Professional Documents
Culture Documents
Olahdata - CSA FRACTINATION - REVISI - 16 APRIL 2024 - TRACKING - 12 Mei 2024
Olahdata - CSA FRACTINATION - REVISI - 16 APRIL 2024 - TRACKING - 12 Mei 2024
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Olahdata_CSA FRACTIN
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Sun 12/05/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 1
BAR CHART SCHEDULE
REFINERY PHASE 2 - FRACTIONATION
CSA PACKAGE
PT. BAKRIE FOOD & ENERGY
PT. MITRA PRATAMA MANDIRI JAYA PERKASA
ID Task WBS Task Name % Duration Start Finish
Mode Complete December January February March April May June
03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 03/03 10/03 17/03 24/03 31/03 07/04 14/04 21/04 28/04 05/05 12/05 19/05 26/05 02/06 09/06
55 1.3.3.1.2 PEKERJAAN PARIT DALAM BANGUNAN 85% 2 wks Mon 20/05/24 Fri 31/05/24
56 1.3.3.1.3 PEKERJAAN BUNWALL (H=12cm) 85% 2 wks Mon 20/05/24 Fri 31/05/24
57 1.3.3.2 PEKERJAAN PERBAIKAN LANTAI 2 PLANT (+10.30) 99% 156 days Mon 04/12/23 Tue 07/05/24
58 1.3.3.2.1 PEKERJAAN LANTAI TERMASUK MINI STOPPER DI DOWN 99% 156 days Mon 04/12/23 Tue 07/05/24
PIPE
59 1.3.3.2.1.1 GRANIT PLATINUM 60X60 (DOUBLE LOADING) 95% 5 wks Tue 02/04/24 Wed 01/05/24
60 1.3.3.2.1.2 DOWNSPOT KE OIL CATCHER 100% 1 wk Mon 04/12/23 Tue 07/05/24
61 1.3.3.2.1.3 TUTUP LUBANG AREA FILTER PRESS 100% 6 wks Tue 02/04/24 Tue 07/05/24
62 1.3.3.2.1.4 PEKERJAAN BUNDWALL (H=12CM) 100% 6 wks Tue 02/04/24 Tue 07/05/24
63 1.3.4 PENGGANTIAN LANTAI CS & PERBAIKAN ATAP REFINERY PLANT 100% 12 days Thu 11/04/24 Mon 22/04/24
64 1.3.4.1 LANTAI 3 (ELV. +14.30) PEKERJAAN PENGGANTIAN 100% 2 wks Thu 11/04/24 Mon 22/04/24
CHECKERED PLATE, T=4,5mm
65 1.3.4.2 LANTAI 3 (ELV. +16.20) PEKERJAAN PENGGANTIAN 100% 2 wks Thu 11/04/24 Mon 22/04/24
CHECKERED PLATE, T=4,5mm
66 1.3.4.3 LANTAI 4 (ELV. +18.30) PEKERJAAN PENGGANTIAN 100% 2 wks Thu 11/04/24 Mon 22/04/24
CHECKERED PLATE, T=4,5mm
67 1.3.4.4 LANTAI 5 (ELV. +21.80), PEKERJAAN PENGGANTIAN 100% 2 wks Thu 11/04/24 Mon 22/04/24
CHECKERED PLATE, T=4,5mm
68 1.3.4.5 LANTAI 6 (ELV. +26.30), PEKERJAAN PENGGANTIAN 100% 2 wks Thu 11/04/24 Mon 22/04/24
CHECKERED PLATE, T=4,5mm
69 1.3.4.6 LANTAI 7 (ELV. +30.30), PEKERJAAN PENGGANTIAN 100% 2 wks Thu 11/04/24 Mon 22/04/24
CHECKERED PLATE, T=4,5mm
70 1.3.5 PEKERJAAN CANOPY, LISPLANK & PENGGANTIAN RABUNG 100% 48 days Wed 03/01/24 Mon 19/02/24
ATAP
