Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Contents lists available at ScienceDirect

Sustainable Energy Technologies and Assessments


journal homepage: www.elsevier.com/locate/seta

Feasibility study of the small scale LNG plant infrastructure for gas supply in T
north of Iran (Case Study)

Laleh Shirazia, Mehran Sarmada, , Roholah Moghadasi Rostamib, Peyman Moeina,
Marziyeh Zarec, Khashayar Mohammadbeigya
a
Gas Research Division, Research Institute of Petroleum Industry (RIPI), Tehran 14665-1998, Iran
b
Islamic Azad University, Central Tehran Branch, Iran
c
Research & Technology Directorate of National Iranian Gas Company, Iran

A R T I C LE I N FO A B S T R A C T

Keywords: More than 85% of urban and 40% of rural areas of Iran are connected to the national gas pipeline network. For
LNG remaining areas of Iran, this method of gas transportation is not possible due to the great distance to the gas
Small scale transmission lines, low population and mountainous areas. In order to reduce energy transportation cost, it is
Feasibility study possible to use other methods such as CNG and LNG. For the first time, use of LNG for the purpose of gas supply
Gas supply
to about 43,000 households in the north of Iran has been considered. In this paper, a techno-economical study
Case study
has been carried out. The scope of study includes natural gas liquefaction plant, LNG storage tanks, LNG trucks
and re-gasification stations. Choosing the proper capacity, cost estimation and calculation of operating fees for
the implementation of this study is done. The calculations show that the cost of investing is 124 million Euros,
(61 million Euros for refrigeration-liquefaction unit and 63 million Euros for the rest). The case study will be
implemented as B.O.T. and the fee paid to investor per cubic meter of gas delivered to local gas networks is 14
cent Euro/m3 for 20 years plant operation and 13% IRR.

Introduction remote industrial plants, small power plants and compressed natural
gas stations.
Currently, by development of gas distribution network in Iran, more CNG has some disadvantages including low safety (due to high
than 90 percent of Iran’s population has been covered by natural gas as pressure of transferred gas near to 250 barg), high number of CNG
the main source of energy supply. More than 85 percent of the urban trucks on the road (in case of high consumption of the gas at the des-
and 40 percent of the rural areas of Iran are connected to the national tination) and the impossibility of gas storage for several days’ con-
gas pipeline network [1]. Many of the remaining areas have scattered sumption. Therefore, the use of this method is not recommended in
and low population, mountainous location or impassable regions and conditions where road blocking due to natural disasters such as heavy
gas supply by pipelines is not acceptable technically and economically. snowfall. Also, this method is not practicable for large distances be-
In such situation, the National Iranian Gas Company (NIGC) is planning tween mother-to-daughter station and high gas consumption, due to
suitable alternatives for the pipeline by providing new gas supply so- need for high number of CNG trucks.
lutions such as Compressed Natural Gas (CNG) and Liquefied Natural In LNG method, by constructing a natural gas liquefaction plant
Gas (LNG). along with the main gas transmission line, natural gas is cooled down to
At present, gas supply to the cities and villages of Iran except for a temperature of −162 °C at atmospheric pressure and became liquid
few cases which is supplied by mother and daughter’s compressed (600-fold volume reduction) and stored in LNG storage tanks. The
natural gas (CNG), has been carried out by pipelines. By looking at the produced LNG by using LNG trucks (similar to oil products) is sent to
new methods of gas supply in other countries known as “Virtual regasification stations at consumption areas (one or more destinations).
Pipelines”, mother and daughter compressed natural gas and small In regasification stations, the stored LNG is vaporized and after me-
scale liquefied natural gas (Mini LNG), can replace with pipelines in tering, the natural gas is injected to the urban-rural (local) gas dis-
special circumstances and by protecting the environmental, and reduce tribution network [2]. In this way, the gas transmission pipeline is re-
gas supply costs. These methods also can be used for gas supply to placed with LNG trucks moving between the liquefaction plant and the


Corresponding author.
E-mail address: sarmadm@ripi.ir (M. Sarmad).

