INSPECTION PROCEDURE MANUAL

MEASURING
PC8000-6-E
HYDRAULIC EXCAVATOR

PM_ 8000-6-D_#12048-49_rev0.DOC Page 1of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

PM-CLINIC SERVICE
General
In order to ensure a reliable and efficient performance of your KOMATSU
Excavator, the PM-CLINIC SERVICE should be carried out through
authorized KOMATSU Dealer every 1000 operating hours.

Customer’s Benefits Distributor’s Benefits


• Machine condition reports including • Uniform Methods of Gathering
recommendations Information
• Maintenance before major failure • Easy Analysis of Data to Show Trends
- Reduced cost • Reduction and Organisation of Field Data
- Reduced Down-Time • Systematic Analysis with Komatsu
- Maintain high machine availability Criteria
• Reports and graphs with trend analysis • Various reports and graphs

Items which have to be checked


The items which have to be checked during the PM-CLINIC SERVICE are
listed in the attached PM-CLINIC DATA SHEETS.
The measured values have to be entered into the column ”Actual Values” and
confirmed by marking S for satisfied or U for unsatisfied.

Handling of the PM-CLINIC DATA SHEETS


After all items have been checked, fill out the PM-CLINIC DATA SHEETS.
and send the original to our Service Department.
Komatsu Mining Germany GmbH
Department 8151
Buscherhofstraße 10
D - 40570 Düsseldorf
GERMANY
One copy should remain at the customer and one copy should be filed in the
dealer records.
The above field test reports provide the responsible departments with the
relevant information about the performance history of the machine.

Table of contents page


Part I: Instructions for Filling in the PM-CLINIC DATA SHEETS 1 to 12
Part II: PM-CLINIC DATA SHEETS 13 to 18

PM_ 8000-6-D_#12048-49_rev0.DOC Page 2of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

) • Fill in on each single sheet the Serial No and the Date of Inspection.

Item No of data sheet Sheet Action required


1. Hydraulic Oil 1 Mark the viscosity grade, manufacturer and
trade name of the actual filled in hydraulic oil.
If necessary contact the responsible
maintenance crew.
2. Attachment 1 Mark the installed type of attachment and the
size of boom, stick, and bucket. If necessary
check the machine record for detailed
information.
3. Shoe Width 1 Mark the installed size of track shoes. If
necessary measure the dimension or check the
machine record for detailed information.
4. Kind of Job 1 Mark the kind of job and add additional
information if necessary.
5. Kind of Soil 1 Mark the kind of soil and add additional
information if necessary.
6. Kind of Operation 1 Mark the kind of operation
7. Scheduled Working 1 Mark the scheduled working hours of the
Hours machine:
• Hours per shift and
• Shifts per day and
• Working days per week
8. Machine History 1 Read out the statistics and protocol memory
by using:
• a printer, (refer to the operation manual)
or
• by using a computer (refer to Service
Bulletin No 21-538)
Attach the print out, respectively a floppy
disk to the PM-CLINIC DATA SHEET

PM_ 8000-6-D_#12048-49_rev0.DOC Page 3of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


9. Operator’s Opinion 2 • Before starting the inspection, ask if the operator
detected any abnormality at the machine and fill
in this information if necessary.
• Fill in the current hydraulic oil temperature
during the test.
Normal operating temperature required,
if necessary warm it up.( refer to the operation
manual)
• Fill in the current ambient temperature during the
test.
• Fill in the approximate altitude.
all nominal values correspond at
)altitudes up to 1000 meter.
10. Work Equipment 2 Inspect visual the components for cracks and confirm
Crack Check the result by marking
• s = satisfied (no cracks found)
or
• u = unsatisfied (cracks found or assumed)
If cracks are found in the steel construction of
your Excavator, please inform our Service
Department as soon as possible. Attach suitable
information material (photos, catalogue drawings
etc.) showing the location and nature of the crack.
11. PTO Inspection 2 Inspect the pump distributor gear boxes (PTO’s) for
leaks and abnormal noise and confirm the result by
marking
• s = satisfied
or
• u = unsatisfied
If the result is unsatisfied, please attach suitable
information material (photos, catalogue drawings
etc.) showing the location and describe nature of
the abnormality.

