KANHAR NAHAR PARIYOJNA KHAND-06 MIRZAPUR

Name of work – CoNSTrUCTIoN of HeaD reGULaTor aT LkC km 19.100 for


PUraNI JHaro mINor.
aBSTraCT of CoST

S.No. Description of Item UNIT QTY. RATE AMOUNT (Rs.)

1 Earth work excavation of foundation with all types


of soil, including all lead and lift, labours, T&P etc.
Required and filling sides of the foundation
Cum. 172.48 182.00 31390.87
trenches and disposal of surplus excavated earth as
per direction of engineer-in-charge.

2 Providing & Laying C.C. 1:3:6 concrete with stone


ballast 25-50 mm size with corage sand i/c cost of
Cum. 11.79 5983.47 70553.29
all material labour etc. Complete but excluding
cost of cement.
3 Providing & Laying R.C.C. 1:1:2 concrete with stone
ballast 4.75-10 mm size with corage sand i/c cost of
Cum. 25.36 8428.54 213736.30
all material labour etc. Complete but excluding
cost of cement.
4 Providing & laying R.R. Stone Masonary in 1:4 CM
with cement, coarse sand and stone boulder
including cost of all material, labour, T&P but
Cum. 18.73 5275.60 98793.08
excluding cost of cement etc. Required for proper
completion of work as per direction of Engineer-in-
charge.
5 Providing & laying sand filter 100mm thik layer
including cost of all material, labour, T&P but
excluding cost of cement etc. Required for proper Cum. 0.25 1931.69 484.47
completion of work as per direction of Engineer-in-
charge.
6 Providing & laying stone grit filter 100mm thik
layer 4.75-20mm size including cost of all material,
labour, T&P etc. Required for proper completion Cum. 0.25 2298.70 576.51
of work as per direction of Engineer-in-charge.

7 Providing & laying coarse filter 100mm thik layer


20-40mm size including cost of all material, labour,
T&P etc. Required for proper completion of work Cum. 0.25 2565.20 643.35
as per direction of Engineer-in-charge.

8 Providing & laying hard stone boulder pitching up


to 20 kg including cost of all material, labour, T&P
etc. Required for proper completion of work as per Cum. 2.93 2105.54 6160.80
direction of Engineer-in-charge.

9 Cutting bending , binding ,placing and


drilliing,grouting Steel for reinforcement with cost
of binding wire & steel including cost of all MT 2.2310 71814.66 160218.51
materials,labour, T&P etc. required for Proper
Completion of work.
Total Rs. 582557.20
Add - 18% GST 104860.30
Total Rs. 687417.49
Say Rs. 6.87 Lacs.

J.E. JE A.E