SITE SPECIFIC PLAN FOR PULL OFF/PULL OUT PMSB.MAR4.223
Vessel’s Information
Mooring Configuration
Vessel Location
(e.g. 8-point; with soft line; etc.)
ALYA D12DR-A PLATFORM 4 POINTS ANCHOR (HEADING NORTH EAST)
Key Personnel
Position Name
Master Capt Zainudin Bin Amat
Const. Supt.
CSR
OIM
The Master has the overriding authority and responsibility in relation to his ship to make decisions with respect to safety of
the Vessel, prevention of Human Injury or Loss of Life and the prevention of property damage and pollution. He may request
the Company’s assistance as necessary.
No Item Check
Approved Anchor Pattern stand-off position to be confirmed by actual pull off upon completion of
1
anchor deployment
Approved Anchor Pattern stand-off position to be confirmed by actual pull off during GPA Exercise
2 at least once a month and whenever there is new Master/ Chief Officer/Chief Engineer joining the
vessel, to be recorded in the Logbook.
1. If the radar gives indication of impending squalls approaching the area of operations
Maximum Time Limit for Vessel to be ready:30 minutes (Must inform POB and Marine Crew for standby)
Once ANY conditions (1A) above are met, the following actions shall be taken immediately:
Maximum Time Limit for Vessel to be ready: 30 minutes (Must inform POB and Marine Crew for standby)
PETRA MARINE SDN BHD FORM / CHECKLIST
Document Number:
SITE SPECIFIC PLAN FOR PULL OFF/PULL OUT PMSB.MAR4.223
Regardless of above environmental safety criteria, the Master MUST use his professional judgement in making decisions to pull off to
ensure the safety of vessel, people, pollution prevention and damage to client assets.
Once ANY conditions (1B) above are met, the following actions shall be taken immediately:
Inform related parties (i.e. construction supervisors, platform staff) to disconnect and clear all umbilical hoses/cables through
1.
the gangway.
Retreat vessel to Approved Anchor Pattern Stand-off position as per contingency plan (approximately 100 metres away from
2.
any part of the offshore installation)..
Mooring winches on standby and anchor wire drum brake released as vessel may need to be moved to the Approved Anchor
3.
Pattern stand-off position.
4. Ascertain propeller is well clear (in event where engine is to be used).
All down weather anchors should be slackened when necessary to allow vessel to move as free as possible to prevailing
5
weather direction with the engine thrust (main engines & bow thruster) as required to minimize effect of the adverse weather.
6 Continuously maintain radar watch, monitor all weather forecast, sea state and anchor wires tension
7 Advise Office & DPA.
Maximum Time Limit for Vessel to be ready: 30 minutes (Must inform POB and Marine Crew for standby)
PETRA MARINE SDN BHD FORM / CHECKLIST
Document Number:
SITE SPECIFIC PLAN FOR PULL OFF/PULL OUT PMSB.MAR4.223
(1C) VESSEL PULL-OUT [RELEASE ANCHOR WIRES] AND FOLLOW-UP ACTION – Any One Condition Met – STAGE 3
(Vessel Currently at “Stand Off” Position – Approximately 100M from Offshore Platform)
Should the weather deteriorate further and the anchor wire tension increase and any one of the below parameters is met,
Master will release the anchors immediately and proceed to shelter:
Shelter Position Bintulu Anchorage
3. Excessive motion of the vessel affecting crew safety and resulting inability to carry out work operations.
5. When Master believe that the vessel can be damaged by the weather conditions eg. sea water flooding on deck.
Irrespective, if the above parameter are not met, Master MUST release the anchor wires and move out when (i) the Bow
Thruster operation exceeded 1 hour and (ii) the main engines propulsion exceeding 45% in keeping / maintaining vessel in
position
Regardless of above environmental and safety criteria, the Master MUST use his professional judgement in making decisions
to pull off to ensure the safety of vessel, people, pollution prevention and damage to client assets.