PM_ 8000-6-D_#12048-49_rev0.DOC Page 4of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


12. Cycle Time Inspection 2
• Check throttle valve setting during initial test and write it down. Count the number of turns from
the bottom stop position.
• For all further test’s confirm that the initial setting was not changed.
• Use a stop watch to measure the cycle time.
• Start both motors.
• Select menu item “Power Check” according to operation manual.
• Carry out all tests with empty bucket.
• Rapidly move the control lever to the respective end position (start the stop watch) and hold it
until the final position of the movement is reached. (stop the stop watch).
• Watch the respective pressure and write down the minimum and maximum value.
• Fill in the measured time in the column actual value.
• Confirm the result by marking:
s = satisfied (within the tolerances) or u = unsatisfied (out-of-tolerance)
Boom
FSA BHA
• Stick cylinders completely extended • Stick cylinders completely retracted.
• Bucket parallel to the ground. • Bucket cylinders completely retracted.
• Lower the boom so, that the bucket is just • Lower the boom so, that the bucket is just
above the ground. above the ground..

2 2

1 1
1. Start Position Boom Raise or Stop Position Boom Lowering
2. Start Position Boom Lowering or Stop Position Boom Raise
Stick
FSA BHA
• Stick cylinders comp. extended. • Stick cylinders completely retracted.
• Lift the boom so, that the bucket is at • Lift the boom so, that the stick is at position
position 3 on the level of the slew ring. 3 vertical.
• Bucket parallel to the ground. • Bucket cylinders completely retracted.

4
4

3 3
3. Start Position Stick Extending or Stop Position Stick Retracting
4. Start Position Stick Retracting or Stop Position Stick Extending

PM_ 8000-6-D_#12048-49_rev0.DOC Page 5of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


12. Cycle Time Inspection 2
Bucket
FSA BHA
A) • Stick cylinders comp. retracted
• Boom cylinder completely extended • Bucket cylinders comp. retracted.
• Sick and Bucket cylinder completely • Lift the boom so, that the bucket is in
retracted. eye level.

B) 6
• Extend the stick cylinder until the
mechanical stop position is obtained.

5. Start Position curl or Stop Position dump


6. Start Position dump or Stop Position Curl

PM_ 8000-6-D_#12048-49_rev0.DOC Page 6of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


12. Cycle Time Inspection 2
Clam (opening and closing)
• Back wall in vertical position.

7. Start Position Clam Open or 8. Stop Position Clam Open or


Stop Position Clam Close. Start Position Clam Close.

Clam (Close):
• Back wall in horizontal position.

10
9

9. Start Position Clam Close 10. Position Clam Close

PM_ 8000-6-D_#12048-49_rev0.DOC Page 7of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


12. Cycle Time Inspection 3
Swing LH and RH Sprocket LH and RH

• Position of work equipment: Max. reach • Raise one track off the ground,
• Measure time taken to swing for 5 turns, • Let it spin one revolution, then measure
after swinging one turn as an approach the time required for it to spin 5
swing. revolutions.
• Repeat this procedure for the other track.

Swing brake
13. Swing brake 3 • Start both motors.
performance test • Move equipment to the position as described
below:
• Move the control lever to the respective end
position (L.H. or R.H.) and swing one turn as an
approach swing. Return the control lever rapidly
in neutral position and estimate the angle until the
swing motion stops comp..
• One time without using the foot brake and
secondly by using it.
• Fill in the values in the column actual value.
• Confirm the results by marking
•s = satisfied (within the tolerances) or
u = unsatisfied (out-of-tolerance)
Brake angle
• Position of work equipment: Max. reach

PM_ 8000-6-D_#12048-49_rev0.DOC Page 8of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


14. Power Check 3
• If the machine is cool, warm it up completely.

) Make sure that the cooler fans are


running with max. speed.

• Start both motors


• Select menu item “Power Check” according to
operation manual.
• Read the following values from the Text-
Display .
Alternatively connect suitable pressure gauges
to check points M5-1 and M5-2 for X1-1,X1-2
pressure and M11.1, M11.2, M11.3, M11.4 for
the main pump pressure (p1 – p8).

• Motor Current:
- Cooler fans running with max. speed

- Pedals and lever in neutral position


- Make sure that the main pumps in Qmax , (carry
out one function only for a short time to
eliminate the pause time control).
- Read the Motor current from the Text-Display

• Supply Tension:
- Read the tension from the analog gauge.

• X1-1, X1-2 Pressure:


- Make sure the change over valves (253.1 and
254.1) are in position E (electronic pump
regulation).
- Read the X1-1 and X1-2 pressure.
- Fill in the actual values

• Confirm the results by marking


s = satisfied or
u = unsatisfied

PM_ 8000-6-D_#12048-49_rev0.DOC Page 9of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


14. Power Check 4 • If the machine is cool, warm it up completely.

) running
Make sure that the cooler fans are
with max. speed.

