Professional Documents
Culture Documents
Revised Progress Report
Revised Progress Report
Course details
Course code: ENG301
Course Title: Technical Writing
Section number:
Instructor name:
Group name:
Student details
[add names and emails]
Student declarations
I [add name] declare that I have equally contributed to this project to the best of my ability, and
if it is proved otherwise, I accept the deducted or failed grade.
[add digital signature]
Date
To
From
Subject
Purpose
A progress report on the site of the community centre building that is ongoing
Summary
This report is an update on the progress of the ongoing building project of a community centre
on Olaya Street Riyadh near Axiom Care Riyadh. The report provides the budget summary and
explains the site material problems experienced. This report is in line with the project manager’s
monthly update. On May 5th, our company landed a tender to build a community centre which
kicked off in September 2022. This progress report aims at giving an update on the current work
done. Also, it provides directions on the tasks planned to enhance the completion of the current
phase. The project faces the problem of a sharp increase in the cost of building materials.
Therefore, the tasks to be included to enhance the smooth running of the project include
modifying the current budget to allow for price increases, using prefabrication, and realigning
When the company was awarded the tender to build a community centre, the management
promised to develop the center within eight months rapidly. The community centre, which
comprises fifty units in nine buildings, is underway and progressing. However, the problem of
increasing the cost of building materials became evident, and the report aims to find feasible
solutions to the problem. A committee to resolve the problem conducted research and concluded
that the solutions involve modification of the current budget to allow for price increases, starting
using prefabrication, and realigning our team to optimize resource management by using
Problem
Although the project’s development had initially been going on smoothly, there is a
approved by the
significant problem facing the site. Having sent the budget and development
Mention tasks
funding, there is a sharp rise in the cost of building materials.
Results of research
challenges they face. Under normal conditions, Khodahemmati and Shahandashti (2020)
indicate that the power of a contractor to quantify the changes in the cost of building materials is
essential in decision-making and budgeting. However, in this case, the cost of materials was
higher than expected. Therefore, the rise will disrupt the ongoing construction processes due to
budget fluctuations.
What is causing the rise in building materials? According to Reuters, the Russian invasion of
Ukraine has disrupted the steel market due to the sanctions and logistics since Russia and
Ukraine combined account for a fifth of the steel market (Onstad, 2022). Bin Saddeeq et al.
(2019) observe that the shortage and delay in the construction materials lead to a cost overrun in
building materials. Hence, the current project is facing a significant blow in providing adequate
Several strategies can be implemented to ensure that the rise in costs does not impede the
development of Phase II of the project. Habibi and Kermanshachi (2018) believe that a project’s
procurement phase is essential for better cost performance if the contractors adopt appropriate
financial policies. Hence, all stakeholders should take an active role in curbing the problems of
productivity of the site are normal. The gutter installation is almost complete in all the units,
while the main entrance to the site is already graded with a stone base. Around the buildings,
grading is incomplete since the materials needed to perform fine grading increased costs; hence
most buildings have not been prepared for hardscaping and landscaping. The water, electricity,
and gas supplies have already been connected to the city’s supply, while the wet and dry utilities
The concrete foundations and slabs have been poured, and the windows and doors of most
houses have been installed. Roofing is completed in seven buildings and is scheduled to be
completed in the last two buildings by next week. Fire alarms and sprinklers have been installed
in all buildings. Mechanical plumbing and HVAC are also complete. The incomplete work
mostly involves the cabinets and countertops, finishing the floor and paint, and sheetrock.
Schedule Update
Progress Chart
100.0%
90.0%
80.0%
70.0%
60.0%
50.0%
40.0%
30.0%
20.0%
10.0%
0.0%
Sep-22 Oct-22 Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Apr-23
Conclusion
The ongoing construction of the community centre is going on smoothly. The current progress
is 17.7% complete of the project and is ahead of schedule. However, the recent rise in building
materials, especially steel, has thrown the project’s budget turmoil due to the inadequacy in price
fluctuations in the budget. Therefore, to enhance the stability of the project, the report
recommends modification of the current budget to allow for price increases, start using
prefabrication, and realign our team to optimize resource management by using software to track
materials.
Assistant 40 24 960
Contractor 40 30 1,200
Total 3,360
References
Bin Seddeeq, A., Assaf, S., Abdallah, A., & Hassanain, M. A. (2019). Time and cost overrun in
the Saudi Arabian oil and gas construction industry. Buildings, 9(2), 41.
https://www.mdpi.com/2075-5309/9/2/41
Habibi, M., & Kermanshachi, S. (2018). Phase-based analysis of key cost and schedule
https://www.emerald.com/insight/content/doi/10.1108/ECAM-10-2017-0219/full/html
https://doi.org/10.1061/(ASCE)NH.1527-6996.0000381
Onstad, E. (2022). European steel prices to extend rally as Ukraine conflict cuts supply. Reuters.
steel-prices-extend-rally-ukraine-conflict-cuts-supply-2022-03-25/