https://doi.org/10.1016/j.seta.2019.07.010
Received 16 March 2019; Received in revised form 13 July 2019; Accepted 13 July 2019
2213-1388/ © 2019 Elsevier Ltd. All rights reserved.
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

regasification station(s). Qyyum et al. [29] investigated the effect of replacing the JT valve with
The initial investment cost of LNG method is high. So, it can only be hydraulic turbine (HT) in the energy efficiency enhancement of a single
used in cases where using the gas pipeline is not possible due to reasons mixed refrigerant (SMR) process. They showed the proposed HT based
such as excessive consumption points to gas transmission lines, gas liquefaction technology can be extended to other natural gas liquefac-
supply for mountainous areas and crossing the gas pipeline from pro- tion processes as an attractive option for enhancing the energy effi-
tected areas and environmental degradation (similar to this case study). ciency. He et al. [30] presented a comprehensive optimization and
This feature can ensure gas supply even in the cold months of the year comparison to show quantitative results on modified mixed refrigerant
(peak consumption) without any problem because of the possibility of liquefaction process (MSMR) and parallel nitrogen expansion lique-
LNG storage [3]. faction process (PNEC) from the perspectives of specific energy con-
This method (LNG) is used in Belgium, France, Spain, Portugal and sumption, exergy efficiency, techno-economy and operational flex-
Turkey [4]. In China and United States, it is currently used to gas supply ibility. The comparison results showed that MSMR had a lower specific
to distant areas, to provide fuel for compressed natural gas and lique- energy consumption, higher exergy efficiency, lower total investment,
fied natural gas stations, peak shaving of gas consumption, gas supply and higher flexibility than PNEC. In conclusion, MSMR is a better
for industrial and power plants, fuel for heavy vehicles and other ap- choice for small-scale mobile LNG plant from the four perspectives.
plications (Naslund [5]; Maynitskiy [6]; Biscardini et al., [7], World Also, the multiplicity of public and infrastructure projects in de-
Gas Conference [8]). For example, in Norway, the liquefied natural gas veloping countries causes financial constraints and timing of project
produced by the Snurrevarden plant, with a capacity of 60 tons per day, implementation. In recent decades, in order to overcome liquidity
is transported by tankers to consumption destinations [5]. In China, shortages and make better use of the private sector, project implement
there are currently about 200 small-scale LNG plants [9], which pro- methods with title of Public-private partnership have become common
duced LNG used for fuel of heavy vehicles [10] and gas supply. China practice.
has the largest market for small-scale LNG plants. The difference in the The general characteristics of these contracts are:
price of gas and diesel, as well as the government's rule to reduce air
pollution, has been caused development of this industry in China [11]. • Long-term contracts are concluded between the public sector and
In the United States, at least 14 small-scale LNG production plants have the private sector
been built to produce fuel of vehicles [12]. Other applications of small- • These contracts are designed by the private sector for the design,
scale LNG plants are the use of LNG fuel in rail and sea transportation construction, financing, commissioning and operation of buildings
which is implemented in Argentina, Canada, China and European and facilities.
countries. For example, Galileo's company in Argentina, by producing • Payments are made to the private sector during the project life time.
85 tons per day of liquefied natural gas, is responsible for providing fuel
for high-speed passenger ships. Also, Canada is developing 3 Passenger Public-private partnership is not solely for the purpose of project
ships with Dual LNG/Diesel motors [13]. Among the projects that have financing and the use of other private sector capacities, such as
been seriously addressed in the National Iranian Gas Company in recent knowledge and expertise, management skills, incentives for optimal use
years, is gas supply to the impassable regions (about 43,000 house- of resources, is also the goal of creating such contracts.
holds) in the north of Iran and for 4 main zones by LNG method. So, a By considering the new approach of the NIGC in order to use the
detailed techno-economic study should be done focusing on the cost private sector's investment potential, use of this contract model, which
estimation to evaluate this method. In literatures, there are several is known as the Build, Operate & Transfer (BOT) is considered for this
feasibility studies on LNG projects in different countries [14–20]. Raj case study.
et al. [21] did a techno-economic assessment of LNG production in In this contractual method, in order to compensate the investment
western Canada. Javanmardi et al. [22] presented a feasibility of and operation costs of the project by the private sector and to provide
transporting LNG from South-Pars gas fields in Iran to potential mar- the necessary profit, the calculated charge for a reasonable rate of re-
kets. Tan et al. [23] proposed a small-scale liquefaction process to li- turn is paid by the National Iranian Gas Company (NIGC). In this way,
quefy a part of natural gas in the pressure-reduction station. They de- natural gas is available to the private sector at the liquefaction plant.
termined the optimal design conditions for the proposed system. He and The private sector after gas liquefaction, storage, transfer, regasification
Ju [24] presented a novel process for small-scale pipeline natural gas and injection into the distribution gas network, the fee for these ser-
liquefaction. They adopted the thermodynamic analysis and optimized vices is received per cubic meter of delivered gas to the network from
the process to approach the maximum liquefaction rate. He and Ju [25] NIGC.
proposed four configuration strategies of expansion liquefaction cycle This investigation presents a techno-economical study of the small
for distributed-scale LNG plant, namely multistage expanders, single scale LNG plant as well as a wide transportation, distribution and re-
precooling cycle, regeneration and mixture working fluid. They con- gasification network of produced LNG for the first time in Iran. In this
figured sixteen feasible liquefaction cycles based on the configuration paper, a complete overview of the technical and economic aspects has
strategies and then optimized by genetic algorithm to maximum FOM been studied as a case study. The case study was considered in a region
(figure of merit) for optimal synthesis. Nguyen et al. [26] investigated at the north of Iran.
three configurations suitable for small-scale applications because of
their simplicity and compactness: the single-mixed refrigerant, single
and dual reverse Brayton cycles. They identified the most promising Case study description
cycle layouts by performing multi-objective optimization procedures.
Ancona et al. [27] proposed two different LNG production layouts and The feed gas for small scale LNG plant is supplied from the national
investigated within a thermodynamic analysis: a Joule-Thompson LNG Iranian gas pipeline network by pressure near to 33 barg and 37,000
expansion process and a new layout with a turbo-expander. They normal cubic meter per hour gas flow rate. This is a lean and sweet gas
showed that the new proposed solution allow to optimize the LNG (with total sulfur less than 20 ppmv) but for LNG production we need
production process and to minimize the process energy consumption. post treatment because the mole percent of CO2 is more than 1%. Also a
Chen et al. [28] established skid-mounted Coal-bed methane (CBM) low amount of heavy hydrocarbons must be separated during the li-
liquefaction processes based on Claude cycle. Cryogenic turbo-expander quefaction process to prevent freezing problem in LNG heat exchangers.
with high expansion ratio was employed to improve the efficiency of The LNG plant is located in Noor city and beside the Caspian Sea. The
CBM liquefaction process. The process optimization was performed and plant schematic is shown in Fig. 1.
optimum operation range of the liquefaction processes was obtained.

