Qty Pipe Culvert

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

KANHAR NAHAR PARIYOJANA KHAND -6 MIRZAPUR

NAME OF WORK :- ESTIMATE FOR CONSTRUCTION OF PIPE CULVERT AT KM. 0.875 OF PURANI JHARO
MINOR
BILL OF QUANTITY
SL. NO. Description Length width Height Quantity Unit

1 Site Clearence for constructing stream including


all leads and lifts, labour charges, T& P etc.
required for proper completion of work and its
disposal as per direction of Engineer-in-charge.

1 x 1 16.00 10.00 160.00 sqm


TOTAL 160.00 sqm
2
Earth work in excavation of foundation in
all types of soil including all leads and lifts,
labour charges, T& P etc. required for
proper completion of work and its disposal
as per direction of Engineer-in-charge.
I) D/S & U/S 1 x 1 16.000 8.018 6.200 795.39 cum
Total 795.386 cum

3 Laying C.C. 1:2:4 (M–15) in raft with cement,


coarse sand of F.M. not less than 2.00 and hard
stone ballast as obtained from the excavation of
foundation including cost of all material, labour,
T&P etc. required for proper completion of
work.
Abutment foundation 2 x 1 3.470 4.200 0.300 8.744 cum
Abutment up to Top 2 x 1 (3.17+.30)/2 4.200 4.945 72.068 cum
Abutment straight portion 2 X 1 0.300 4.200 0.500 1.260 cum
Deduction of pipe encasing -2 x 1 1.740 1.090 1.090 -2.173 cum
Pipe encasing 1 x 1 1.090 19.380 1.090 23.025 cum
Deduction of pipe -1 x 1 3.14x0.60x0.60x19.38 -21.907 cum
Rcc piller guard at road level 2 x 3 0.75 0.20 0.15 0.135 cum
Total 81.153 cum
Total 81.153 cum

4 Centering & shuttering for C.C. work in


different parts of structure as below including
cost of all materials, labour, T&P etc. required
for proper completion of work.
Abutment D/S & U/S
pcc levelling base 2 x 2 3.47 0.30 4.16 sqm
Inclined face 1 x 2 5.72 4.20 48.05 sqm
vertical face 1 x 2 4.92 4.20 41.33 sqm
side face 2 x 2 (3.17+0.30)/2 4.92 34.14 sqm
2 x 2 0.30 0.50 0.60 sqm
Pipe encasing 2 x 1 19.38 1.09 42.25 sqm
Rcc piller guard above to GL 1 x 4 0.20 0.75 0.60 sqm
Total 171.13 sqm
5 Carriage, Cutting, Bending, Binding and placing
steel for reinforcement with cost of binding
wire including cost of all materials, labour, T&P
etc. required for proper completion of work.
Abutment D/S & U/S
Vertical face
vertical bar 10 mm dia 2 x 18 4.92 177.12 R.M
Transverse bar 10 mm dia 2 x 20 4.10 164.00 R.M
Inclined face
vertical bar 10 mm dia 2 x 18 5.72 205.92 R.M
Transverse bar 10 mm dia 2 x 20 4.10 164.00 R.M
Rcc piller guard 2 x 6 0.75 9.00 R.M
Total 720.04 R.M
total weight of 10 mm dia @0.618kg/m=720.04x0.618= 444.98 KG
Total 0.445 MT
6
Providing and fixing 600mm. Dia NP-2 Pipe
including cost of all materials, labours, T&P etc,
required for proper completion of work.

1 x 8 2.50 20.00 RM
Total 20.00 RM
7 Providing and fixing PVC Pipe 100mm in
drainage spout & weep hole including cost of all
materials, labours, T&P etc, required for proper
completion of work.
2 x 5 1.310 13.100 RM
Total 13.100 RM
8 Supplying and laying Local sand on Top of pipe
including cost of all materials, labour, T&P etc.
required for proper completion of work.

Below pipe 1 x 1 4.20 19.38 1.95 158.72 cum


above pipe encasing 1x 1 3.14 19.38 0.6 36.51 cum
Total 195.23 cum
9
Dewatering by 5 H.P. Diesel pump of foundation
including cost of dewatering equipment, and its
accessories, required material, labour etc.

300.00 Hours
Total 300.00 Hours

Providing /Arrangement of Supervisor for


super vision of site including cost of all
10
labour & T&P etc required for proper
completion of work.
1 x 60 60.00 day
Total 60.00 day
Providing /Arrangement of Beldar for super
vision and helping of supervisor including cost of
11
all labour & T&P etc required for proper
completion of work.
1 x 60 60.00 day
Total 60.00 day
Testing of material and cubes for quality control
12 purpose by third party including cost of carriage
fees etc.

1 x 1 1.00 Job
Total 1.00 Job

J.E AE

You might also like