20-D Weight of Ram: 22.57 KN
d. Driving Equipment Required Bearing Capacity: 344 KN
Cut-Off Elevation: (+) 1.53 m WHERE:
Date Driven: 01-15-03
Disadvantages-1)require more
investment
2)More complicated/high
maintenance cost
3)More time to set up/take down,
4)require large operating crew
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.1 Pre-cast Concrete Piles
d. Driving Equipment
o Drop Hammer
o Single Acting Hammer
o Double Acting Hammer
o Diesel Hammer
o Vibratory Hammer
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.1 Pre-cast Concrete Piles
e. Driving of Piles
b. Establish vertical and horizontal control points (benchmark) that are fixed and
non-movable near the abutment for easier and expeditious control and re
checking of the actual elevation and alignment.
c. Level the area and the location of the Bridge Abutments and Piers with adequate
working area for construction equipment and temporary stock pile of excavated
materials
4 meters
0.40 m.
o Splice Can
o Build-up
o Structural Epoxy
Male/Female
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.1 Pre-cast Concrete Piles
g. Importance of Driving Each Pile Continuously
III. Construction of Bridge Foundation
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.2 Steel Piles
Types of Monotube Piles
Common Types of Steel Piles
Unit Weight
depends on the
design and
indicated in the
Mill Certificate
III. Construction of Bridge Foundation
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
STAKE OUT SURVEY
a. Establish the alignment of the bridge structure H-Pile
and the location of Abutments and Piers based
from the known reference elevation and
coordinates provided in the approved plans
Timber Cofferdam
Steel Cofferdam
III. Construction of Bridge Foundation
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.4 Bored Pile
Advantages Over Driven Piles Disadvantages
o Larger sections oRequires specialized personnel
o Can penetrate hard layers oRisk of disturbed soil around the pile
o Adapts to different depths oRisk of poor contact at the base
o Risk of false refusal is eradicated oFrequently difficult to keep site clean
o Less vibration and not noisy
o Fast execution
o More economical
III. Construction of Bridge Foundation
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.4 Bored Pile
Assembly of Reinforcing Steel Cage Bars Installation of Reinforcing Steel Cage Bars
for Bored Piles for Bored Piles
III. Construction of Bridge Foundation
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.4 Bored Pile
First Stage
Drilling Works
III. Construction of Bridge Foundation
III-B. CONSTRUCTION OF BRIDGE FOUNDATION
III-B.4 Bored Pile
o Girder
o Diaphragm
o Deck Slab
o Bridge Railing and Sidewalk
Installation of rebars and Concrete Pouring for Girder Installation of RSB Deck Slab
side forms for Girder
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.2 Prestressed Concrete Girder (PSCG)
Installation of Forms and Bracings for Deck Slab. Preparation for Deck Slab Pouring.
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.2 Prestressed Concrete Girder (PSCG)
Pouring Sequence
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.3 Steel Bridges
Steel Girder with Reinforced Concrete Deck. Concrete Sidewalk Bridge Drain
for Steel Girder Bridge
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.3 Steel Bridges
Expansion Dam
Sliding Plate
• Fixed
• Expansion
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.3 Steel Bridges
Bridge Bearings
• Neoprene bearing pads
• Pot bearings
• Spherical bearings
• Sliding plates
• Up-lift bearings
• Rocker bearings
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.3 Steel Bridges
Bridge Bearings
• Neoprene bearing pads
• Pot bearings
• Spherical bearings
• Sliding plates
• Up-lift bearings
• Rocker bearings
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.4 Suspension Bridge/ Cable-stayed Bridge
The cable-stayed bridge is optimal for spans longer than cantilever bridges, and
shorter than suspension bridges. This is the range where cantilever bridges would
rapidly grow heavier if the span were lengthened, and suspension bridge cabling
would not be more economical if the span were shortened.
There are two major classes of cable-stayed bridges: harp and fan.
In the harp design, the cables are nearly parallel so that the height of
their attachment to the tower is proportional to the distance from the tower to their
mounting on the deck.
