Advanced Work Packaging:

A Game Changer in Oil and


Gas Projects
ABDELGHANI SINNO
SR CONSTRUCTION CONSULTATION
Agenda

 Industry Challenges
 AWP Overview
 ConstructSim Solution Overview
 Benefits & Programmatic Approach
 Q&A
3 out of 4
mega-projects
(Oil & Gas) were
considered a
failure
due to cost or
schedule overrun.

IPA - 2015
Industry
Challenges
Typical Project Ecosystem

Utilities Spool Fabricator


Contractor
Sub 1

Module
Fabricat
Steel Fabricator or sub.

Civil
Sub 2 Contractor Engineerin Module
g sub. Fabricat
or sub.

EPCM
Module
Fabricat
or sub.

Module
Fabricator 2
Sub 1 MEI
Contractor
Equipment
Vendor Owner(s) Engineerin
g sub.

Sub 2
Engineerin

Module g sub.

Fabricator 1 Engineer (Feed)


A World of World

Courtesy
of
Fiatech
Advanced Work Packaging - AWP

 A construction best practice

 Aligns Engineering, Procurement and Construction

 Helps you define a project plan that best reflects construction’s


requirements, to provide greater safety, productivity and overall
effectiveness
AWP: A contractual requirement

“IWP’s shall be issued to Company


for Approval a minimum of thirty
(30) days prior to planned
associated Work execution at site.
2014: One of the early project with AWP

requirements – RHIP
AWP At bidding stage

“Bidder to provide examples of


current and previous AWP
implementations (Projects, Scope,
Number of IWP’s, number of WFP)

62 pages of AWP requirements/deliverables by contractors.
AWP Workflow

Execute IWP
through job
cards

Progress
IWP approved
collection /
by
reason
Client/Controls
Review Path of codes
construction

Set EWP & CWP Clear


boundaries constraints
IWP Closed

Link IWP’s
with check
items
Extract IWPs
ConstructSim provides a dynamic planning environment that
addresses the nature of Construction Collaboration issues

Owners Construction
Contractor
Managers
Contract Monitoring
Work Packs

Constraint analysis

Planning
& Tracking
Change CWP 4D
Orders s
Plan Simulatio
Verification
n
Data Centric Execution

Many
ot hers
Models & ISO Schedule Cost Plan Resources Mat erials Equipment ERP
IN

IN
IN
IN

IN

IN

IN

IN
Virtual Construction Model (VCM)
Bentley Construction Solution
Enabling

Engineering models Work package Status visualisation, Field based work Field based Dashboards &
& data management Look ahead planning progressing QA/QC reports
management

Change management
ConstructSim Components
Review packages in VR
Advanced Work Packaging
Proven Benefits

Productivity Cost Safety

+
$
25% 10% 30%
ConstructSim Project Benefits

• Improved constructability analysis, interactive planning and


coordination between engineering office and site office in using
Virtual Plant Model
• Visually plan optimal work crew packages (EWP, CWP, IWP, TWP)

• Streamline material, equipment & sequencing


• Reduce rework / out-of sequence work

• 20to|start-up by systems tracking


Speed time
• WWW.BENT
Automated task estimates / automate data entry

• LEY.COM
Reduce time looking for information via visual monitoring the status of
engineering, materials and construction execution progress