CADANGAN PEMBANGUNAN 1 TINGKAT GALERI JUALAN TERMASUK GALERIA PAMERAN DAN KAFETERIA (BANGUNAN SEMENTARA) DI ATAS LOT PT 54383

DAN LOT PT 54384, JALAN TUN MOHD FUAD 3, TAMAN TUN DR ISMAIL, KUALA LUMPUR
UNTUK TETUAN TTDI HARTA SDN BHD
ID Task Task Name Duration Start Finish Predecessors Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
Mode 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5
1 TTDI Zaaba Sales Gallery 153 days Tue 20/9/22 Sun 19/2/23
2 Mobilization 7 days Tue 20/9/22 Mon 26/9/22
3 Land Survey and Setting Out 7 days Tue 27/9/22 Mon 3/10/22 2
4 Temporary Works 14 days Tue 4/10/22 Mon 17/10/22 3
5 Wash Trough & Silt Trap 14 days Tue 4/10/22 Mon 17/10/22 4SS
6 Building Works 126 days Sat 8/10/22 Fri 10/2/23
7 WBLFF 30 days Sat 8/10/22 Sun 6/11/22 Handover date to ID for show
8 Pad Footing 10 days Sat 8/10/22 Mon 17/10/22 5FS-10 days WBLF: unit
9 Ground Beam 10 days Tue 18/10/22 Thu 27/10/22 8 pad footing, G. beam & slab shall
10 Ground Slab 10 days Fri 28/10/22 Sun 6/11/22 9 schedule in overlapping time
11 Frame 19 days Mon 7/11/22 Fri 25/11/22 frame
12 Column 10 days Mon 7/11/22 Wed 16/11/22 10
13 Mild Steel Post 14 days Sat 12/11/22 Fri 25/11/22 12FS-5 days
14 Roof 20 days Sat 26/11/22 Thu 15/12/22
15 Roof Truss 10 days Sat 26/11/22 Mon 5/12/22 12,13
16 Roof Finishes 10 days Tue 6/12/22 Thu 15/12/22 15
17 Gutter and RWDP 7 days Fri 9/12/22 Thu 15/12/22 16FF Brick wall commencement date
18 Wall and Partitions 38 days Sat 26/11/22 Mon 2/1/23 to consider early start
19 Brickworks 14 days Sat 26/11/22 Fri 9/12/22 13
20 Drywall 10 days Fri 16/12/22 Sun 25/12/22 16
21 Glazing Works 14 days Tue 20/12/22 Mon 2/1/23 19,23,24
Plastering works
22 Wall Finishes 61 days Wed 30/11/22 Sun 29/1/23 should be start first
23 Skim Coat 10 days Wed 30/11/22 Fri 9/12/22 19FF before skim coat
24 Plastering Works 10 days Sat 10/12/22 Mon 19/12/22 19
25 Painting Works 10 days Tue 20/12/22 Thu 29/12/22 24,23,19
26 Tiling Works 21 days Mon 9/1/23 Sun 29/1/23 34SS
Tiling work commencement too
27 Ceiling Works 21 days Mon 26/12/22 Sun 15/1/23
late.
28 Aluminium Strip Ceiling 14 days Fri 30/12/22 Thu 12/1/23 25 Water proofing may commence
29 Plasterboard 14 days Mon 26/12/22 Sun 8/1/23 20,19 after brickwall plastering/early
30 Painting Works 7 days Mon 9/1/23 Sun 15/1/23 29 commencement
31 Floor Finishes 41 days Tue 20/12/22 Sun 29/1/23
32 Waterproofing Works 10 days Tue 20/12/22 Thu 29/12/22 24
33 Screeding Works 10 days Fri 30/12/22 Sun 8/1/23 32
34 Tiling Works 21 days Mon 9/1/23 Sun 29/1/23 33 Installation work can be
35 Door and Windows 58 days Sat 10/12/22 Sun 5/2/23 start after completion of
36
wall plastering work. *can
Fabrication 21 days Sat 10/12/22 Fri 30/12/22 19
finish installation in earlier
37 Installation 7 days Mon 30/1/23 Sun 5/2/23 34,36
of Jan 2023.
38 Sanitary Fittings 7 days Mon 30/1/23 Sun 5/2/23 34
39 M&E Works 78 days Fri 25/11/22 Fri 10/2/23

Task Project Summary Manual Task Start-only Deadline


Prepared by: Sri Kim
Split Inactive Task Duration-only Finish-only Progress
Construction Sdn Bhd
Date: Thu 6/10/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
CADANGAN PEMBANGUNAN 1 TINGKAT GALERI JUALAN TERMASUK GALERIA PAMERAN DAN KAFETERIA (BANGUNAN SEMENTARA) DI ATAS LOT PT 54383 DAN LOT PT 54384, JALAN TUN MOHD FUAD 3, TAMAN TUN DR ISMAIL, KUALA LUMPUR
UNTUK TETUAN TTDI HARTA SDN BHD
ID Task Task Name Duration Start Finish Predecessors Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
Mode 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5
40 Cold Water and Sanitary Plumbing 45 days Sat 26/11/22 Mon 9/1/23 19SS
41 Electrical Works 70 days Sat 26/11/22 Fri 3/2/23 19SS
42 Telecommunication 70 days Sat 26/11/22 Fri 3/2/23 19SS
43 Fire Protection Works 45 days Sat 10/12/22 Mon 23/1/23 19
44 CCTV System 45 days Wed 21/12/22 Fri 3/2/23 41FF,42FF
45 Air-conditioning 60 days Tue 6/12/22 Fri 3/2/23 41FF
46 Pool piping and Filtration System 45 days Fri 25/11/22 Sun 8/1/23 57SS
47 Testing Commisionning 7 days Sat 4/2/23 Fri 10/2/23 40,41,42,43,44,45,46
May require early T&C in
48 External Works 121 days Tue 18/10/22 Wed 15/2/23 order to arrange authority
49 Sewerage Works 14 days Tue 18/10/22 Mon 31/10/22 8,4,5 CCC inspection
50 Bricksump 10 days Tue 1/11/22 Thu 10/11/22 49
51 Surface Water Drainage 14 days Fri 11/11/22 Thu 24/11/22 49,50
52 Curtain Wall 45 days Tue 20/12/22 Thu 2/2/23 24
53 Glazing Works 45 days Tue 20/12/22 Thu 2/2/23 24,21SS
54 Kerbs and Scupper Drain 7 days Sat 4/2/23 Fri 10/2/23 49,50,51,41,42
55 Road and Carparks 5 days Sat 11/2/23 Wed 15/2/23 54
56 Landscape 31 days Fri 25/11/22 Sun 25/12/22
57 Hardscape 21 days Fri 25/11/22 Thu 15/12/22 49,50,51
58 Softscape 10 days Fri 16/12/22 Sun 25/12/22 57
59 Snaglist & Final Cleaning 3 days Thu 16/2/23 Sat 18/2/23 17,21,26,30,37,38,47,52,53,55,58
60 Handover 1 day Sun 19/2/23 Sun 19/2/23 59

Genreal comments:
- To prepare physical & financial S-curve
- To provide PDI schedule
- To incorporate CCC schedule
- As it's 5 months contract, SriKim to compress the sequence of work accordingly.
- We anticipate to handover show unit area for ID on the 3rd month, which falls on 20/12/2022

Task Project Summary Manual Task Start-only Deadline


Prepared by: Sri Kim
Split Inactive Task Duration-only Finish-only Progress
Construction Sdn Bhd
Date: Thu 6/10/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2

You might also like