Name of work – CoNSTrUCTIoN of HeaD reGULaTor aT LkC km 19.100 for
PUraNI JHaro mINor. aBSTraCT of CoST
S.No. Description of Item UNIT QTY. RATE AMOUNT (Rs.)
1 Earth work excavation of foundation with all types
of soil, including all lead and lift, labours, T&P etc. Required and filling sides of the foundation Cum. 172.48 182.00 31390.87 trenches and disposal of surplus excavated earth as per direction of engineer-in-charge.
2 Providing & Laying C.C. 1:3:6 concrete with stone
ballast 25-50 mm size with corage sand i/c cost of Cum. 11.79 5983.47 70553.29 all material labour etc. Complete but excluding cost of cement. 3 Providing & Laying R.C.C. 1:1:2 concrete with stone ballast 4.75-10 mm size with corage sand i/c cost of Cum. 25.36 8428.54 213736.30 all material labour etc. Complete but excluding cost of cement. 4 Providing & laying R.R. Stone Masonary in 1:4 CM with cement, coarse sand and stone boulder including cost of all material, labour, T&P but Cum. 18.73 5275.60 98793.08 excluding cost of cement etc. Required for proper completion of work as per direction of Engineer-in- charge. 5 Providing & laying sand filter 100mm thik layer including cost of all material, labour, T&P but excluding cost of cement etc. Required for proper Cum. 0.25 1931.69 484.47 completion of work as per direction of Engineer-in- charge. 6 Providing & laying stone grit filter 100mm thik layer 4.75-20mm size including cost of all material, labour, T&P etc. Required for proper completion Cum. 0.25 2298.70 576.51 of work as per direction of Engineer-in-charge.
20-40mm size including cost of all material, labour, T&P etc. Required for proper completion of work Cum. 0.25 2565.20 643.35 as per direction of Engineer-in-charge.
8 Providing & laying hard stone boulder pitching up
to 20 kg including cost of all material, labour, T&P etc. Required for proper completion of work as per Cum. 2.93 2105.54 6160.80 direction of Engineer-in-charge.
9 Cutting bending , binding ,placing and
drilliing,grouting Steel for reinforcement with cost of binding wire & steel including cost of all MT 2.2310 71814.66 160218.51 materials,labour, T&P etc. required for Proper Completion of work. Total Rs. 582557.20 Add - 18% GST 104860.30 Total Rs. 687417.49 Say Rs. 6.87 Lacs.