221
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Fig. 1. Plant Schematic.

Amine and adsorption units A: Gas liquefaction Plant:

The Amine and Adsorption units include one train with 50% and • Receiving, filtration and gas measurement facility
110% turn down and over design ratios respectively. For LNG pro- • Amine unit with amine solvent to remove carbon dioxide.
duction it is needed to reduce CO2 content less than 50 ppmv and H2O • Adsorption unit including dehydration and mercury removal (to less
3
less than 1 ppmv. For this reason, the formulated amine than 10 Nano gram/Nm )
(MDEA + activators) and 3A absorber has been used. A schematic • Refrigeration and liquefaction unit
diagram for Amine & Adsorption unit is shown in Fig. 2. • LNG Storage and loading facilities
• Utilities
Refrigeration and liquefaction unit
B: Road distribution network; including LNG trucks for LNG dis-
The single mixed refrigerant liquefaction process has been used for tribution to main consumption centers
gas liquefying. This liquefaction process is used in many small scale C: Regasification units:
LNG plants in the world. The refrigeration and liquefaction unit in-
cludes 2 parallel trains with similar capacity for LNG production flex- • Temporary LNG storage tanks for 3–5 days backup
ibility during the plant operation in a year. A schematic diagram for • LNG Vaporizer
Refrigeration and liquefaction unit is shown in Fig. 3. • Odorizer and gas measurement system
LNG storage and loading facilities This case study is divided to 4 zones for gas supply. It should be
noted that the number of regasification units in this case study was 23,
For LNG storage in this study, double wall cryogenic storage tanks with distribution as follows for each zone:
(inner wall is 9% nickel stainless steel and external wall is carbon steel
and between two walls is filled with vacuum perlite) are used. The LNG • Zone 1: 8 Regasification units
storage volume is considered for 7 days of plant production, which will • Zone 2: 6 Regasification units
be 10,000 m3. A schematic diagram for LNG Storage and loading fa- • Zone 3: 8 Regasification units
cilities is shown in Fig. 4. • Zone 4: 1 Regasification unit
LNG trucks The total number of end users (households) in the mentioned areas
is 42,880, which its distribution is given in Table 1.
Similar to LNG storage tanks, double wall cryogenic vessels with
20 m3 nominal capacity is considered for LNG transportation to re- Analysis of the case study technical aspects
gasification units. Near to 70 LNG trucks is required for LNG trans-
portation for the peak gas consumption. Determine the liquefaction plant proper capacity