III. Construction of Bridge Foundation
III-C. CONSTRUCTION OF BRIDGE SUPERSTRUCTURE
III-C.4 Suspension Bridge/ Cable-stayed Bridge
CAUSES
1. INADEQUATE LATERAL SUPPORT
2. SQUARE HOLES NOT ALIGNED VERTICALLY
3. PILE TIP STRIKE A BOULDER
CAUSES
CAUSES
1. LACK OF LATERAL SUPPORT
2. EXCESSIVE DRIVING
3. OVERWEIGHT HAMMER
4. WEAK CONCRETE
5. IMPROPER LIFTING OF PILES
GROUND LINE
REMEDIAL MEASURES
1. REMOVE AND REPLACE
CAUSES
1. PRESENCE OF HARD STRATA
2. HAMMER USED IS VERY LIGHT
3. USED OF INAPPROPRIATE TYPE OF PILES
4. USED OF INAPPROPRIATE TYPE DRIVING
EQUIPMENT
GROUND LINE
CAUSE
1. UNDERLYING STRATA IS SOFT
REMEDIAL MEASURE
1. SPLICE THE PILES
SOFT STRATA
CAUSE
1. PRESENCE OF OBSTRUCTION
STEEL CASING
POSSIBLE REMIDIAL MEASURE
GROUND LINE
1. PROPER USED OF DRILLING TOOLS (CHISSEL,
AUGE, GRAB & BUCKET)
OBSTRUCTION
CAUSES
1. PRESENCE OF COLLAPSIBLE MATERIALS
SUCH AS LOOSE SOIL AND COHESSIONLESS KELLY BAR
MATERIALS
2. APPROPRIATE PROPERTIES OF STABILIZING
MUD WAS NOT USED GROUND LINE
3. HEAD PRESSURE OF STABILIZING MUD WAS
NOT MAINTAINED DURING DRILLING STEEL CASING
REMEDIAL MEASURE
DRILLING BUCKET
1. EXTEND THE DEPTH OF PERMANENT STEEL
CASING
CAUSE
1. DEFORMATION OF THE TIP OF THE
KELLY BAR
PERMANENT STEEL CASING
2. LARGE VOLUME OF CAVE-IN MATERIALS OVER
THE DRILLING BUCKET GROUND LINE
STEEL CASING
REMEDIAL MEASURE
1. UNDERWATER CUTING OF STEEL CASING
2. REMOVAL OF CAVE-IN MATERIALS
3. ADJUST THE POSITION OF PILE
DRILLING BUCKET
REMEDIAL MEASURES
GROUND LINE
1. REMOVAL & REINSTALLATION OF STEEL
CASING STEEL CASING
2. USE APPROPRIATE DRILLING TOOLS
DRILLING BUCKET
HARD STRATA
CAUSE
1. DEFECTIVE OR OVERSTRESSED KELLY BAR
REMEDIAL MEASURE
GROUND LINE
1. OFFSETTING THE POSITION OF PILES
2. RETRIEVE THE CUT PORTION USING DIVERS STEEL CASING
DRILLING BUCKET
4. OCCURRENCE OF CAVE-IN
STEEL CASING
REPLACEMENT OF REBARS
2. RESHAPING OF BOREHOLE
3. REMOVAL OF CAVE-IN MATERIALS
CAUSES
1. WEAK/ABSENCE OF STIFINING RING SUPPORT
2. INSUFFICIENT WELDING AND TIE WIRE AT
GROUND LINE
SPLICE SECTION
STEEL CASING
REMEDIAL MEASURE
1. REMOVAL AND REPLACEMENT
CAGE BAR
CAUSES
1. HEAD PRESSURE OF STABILIZING MUD NOT
GROUND LINE
MAINTAINED DURING POURING
2. STRONG EARTH VIBRATION CAUSE BY EARTH
TREMOR AND MOVEMENTS OF HEAVY STEEL CASING
CONCRETE
1. OCCURENCE OF CAVE-IN
IV. COMMON PROBLEMS IN BRIDGE CONSTRUCTION
N. Discontinuity of Concrete
CAUSE
1. BREAKDOWN OF BATCHING PLANT GROUND LINE
POURING
CAGE BAR
2. DISCONTINUITY OF CONCRETE
IV. COMMON PROBLEMS IN BRIDGE CONSTRUCTION
O. Clogging of Tremie Pipes
CAUSES
1. CONSISTENCY OF CONCRETE NOT PROPERLY
MONITORED
2. RATE OF DISCHARGE OF CONCRETE IS VERY
FAST
3. PRESENCE OF WATER INSIDE THE TREMIE
PIPES
4. OVERSIZED AGGREGATES
REMEDIAL MEASURE
1. REMOVAL AND REINSTALLATION OF TREMIE
PIPES
IV. COMMON PROBLEMS IN BRIDGE CONSTRUCTION
P. Pile Integrity shows Discontinuity or Dirty Concrete
CAUSE
1. PRESENCE OF SEDIMENTS DUE TO ABSENCE
OR INSUFFICIENT CLEANING OF BOREHOLE
2. CAVING OCCURS DURING CONCRETE
POURING
3. POURING INTERUPTIONS
CAUSE
1. PRESENCE OF SEDIMENTS AT THE BASE OF
PILE DUE TO ABSENCE OR INSUFFICIENT
CLEANING OF BOREHOLE
2. LOW SOIL BEARING CAPACITY (FAILURE TO
CONDUCT SPT TEST PRIOR TO POURING OF
CONCRETE)
• Bridges serve as a
primary means of linking
and bringing people
together from various
parts of the country.
Hence, Bridge means
Friendship.