Professional Documents
Culture Documents
Design Problem of Weir
Design Problem of Weir
Design a glacis weir for the following data obtained at the site.
Solution
Hence
n = no of end contractions
= Q / (L – K n H)
= 1.7 H 3/2
H = 3.78 m
= crest level + H
Where q and f are Maximum discharge intensity on weir crest and Lacey’s silt factor
respectively.
Regime velocity V
q 12.5
V=( )=( ) = 1.6m/s
R 7.53
Velocity head h
v2 1.62
h=( )=( ) = 0.14m
2g 2 ∗ 9.81
U/S HFL
Afflux
= 226.14 – 225
D/S TEL
HL at high flood
Summary of Calculations
Step (3) when the weir is discharging with pond level (u/s), then
= 224 – 221.50
= 2.50 m
= 214.85 m
= 224.5 – 2 (7.53)
Provide an intermediate pile at d/s toe of the glacis as the second line of defense with its
bottom at the same level of 209.50 m
Profile of Glacis
On u/s side, no impervious floor is required. However a floor length 1.05 m may be,
provide on the u/s side. Total length of impervious floor
= 38 m