• Make sure the change over valves (253.1 and


254.1) are in position E (electronic pump
regulation).
• Read the following values from the text-display
on the Power Check page.
Alternative connect suitable pressure gauges to
the check point
Alternatively connect suitable pressure gauges
to check points M5-1 and M5-2 for X1-1,X1-2
pressure and M11.1, M11.2, M11.3, M11.4 for
the main pump pressure (p1 – p8).
1. Peak value:
• Start both motors.
• Create max. pressure to all pumps with the
function “bucket curl” in final position.
(all pumps engaged).
• Adjust the Main Relieve Valves (MRV) of
control block I, II, III and IV to the peak value
pressure (nominal value e.g. 172 bar).
• Read the X1-1, X1-2 pressure and the motor
current Imot1, Imot2 (display designation: M1 and
M2).
• Write down the actual values.

2. Regulation and pressure cut off check:


• With the same condition as Item 1. Peak value
increase the MRV’s in steps to 280 bar, 290 bar,
300 bar and finally to the nominal setting.
• At each step read the X1-1, X1-2 pressure and
the motor current.
• Write down the actual values.

• Confirm the result by marking


s = satisfied or
u = unsatisfied

PM_ 8000-6-D_#12048-49_rev0.DOC Page 10of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


15. Operating pressure 5 • If the machine is cool, warm it up completely.
Make sure that the cooler fans are
) running with max. speed.
• Start both motors
• Select menu item “Power Check” according to
operation manual.
• Read the following values from the Text-
Display .
Alternatively connect suitable pressure gauges
to check points M11.1, M11.2, M11.3 and
M11.4 for the main pump pressure p1 – p8
(control block I, II, III and IV).

Boom, Stick, Bucket and Clam function.


• Extent respectively retract the cylinders of the
selected function completely and hold the
control unit in end position.
• Read the respective pressure.
• Fill in the actual values.
• Confirm the result by marking:
s = satisfied or u = unsatisfied

16. Pilot pressure 5 • Select the analog X2-pressure page in menu


item “Analog input” according to operation
manual.
• Start only one motor. Do the test separately for
both motors.
• Read the “X2-pressure” at the display.
Alternatively Connect a suitable pressure
gauges ( 0 to 60 bar) to test point M1.2.
• Fill in the actual value.

• Confirm the results by marking:


s = satisfied (within the tolerances) or
u = unsatisfied (out-of-tolerance)

PM_ 8000-6-D_#12048-49_rev0.DOC Page 11of 18 27.03.06


INSTRUCTIONS FOR FILLING IN PC8000-6
THE PM-CLINIC DATA SHEETS Electro

Item No of data sheet Sheet Action required


17. Back Pressure Valve 5 • If the machine is cool, warm it up completely.
• Connect a suitable pressure gauges
( e.g. 0 to 25bar) to test point M15.
• Start both motors.
• Make sure that the main pumps are in Qmax
(eliminate pause time control).
• Read the “Back-pressure” at the pressure gauge.
• Fill in the actual value.
• Confirm the results by marking:
s = satisfied (within the tolerances) or
u = unsatisfied (out-of-tolerance)

18. Undercarriage 5 • Move R.H. track group backward respectively


forward, until the contact area sprocket tooth (0)
and the track-pad lug (0) is in the illustrated
position and make a photo.
• Repeat the procedure on the L.H. track group.
• Make a visual inspection at the whole
undercarriage and confirm the results by marking:
s = satisfied (within the tolerances) or
u = unsatisfied (out-of-tolerance)
Travel forward Travel backward

PM_ 8000-6-D_#12048-49_rev0.DOC Page 12of 18 27.03.06


PM-CLINIC DATA SHEET 1 SERVICE 8151
PC8000-6-E 2nd Edition 03/2006

Customer Name Location Serial No.

Work Order No. Date of Inspection Inspected By

Engine / Motor model Engine / Motor No Service meter

1. Hydraulic Oil:
VG22 ó VG32 ó VG46 ó VG68 ó VG100 ó Other ......... ó
Manufacturer: Trade name:
2. Attachment:
FSA1) BHA2)
Boom Stick Bucket
FSA FSA FSA
8150 mm ó 5750 mm ó 40.0 m3 ó
mm ó mm ó m3 ó
BHA BHA BHA
mm ó mm ó m3 ó
mm ó mm ó m3 ó
3.Shoe Width
1500 mm ó
1900 mm ó
4. Kind of Job
Mining ó Other: ó
Quarry ó
Aquadigger ó