Regasification units Due to high investment cost of natural gas liquefaction plants in Iran
and other countries, the selection of optimal capacity according to
Due to extreme cold weather in gas consumer areas (less than 15 °C consumption patterns is one of the most important steps in conceptual
in winter), the indirect LNG vaporizer (hot Water & Glycol system) is design and feasibility studies. In baseload LNG plants which designed
recommended instead of using ambient air vaporizer for LNG re- and constructed for the purpose of gas export, LNG production rate is
gasification. In order to ensure the continuous supply of gas, a tem- constant over the year, independent of changes in weather conditions.
porary LNG storage tank is considered in the re-regasification units. A But in the present case study, which aims to gas supply to the moun-
schematic diagram for Regasification units is shown in Fig. 5. tainous and impassable regions and the main consumers are the
households, the rate of gas consumption is different throughout the
The scope of feasibility study year and its amount is dependent to the weather condition and popu-
lation living in these areas. Table 2 presents the estimated gas con-
The scope of feasibility study includes techno-economical studies as sumption for the intended area.
the following categorization: Estimation of hourly peak for gas consumption is commonly used in

222
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Fig. 2. Schematic Diagram of (a) Amine Unit (b) Adsorption Unit.

223
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Fig. 3. Schematic Diagram of Refrigeration and liquefaction Unit.

the design of gas networks. But when we use LNG technology for gas (617 tons per day). Accordingly, at first glance, the design and con-
supply, due to the possibility of LNG storage for some days, the use of a struction of a LNG plant with a capacity of 600 tons per day can be used
daily peak is appropriate. If the plant is designed based on the hourly for this study. But, the required LNG capacity in the summer is less than
peak, the capacity of the plant and the investment cost have been in- 50% of the nominal capacity of the plant (∼20%), and technically it is
creased sharply and the bulk of this capacity will not be utilized not possible to reduce the production capacity to this amount.
throughout the year. In Fig. 6, the gas consumption pattern (one year) is Therefore, the design of two parallel production trains with a capacity
presented based on daily peak. of 300 tons per day (capable of increasing capacity (over design) by
In Table 3, the required LNG capacity is shown based on the daily 10% and reducing capacity (turn down) to 50%) would be a proposed
peak at each month of the year. solution for this project. In this case, the LNG production profile will be
As seen, the lowest consumption is for July and August (123 tons per in accordance with Table 4.
day) and the highest consumption is for January and February As shown in Table 4, in fact, during 6 months of the year, one train

Fig. 4. Schematic Diagram of LNG Storage and loading facilities.

224
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Fig. 5. Schematic Diagram of Regasification units.

Table 1 liquefaction plant, equivalent to 7 days of plant production, which will


Areas for gas supply and No. of household. be 10,000 m3.
Area No. of household
Regasification units’ capacity determination
Zone 1 12,412
Zone 2 12,513
Zone 3 15,090 Regasification units must be designed for hourly peak of gas con-
Zone 4 2865 sumption. Therefore, the capacity of LNG vaporizer should be con-
Total 42,880 sidered equal to the hourly peak specified for gas consumption at each
of the 23 regasification units. The capacity range of the LNG vaporizers
is estimated between 500 and 5500 m3 per hour due to the gas con-
Table 2 sumption of each regasification unit. In order to ensure the continuous
Estimated gas consumption for gas supply to the intended area. supply of gas, a temporary LNG storage tank is considered between 3
and 5 days in the re-regasification units. The number of storage days
Month Hourly peak (m3) Daily peak (m3)
has been optimized based on site visits and the status of road access.
April 36,019 576,307 Table 5 shows the regasification units capacity and recommended LNG
May 20,528 329,318 storage tanks.
June 12,864 205,824
July 10,291 164,659
August 10,291 164,659 Capacity and No. of LNG trucks
September 14,408 230,523
October 18,010 288,154
LNG trucks are used to transport LNG from liquefaction plant to
November 36,019 576,307
December 46,310 740,966 consumption areas. Permissible capacity for LNG trailers depends on
January 51,456 823,296 access road conditions. With regard to road transport restrictions, the
February 51,456 823,296 nominal capacity of the LNG trailers is considered to be maximum
March 41,165 658,637
20 m3. Due to the time of loading and unloading of each trailer, path
length, the duration of the working per day and the average speed of
the trailer, the number of required LNG trucks for the peak consump-
(300 tons per day) is withdrawn from the production cycle and in the
tion is estimated to 70, which is the share of each area is as follows:
summer, the same one operating unit will reach less than 50% of pro-
duction capacity; In order to prevent technical problems in the gas li-
quefaction unit, it is possible to make overall maintenance of the plant • Zone 1: 22 LNG trucks
and temporary shutdown of the production in the months of July and • Zone 2: 20 LNG trucks
August. • Zone 3: 23 LNG trucks
• Zone 4: 5 LNG trucks
Selecting the right capacity for LNG storage tank in liquefaction plant Obviously, the number of LNG trucks for summer is much lower
than required LNG trucks for peak consumption.
Due to the necessity for continuous gas supply to the 42,880
households, it is necessary to take the appropriate predictions in order Cost estimation
to prevent interrupt in gas supply. For this purpose, and by considering
the LNG storage capability, the storage volume is considered in the In order to accurately estimate the investment cost in the feasibility

225
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Fig. 6. Gas consumption pattern (one year) based on daily peak.