Once ANY conditions (1C) above are met, the following actions shall be taken immediately:
3. Navigate vessel safely away from platform to allow anchor wire to slip off safely
4. Vessel steaming off offshore location or proceeds to shelter point as advised by CSR.
Ensure entries made in Deck (Chief Officer) Logbook. Make an official marine note of protest and entry into the Official
5.
Logbook at the earliest opportunity if Master believed that the vessel sustained damages due to the weather conditions.
PETRA MARINE SDN BHD FORM / CHECKLIST
Document Number:
SITE SPECIFIC PLAN FOR PULL OFF/PULL OUT PMSB.MAR4.223
2. Main Engines, Bow Thruster and Anchor Winches are to be started, with relevant crew manning their stations.
3. Emergency Fire Pump is to be started and ready to assist in fighting the fire
Marine Emergency Response Team (ERT) is to be on standby and ready to man their fire-fighting stations should assistance
4.
be required (Construction back-up ERT to platform standby at main deck as required assistance).
All umbilical hoses/cables are to be disconnected in the event the fire escalates beyond control and the vessel needs to
5. withdraw to her Approved Anchor Pattern Stand Off position (approximately 100 metres) from nearest part of offshore
installation).
2. Inform CSR/OIM the decision for the vessel to stand-by up-wind within the vicinity to render assistance, whenever needed.
4. Should assistance not required, proceed towards the agreed holding or shelter.
Should the vessel be withdrawn to a standing-by mode up-wind within the vicinity of the platform installation, Marine
5. Emergency Response Team is to man their “Man Overboard” stations to assist in any search and rescue operation, to
retrieve survivors from the offshore installation.
4. Start all anchor winches motor, pull off vessel to a safe distance up to maximum anchor wires spread.
3. Start all anchor winches motor, Main Engines and Bow Thruster
2. Main Engines, Bow Thruster and Anchor Winches are to be started, with relevant crew manning their stations.
3. All umbilical hoses/cables are to be disconnected between the vessel and the offshore installation
Master shall pull off the vessel to her designated stand-off position, or to the limits of the anchor spread, whichever is
4.
deemed appropriate as per (1B)
5. Inform CSR/OIM the decision for the vessel to stand-by up-wind within the vicinity to render assistance, whenever needed
6. Should the situation required for the vessel to pull out, Master shall initiate the pull out procedure as per section 1C above
8. Vessel shall seek shelter at agreed shelter point should her presence is no longer required at site and as advised by CSR.
(4) OPERATIONAL LIMITATION: ANCHOR WIRE TENSION & ANCHOR HOLDING POWER
Item Detail
Anchor wire type Galvanized Steel Wire
Anchor weight 5T
Breaking Load
Acknowledgement
Prepared By Reviewed & Approved By (PMSB Shore Representative)
Name Capt Zainudin bin Amat Name Ahmad Mustaqim Bin Che Ghani
Position Master Position Marine Manager
Date 26th September 2023 Date 26th September 2023
Note:
1. Master is solely responsible to amend this form as where and when required. The following shall be considered, but not
limited to;
a. Changes in weather condition – prevailing wind and/or swell,
b. Changes in anchor pattern, including soft mooring; and
c. Changes in site condition and/or limitation.
PETRA MARINE SDN BHD FORM / CHECKLIST
Document Number:
SITE SPECIFIC PLAN FOR PULL OFF/PULL OUT PMSB.MAR4.223
2. This form is to be prepared and completed during the tool box meeting upon vessel arrive location and prior to
commencement of anchor handling.
3. The following personnel to be present during this SSP form preparation;
a. Bridge Team;
b. Deck Personnel;
c. Construction Team Key Personnel; and
d. Client/End User Key Personnel.
4. The following procedures are to be referred to when preparing the site specific plan;
a. PMSB.MAR3.120 – Adverse Weather Guideline
b. PMSB.MAR3.200 – Emergency Departure (Pull Out & Pull Off)
5. Retention period: 2 years
Weather Guideline Station keeping (Pull-off / Pull-out) – Work vessels (Extract from PMSB.MAR3.120)