5. Kind of Soil
Rock: Overburden:
Soft ó Clay ó Other ó =
Medium ó Sand ó
Hard ó Soil ó
6. Kind of Operation

7. Scheduled Working Hour


Hours / shift Shifts / day Days / week
8 ó 11 ó 1ó 5ó
9 ó 12 ó 2ó 6ó
10 ó Other................. 3ó 7ó
8. Machine History
Retrieve: PROTOCOL and STATISTICS MEMORY (ETM / ECS)
Floppy disk attached ó
Print out attached ó

1) 2)
FSA = Front Shovel Attachment BHA = Back Hoe Attachment

PM_ 8000-6-D_#12048-49_rev0.DOC Page 13of 18 27.03.06


PM-CLINIC DATA SHEET 2 SERVICE 8151
PC8000-6-E 2nd Edition 03/2006

PC8000, Electric Drive Serial No. ................. Date of inspection:....................

9. Operator’s Opinion
Before starting, Any abnormality? Current hydraulic oil Temp.: Current Ambient Temp.
T: .............. °C T: ....................°C

Altitude: ..........meters

10. Work Equipment Crack Check


Boom: S* ó U** ó Bucket: S* ó U** ó Revolving frame: S* ó U** ó
Stick: S* ó U** ó Carbody S* ó U** ó Track frame: S* ó U** ó Other:.......................

11. PTO Inspection


PTO 1 S* U**
Leaks:
Abnormal noise
PTO 2
Leaks:
Abnormal noise

12. Cycle Time Inspection


Throttle FSA1) BHA2)
Motor 1 & 2 Motor 1 & 2
valve
Movements Rev. Unit Nominal Actual Nominal Actual S* U**
Boom : sec
Raise Pos. 1 → 2
bar
sec
Lowering Pos. 2 →1
bar
Stick : sec
Extending Pos. 3 → 4
bar
sec
Retracting Pos. 4 → 3
bar
Bucket: sec
Curl Pos. 5 → 6
bar
sec
Dump Pos. 6 → 5
bar
Clam: sec
Open Pos. 7 → 8
bar
sec
Close Pos. 8 → 7
bar
sec
Close Pos. 9 → 10
bar

1)
FSA = Front Shovel Attachment
2)
BHA = Back Hoe Attachment
* S = satisfied ** U = unsatisfied ⇒ corrective action necessary
PM_ 8000-6-D_#12048-49_rev0.DOC Page 14of 18 27.03.06
PM-CLINIC DATA SHEET 3 SERVICE 8151
PC8000-6-E 2nd Edition 03/2006

PC8000, Electric Drive Serial No. ................. Date of inspection:....................

12. Cycle Time Inspection


Item Condition Unit Nominal value Actual value S* U*
*
R.H. Swing: sec
5 turns Both motors running
(start counting after 1 bar
full turn)
L.H. Swing: sec
5 turns Both motors running
(start counting after 1 bar
full turn)
R.H. Sprocket : sec
5 turns Both motors running
(start counting after 1 bar
full turn)
L.H. Sprocket: sec
5 turns Both motors running
(start counting after 1 bar
full turn)

13. Swing brake performance test


Item Condition Unit Nominal value Actual value S* U*
*
Swing RH Joystick in neutral without °∠ °∠= 70±10°
Brake angle foot brake
(start counting after 1 full turn)

Swing RH Joystick in neutral & °∠ °∠= 25±10°


Brake angle activated foot brake
(start counting after 1 full turn)

Swing LH Joystick in neutral without °∠ °∠= 70±10°


Brake angle foot brake
(start counting after 1 full turn)

Swing LH Joystick in neutral & °∠ °∠= 25±10°


Brake angle activated foot brake
(start counting after 1 full turn)

14. Power Check


Item Condition Unit Nominal value Actual value S* U**
Current Motor 1 Without load
cooler fan max. RPM A I1 = I1 = ................
Current Motor 2 Without load &
cooler fan max. RPM A I2 = I2 = ................
Supply tension Without load V U = 6300 U = ................
Frequency Hz ƒ = 50 ƒ =.................
X1-1 pressure bar pX1-1 = 34±0,5 p X1-1 =.............
X1-2 pressure bar pX1-2 = 34±0,5 p X1-2 =.............

* S = satisfied ** U = unsatisfied ⇒ corrective action necessary

PM_ 8000-6-D_#12048-49_rev0.DOC Page 15of 18 27.03.06


PM-CLINIC DATA SHEET 4 SERVICE 8151
PC8000-6-E 2nd Edition 03/2006

PC8000, Electric Drive Serial No. ................. Date of inspection:....................