Table 3 Table 5
Estimated required LNG capacity in different months of the year. Regasification units’ capacity and recommended LNG storage tanks.
Month LNG capacity (tons per day) Regasification Capacity LNG Storage Capacity Regasification Zone/No.
(Nm3/h) (m3)
April 432
May 247 Zone 1
June 154 1600 210 1
July 123 1960 260 2
August 123 1930 260 3
September 173 2200 180 4
October 216 2090 170 5
November 432 3630 480 6
December 556 540 70 7
January 617 960 80 8
February 617
Zone 2
March 494
690 90 1
1630 130 2
3400 270 3
Table 4 1800 140 4
LNG plant Production profile (one year) with 2 parallel LNG production trains 5410 430 5
equal to 300 tons per day for each one. 2080 170 6

Zone 3
Month The required LNG (tons proposed LNG production capacity
2350 190 1
per day) (tons per day)
3430 460 2
April 432 2 × 300 (Reduce production: ∼70%) 1180 90 3
May 247 1 × 300 (Reduce production: ∼80%) 1400 110 4
June 154 1 × 300 (Reduce production: ∼50%) 4130 330 5
July 123 1 × 300 (Reduce production: ∼40%) 3760 300 6
August 123 1 × 300 (Reduce production: ∼40%) 880 120 7
September 173 1 × 300 (Reduce production: ∼60%) 980 130 8
October 216 1 × 300 (Reduce production: ∼70%) Zone 4
November 432 2 × 300 (Reduce production: ∼70%) 3440 460 1
December 556 2 × 300 (Reduce production: ∼90%)
January 617 2 × 300 (Reduce production: ∼3%)
February 617 2 × 300 (Reduce production: ∼3%)
March 494 2 × 300 (Reduce production: ∼80%)
In this paper the cost estimation was performed by combination of
the following methods.
The capital cost of a plant or process unit can be related to capacity
study, the following actions were done: by the following equation.
n

• Simulation and optimization of process units


S
C2 = C1 ⎛ 2 ⎞
⎜ ⎟

• Provide list and size of the main equipment ⎝ S1 ⎠ (1)

• Price inquiry and cost estimation of the main equipment or packages where C1 and C2 are capital costs of the plant with capacity S1 and S2 ,
• Estimation of engineering costs, equipment supply and construction respectively. The exponent n is typically about 0.6 Averaged across the
(EPC cost) for different parts of the plant (process units, LNG sto- whole chemical industry [31]. The capital cost per unit of production of
rage, loading and utilities), LNG trucks and regasification units se- product could be expressed by economy of scale as follow:
parately.
C2
= aS2n − 1
S2 (2)

226
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Table 6 Table 10
Amine unit main equipment list and price. LNG storage and loading facilities main equipment list and price.
No. Equipment Item Investment cost (million Euros)

1 Amine absorber column Gas Receiving and treatment unit 9


2 Amine regenerator column Refrigeration and liquefaction unit 61
3 Treated gas K.O. Drum LNG storage and loading unit 14
4 Rich amine flash Drum Regasification units 21
5 Amine sump Drum Utilities 8
6 Reflux Drum LNG trucks 11
7 Amine HP pump
Total 124
8 Reflux pump
9 Amine sump pump
10 Precoat filtration pump
11 Amine/amine exchanger Couper et al. [32] are collected the prices of classes of the most
12 Regenerator reboiler frequently used equipment in the form of correlating equations. The
13 Lean Amine Air cooler prices are given in terms of appropriate key characteristics of the
14 Regenerator condenser
15 Filtration Package
equipment, such as sqft, gpm, lb/h, etc. Factors for materials of con-
16 Antifoam Package struction and performance characteristics other than the basic ones also
are provided.
Equipment Cost = 1,667,000 Euro
In the cost estimation of a plant it is always necessary to get a real
price quotation from an equipment vendor. In addition to the above
Table 7 correlations in this paper cost of the some equipment was estimated by
Adsorption unit main equipment list and price. inquiry from vendors. Price inquiry was performed for process packages
such as amine anti-foam, amine filtration and other packages.
No. Equipment

1 Absorption columns Cost estimation of Inlet facility and Amine unit


2 Mercury removal column
3 Pre-cooling heat exchanger
4 Gas K.O. Drum For cost estimation of Amine unit, following the process simulation,
5 Regeneration gas air cooler the list of main equipment was determined according to Table 6. The
6 Regeneration gas heat exchanger main equipment cost was 1.67 million Euros and the EPC cost was 4.4
7 Regeneration gas separator
million Euros with conversion factor 2.63 in order to convert the main
8 Filters & Strainers
equipment cost to EPC (Engineering, procurement & construction) cost.
Equipment Cost = 1,500,000 Euro The EPC cost of inlet facility (metering & filtration) was estimated
0.4 million Euros given the experiences of similar projects.
Table 8
Refrigeration and liquefaction unit main equipment list and Cost estimation of adsorption unit
price.
No. Equipment
The main equipment list of Adsorption unit is shown in Table 7. The
main equipment cost was 1.5 million Euros and the EPC cost was 4.2
1 Cold Box million Euros with conversion factor 2.80.
2 Compressor package
3 End flash drum
4 Refrigerant separator Cost estimation of Refrigeration and Liquefaction unit
Equipment Cost = 22,593,000 Euro
The main equipment list of Refrigeration and liquefaction unit is
shown in Table 8. The main equipment cost was 22.6 million Euros and
Table 9 the EPC cost was 61.0 million Euros with conversion factor 2.70.
LNG storage and loading facilities main equipment list and
price.
Cost estimation of LNG storage and loading facilities
No. Equipment
The main equipment list of LNG storage and loading facilities is
1 LNG storage tanks
2 Refrigerant make-up tanks
shown in Table 9. The main equipment cost was 6.36 million Euros and
3 Refrigerant vaporizers the EPC cost was 14.0 million Euros with conversion factor 2.2.
4 Cryogenic pumps
5 Loading facilities
Cost estimation of LNG trucks
Equipment Cost = 6,364,000 Euro

It is considered 157,000 Euros for each LNG truck. For this study,
the total cost for 70 LNG trucks will be 11 million Euros.
Towler and Sinnott [31] listed values of the parameters a and n for
some fuels and commodity chemical processes. The another correlation
for preliminary cost estimation of equipment is shown in Eq. (3). Cost estimation of regasification units
Ce = a + bS n (3)
In this case study there are 23 regasification units. Each re-
where Ce is purchased equipment cost on a U.S. Gulf Coast basis. a and b gasification unit has a small LNG storage tank, LNG vaporizer and
are cost constants. S is the size parameter and n is an exponent for that metering system. The main equipment cost for this 23 units was 10.82
type of equipment. These parameters are listed for various types of million Euros and the EPC cost was 21.0 million Euros with conversion
equipment in a range of capacity by Towler and Sinnott [31]. factor 1.94.

227
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Fig. 7. Investment cost distribution.

Table 11
Assumptions for economic calculations.
Item Assumption value

LNG plant capacity 600 tons per day


Total investment cost 124 million Euros
Annual operating costs 4.48 million Euros per year
Discount Rate 5.56% per year
Long-term inflation rate for Euro 1.5%
Construction period 3 years
Operational period 20 years
Gas Consumption* 169 million cubic meters per
year
Accepted Internal Rate of Return with private 13%
sector

* According to the estimates made by NIGC.

Table 12 Fig. 8. Sensitivity analysis of IRR with investment cost changes.


Results of economic calculations.
Item Value Table 14
Sensitivity analysis of IRR with annual operating cost changes.
Fee paid to the investor per cubic meter of gas delivered to local gas 14
networks (cent Euro/m3) Item Changes percent
Total revenue (million Euros) 550
Dynamic payback (year) 6.3 Operating cost +15% +10% +5% 0% −5% −10% −15%
Net Present Value (million Euros) 87.5 changes
Internal Rate of 12.43 12.61 12.79 12.96 13.14 13.31 13.49
Return (%)

Table 13
Sensitivity analysis of IRR with investment cost changes.
Item Changes percent

Investment cost +15% +10% +5% 0% −5% −10% −15%


changes
Internal Rate of 10.99 11.60 12.26 12.96 13.72 14.55 15.45
Return (%)

Total capital investment cost

According to the above calculations, the total investment cost was


estimated 124 million Euros, which the breakdown of the costs is shown
in Table 10 and Fig. 7.
As can be seen, the major investment cost is for the refrigeration &
liquefaction unit. Subsequently, LNG regasification (23 points) and LNG
storage units (in the liquefaction plant) have the largest share.
Fig. 9. Sensitivity analysis of IRR with annual operating cost changes.