14. Power Check
Item Condition Unit Nominal value Actual value S* U**
Set MRV’s to 172 bar. bar p1/5 = p1/5 =........
(Control block I, II, III bar p2/6 = p2/6 =........
and IV)
Both motors running bar p3/7 = p3/7 =........
Peak value
Stall motors by using only bar p4/8 = p4/8 =........
the bucket filling function A I mot1 = Imot1 =........
fill in the other values at
this moment. A I mot2 = Imot2 =........
bar pX1-1 = 34±0,5 pX1-1 =........
bar pX1-2 = 34±0,5 pX1-2 =........
1. Set MRV’s to 280 bar. bar p1/5 = p1/5 =........
(Control block I, II, III bar p2/6 = p2/6 =........
and IV)
Both motors running bar p3/7 = p3/7 =........
Stall motors by using only bar p4/8 = p4/8 =........
the bucket filling function A I mot1 = Imot1 =........
fill in the other values at
this moment. A I mot2 = Imot2 =........
bar pX1-1 = pX1-1 =........
bar pX1-2 = pX1-2 =........
2. Set MRV’s to 290 bar. bar p1/5 = p1/5 =........
(Control block I, II, III bar p2/6 = p2/6 =........
and IV)
Both motors running bar p3/7 = p3/7 =........
Stall motors by using only bar p4/8 = p4/8 =........
Electronic the bucket filling function
pump A I mot1 = Imot1 =........
fill in the other values at
regulation and this moment. A I mot2 = Imot2 =........
pressure cut bar pX1-1 = 34±0,5 pX1-1 =........
off
bar pX1-2 = 34±0,5 pX1-2 =........
3. Set MRV’s to 300 bar. bar p1/5 = p1/5 =........
(Control block I, II, III bar p2/6 = p2/6 =........
and IV)
Both motors running bar p3/7 = p3/7 =........
Stall motors by using only bar p4/8 = p4/8 =........
the bucket filling function A I mot1 = Imot1 =........
fill in the other values at
this moment. A I mot2 = Imot2 =........
bar pX1-1 = pX1-1 =........
bar pX1-2 = pX1-2 =........
4. Set MRV’s back to bar p1/5 = p1/5 =........
nominal setting bar p2/6 = p2/6 =........
(310-315 bar).
(Control block I, II, III bar p3/7 = p3/7 =........
and IV) bar p4/8 = p4/8 =........
Both motors running A I mot1 = Imot1 =........
Stall motors by using only
the bucket filling function A I mot2 = Imot2 =........
fill in the other values at bar pX1-1 = 34±0,5 pX1-1 =........
this moment.
bar pX1-2 = 34±0,5 pX1-2 =........
* S = satisfied ** U = unsatisfied ⇒ corrective action necessary

PM_ 8000-6-D_#12048-49_rev0.DOC Page 16of 18 27.03.06


PM-CLINIC DATA SHEET 5 SERVICE 8151
PC8000-6-E 2nd Edition 03/2006

PC8000, Electric Drive Serial No. ................. Date of inspection:....................

15. Operating pressure


Item Condition Unit Nominal value Actual value S* U**
Boom raise bar 310 - 315
Floating system
deactivated ***
down bar 310 - 315
Stick out bar 310 - 315
Floating system
deactivated ***
in bar 310 - 315
Bucket curl bar 310 - 315
dump bar 310 - 315
Clam open bar 310 - 315
close bar 150 - 200
*** “floating” button at the respective lever activated

16. Pilot pressure


Item Condition Unit Nominal Motor 1 Motor 2 S* U**
value Actual Actual
value value
X2-pressure bar 45 - 48
Motor 1 only
X2-pressure bar 45 - 48
Motor 2 only

17. Back Pressure Valve


Item Condition Unit Nominal value Actual value S* U**
Back-pressure bar 10± 0,5
Motor 1 & Motor 2

18. Undercarriage
Travel forward Travel backward S* U**
Sprocket R.H. Please attach Photos

Travel forward Travel backward


Sprocket L.H. Please attach Photos

Track pads Visual inspection


R.H. crawler
Track pads Visual inspection
L.H. crawler
Rollers Visual inspection
R.H. crawler
Rollers Visual inspection
L.H. crawler

* S = satisfied ** U = unsatisfied ⇒ corrective action necessary


PM_ 8000-6-D_#12048-49_rev0.DOC Page 17of 18 27.03.06
PM-CLINIC DATA SHEET 6 SERVICE 8151
PC8000-6-E 2nd Edition 03/2006

PC8000, Electric Drive Serial No. ................. Date of inspection:....................

19. Remarks:

Date: Dealer: Signature and Stamp:

Date: Customer: Signature:

PM_ 8000-6-D_#12048-49_rev0.DOC Page 18of 18 27.03.06