228
L. Shirazi, et al. Sustainable Energy Technologies and Assessments 35 (2019) 220–229

Economic evaluation References

In order to economic evaluation, the assumptions which are shown [1] Performance report of provincial gas companies. National Iranian Gas Company;
July 2018.
in Table 11 have been used. The annual operating costs are including
[2] He T, Karimi IA, Ju Y. Review on the design and optimization of natural gas li-
human resources, repair and maintenance, utilities and etc. The dis- quefaction processes for onshore and offshore applications. Chem Eng Res Des
count rate was estimated by considering the choice of the Euro as a 2018;132:89–114. https://doi.org/10.1016/j.cherd.2018.01.002.
[3] Pfoser S, Schauer O, Costa Y. Acceptance of LNG as an alternative fuel: determinants
monetary unit and the interest rate of the long-term deposits of this and policy implications. Energy Policy 2018;120:259–67. https://doi.org/10.1016/
currency and the long-term inflation rate at the time of preparing the j.enpol.2018.05.046.
paper. The Comfar III software was applied to economic evaluating. The [4] Best Practice Policy Guidance for Liquefied Natural Gas (LNG). Case study: small
scale LNG – truck loading. United Nations economic commission for Europe; 2017.
construction duration, duration of the plant operation, discount rate, p. 14.
investment cost and operating cost which was calculated in previous [5] Naslund M. LNG status in Denmark (Technology and Potential). Danish gas tech-
nology center 2012.
sections, was entered to software as input data. To calculate the fee paid [6] Maynitskiy I. The evolution of small scale LNG markets (The view from Gazprom
to the investor, the annual income was entered to software in the form export). Istanbul, Turkey: Small scale LNG Forum; 2012. p. 6.
of guess and error to calculate the required IRR (13%) which mentioned [7] Biscardini G, Schmill R, Del Maestro A. Why small-scale LNG may be the next big
wave. PWC 2017:11.
in Table 11. Then the final calculated income divided to total gas flow [8] International Gas Union. 27th World Gas Conference, World LNG Report, 2018;
(169 million cubic meters per year) and the fee paid to the investor was Edition, 63.
calculated 14 cent Euro/m3. The results of the economic calculations [9] Wensheng L. Small LNG: China Experiences, LNG Conference, 10–11 May 2017;
Naples, Italy, p. 21.
based on BOT projects are presented in Table 12. [10] Verbeek R, Nesterova N, Beemt B van den, Widdershoven C, Spreen J. Global po-
The result show that the payback period is near to 6 years with 87.5 tential of small-scale LNG distribution September 2014;TNO Report, 15.
[11] International Gas Union, World Gas Conference, LNG as Fuel Report, 93. June 2015.
million Euros net present value and the 13% internal rate of return [12] International Gas Union, World Gas Conference, Small Scale LNG Report, 20. June
which has been adjusted for economic calculations. Also, total revenue 2015.
is calculated to 550 million Euros. [13] World Bank Group, Mini/Micro LNG for commercialization of small volumes of
associated gas, 64. October 2015.
[14] Adibi SA, Bakhtiari HR. Investigation of possibility of LNG production and export in
Iran. In: 12th Oil, Gas & Petrochemical Congress 2003; Tehran, Iran.
Sensitivity analysis [15] Peters L, Hussain A, Follmann M, Melin T, Hägg MB. CO2 removal from natural gas
by employing amine absorption and membrane technology, a technical and eco-
nomical analysis. Chem Eng J 2011;172(2–3):952–60. https://doi.org/10.1016/j.
Sensitivity analysis of investment cost cej.2011.07.007.
[16] Raj R, Ghandehariun S, Kumar A, Geng J, Linwei M. A techno-economic study of
shipping LNG to the Asia-Pacific from Western Canada by LNG carrier. J Nat Gas Sci
According to the studies, the sensitivity of internal rate of returns to Eng 2016;34:979–92. https://doi.org/10.1016/j.jngse.2016.07.024.
investment cost changes is significant so that with an increase of 15% in [17] Pellegrini LA, Langè S, Baccanelli M, De Guido G. Techno-Economic Analysis of
investment cost, the internal returns decrease to 11% (Table 13 & LNG Production Using Cryogenic Vs Conventional Techniques for Natural Gas
Purification, Offshore Mediterranean Conference and Exhibition. 25–27 March
Fig. 8). 2015; Ravenna, Italy.
[18] Ge J, Wang X. Techno-economic study of LNG diesel power (dual fuel) ship. WMU J
Maritime Affairs 2016;16(2). https://doi.org/10.1007/s13437-016-0120-x.
[19] Vyas N. A techno-economic study of liquefied natural gas transportation: a pro-
Sensitivity analysis of annual operating cost spective to develop India’s first import terminal Master of Science dissertation
India: World Maritime University; 2000.
The internal rate of returns to annual operating cost changes are not [20] Lee SH, Seo YK, Chang DJ. Techno-economic analysis of acid gas removal and li-
quefaction for pressurized LNG. IOP Conf Ser: Mater Sci Eng 2018;358. https://doi.
very sensitive, so that with an increase of 15% in operating costs, the org/10.1088/1757-899X/358/1/012066.
internal returns decrease to 12.4% (Table 14 & Fig. 9). [21] Raj R, Suman R, Ghandehariun S, Kumar A, Tiwari MK. A techno-economic as-
sessment of the liquefied natural gas (LNG) production facilities in Western Canada.
Sustainable Energy Technol Assess 2016;18:140–52. https://doi.org/10.1016/j.
seta.2016.10.005.
Conclusion [22] Javanmardi J, Nasrifar KH, Najibi SH, Moshfeghian M. Feasibility of transporting
LNG from South-Pars gas field to potential markets. Appl Therm Eng
2006;26:1812–9. https://doi.org/10.1016/j.applthermaleng.2006.02.003.
In this case study, the technical and economic aspects of gas supply [23] Tan H, Zhao Q, Zheng J, Shan S. Design and optimization of an improved small-
to some 43,000 households in the impassable regions in north of Iran scale liquefaction process for the natural gas pressure-reducing station in Pipelines.
have been studied. For this purpose, due to the predicted gas con- J Pipeline Syst Eng Pract 2017;8(4). https://doi.org/10.1061/(ASCE)PS.1949-
1204.0000271. 104017011.
sumption pattern for these areas, first, the suitable capacity of natural [24] He TB, Ju YL. A novel process for small-scale pipeline natural gas liquefaction. Appl
gas liquefaction plant is determined equal to 600 tons per day. After Energy 2014;115:17–24. https://doi.org/10.1016/j.apenergy.2013.11.016.
[25] He T, Ju Y. Optimal synthesis of expansion liquefaction cycle for distributed-scale
that, the number of required LNG trucks and the capacity of re- LNG (liquefied natural gas) plant. Energy 2015;88:268–80. https://doi.org/10.
gasification units were determined based on the amount of their gas 1016/j.energy.2015.05.046.
need. The primary design and estimation of the investment costs shows [26] Nguyen T-V, Rothuizen ED, Markussen WB, Elmegaard B. Thermodynamic com-
parison of three small-scale gas liquefaction systems. Appl Therm Eng
that an investment near to 124 million Euros is required for the im- 2018;128:712–24. https://doi.org/10.1016/j.applthermaleng.2017.09.055.
plementation of this study. [27] Ancona M, Bianchi M, Branchini L, De Pascale A, Melino F. Performance increase of
According to the method of case study implementation in the form a small-scale liquefied natural gas production process by means of turbo-expander.
Energy Procedia 2017;105:4859–65. https://doi.org/10.1016/j.egypro.2017.03.
of investment (BOT), the calculated paid salary to the investor is esti- 963.
mated at 14 cents Euro per each cubic meter of gas injected to dis- [28] Chen S, Niu L, Zeng Q, Li X, Lou F, Chen L, et al. Thermodynamic analysis on of
skid-mounted coal-bed methane liquefaction device using cryogenic turbo-ex-
tribution gas networks. In the sensitivity analysis section, the results pander. IOP Conf Ser: Mater Sci Eng: IOP Publishing 2017;278. https://doi.org/10.
also show that the Internal Rate of Return with a 15% increase in in- 1088/1757-899X/278/1/012027.
vestment cost, decreases by about 2%. Therefore, accurate estimation of [29] Qyyum MA, Ali W, Long NVD, Khan MS, Lee M. Energy efficiency enhancement of a
single mixed refrigerant LNG process using a novel hydraulic turbine. Energy
the investment cost is crucial for NIGC and private sector. This im- 2018;144:968–76. https://doi.org/10.1016/j.energy.2017.12.084.
portance is less sensitive to estimating annual operating costs. [30] He T, Liu Z, Ju Y, Parvez AM. A comprehensive optimization and comparison of
modified single mixed refrigerant and parallel nitrogen expansion liquefaction
process for small-scale mobile LNG plant. Energy 2019;167:1–12. https://doi.org/
10.1016/j.energy.2018.10.169.
Acknowledgments [31] Towler G, Sinnott R. Chemical engineering design, principles, practice and eco-
nomics of plant and process design. Amsterdam: Elsevier Inc.; 2008.
[32] Couper JR, Penney WR, Fair JR, Walas SM. Costs of individual equipment. In:
We would like to thank the National Iranian Gas Company’s re- Couper JR, Penney WR, Fair JR, Walas SM, editors. Chemical process equipment.
search and technology management support for carrying out this study. Boston: Butterworth-Heinemann; 2012. p. 731–41.

229

You might also like