71 1.3.5.1 EXTEND CANOPY ELV. +18.30 100% 2 wks Wed 03/01/24 Sun 14/01/24
72 1.3.5.2 EXTEND CANOPY ELV. +26.30 100% 2 wks Mon 15/01/24 Fri 26/01/24
73 1.3.5.3 EXTEND CANOPY ELV. +30.30 100% 2 wks Sat 27/01/24 Wed 07/02/24
74 1.3.5.4 PENGGANTIAN RABUNG ATAP ELV. +20.60 100% 2 wks Thu 08/02/24 Mon 19/02/24
75 1.3.6 CAT (TOUCH UP) STRUKTUR BANGUNAN PLANT 93% 27 days Tue 02/04/24 Sun 28/04/24
76 1.3.6.1 CAT (TOUCH UP) STRUCTURE 95% 22 days Tue 02/04/24 Tue 23/04/24
77 1.3.6.1.1 TOUCHUP STRUKTUR AREA LANTAI DASAR (ELV. +4.30) 93% 22 days Tue 02/04/24 Tue 23/04/24
78 1.3.6.1.2 TOUCHUP STRUKTUR AREA LANTAI I (ELV. +10.30) 95% 10 days Sun 14/04/24 Tue 23/04/24
79 1.3.6.1.3 TOUCHUP STRUKTUR AREA LANTAI II (ELV. +14.30) 95% 10 days Sun 14/04/24 Tue 23/04/24
80 1.3.6.1.4 TOUCHUP STRUKTUR AREA LANTAI III (ELV. +16.60) 95% 10 days Sun 14/04/24 Tue 23/04/24
81 1.3.6.1.5 TOUCHUP STRUKTUR AREA LANTAI IV (ELV. +18.30) 95% 10 days Sun 14/04/24 Tue 23/04/24
82 1.3.6.1.6 TOUCHUP STRUKTUR AREA LANTAI V (ELV. +21.80) 95% 10 days Sun 14/04/24 Tue 23/04/24
83 1.3.6.1.7 TOUCHUP STRUKTUR AREA LANTAI VI (ELV. +26.30) 95% 10 days Sun 14/04/24 Tue 23/04/24
84 1.3.6.1.8 TOUCHUP STRUKTUR AREA LANTAI VII (ELV. +30.30) 95% 10 days Sun 14/04/24 Tue 23/04/24
85 1.3.6.2 PENGECATAN DINDING & ATAP SENG 75% 3 wks Thu 11/04/24 Sun 28/04/24
86 1.3.6.3 PENGECATAN DINDING BATA 100% 3 wks Thu 11/04/24 Sun 28/04/24
87
88 1.4 OSBL 83% 174 days Mon 04/12/23 Sat 25/05/24
89 1.4.1 RENOVASI CLEAN COOLING TOWER FRAKSINASI & CAT 85% 138 days Tue 09/01/24 Sat 25/05/24
DINDING LUAR BAK
90 1.4.1.1 MERAPIKAN & COATING BAK CLEAN COOLING TOWER 100% 4 wks Tue 09/01/24 Thu 01/02/24
FRAKSINASI (Uk. 8,4m x 18,55m, H=1,2m) (pH. 6-8, Temp. max
91 1.4.1.2 COATING DINDING FIBER GLASS TAHAN ASAM, RESIN ISO (Ph. 50% 3 wks Wed 08/05/24 Sat 25/05/24
5 - 9, Temp 25 - 50 C) 3 lapis (300 micron/3mm dan finishing
coating resin)
92 1.4.1.3 PENGECATAN BAK COOLING WATER & HOTWELL (DINDING 100% 3 wks Mon 08/04/24 Thu 25/04/24
LUAR)
93 1.4.2 PENGECATAN PIPERACK & PIPE BRIDGE 100% 42 days Thu 28/12/23 Wed 07/02/24
94 1.4.2.1 PIPERACK 100% 4 wks Thu 28/12/23 Sat 20/01/24
95 1.4.2.2 PIPE BRIDGE 100% 3 wks Sun 21/01/24 Wed 07/02/24
96 1.4.3 PEKERJAAN SUMPIT REFINERY (3 UNIT) 91% 72 days Sun 03/03/24 Mon 13/05/24
97 1.4.3.1 GALIAN TANAH & TIMBUNAN 100% 2 wks Sun 03/03/24 Thu 14/03/24
98 1.4.3.2 DINDING, RING BALOK & LANTAI BETON 100% 4 wks Fri 15/03/24 Sun 07/04/24
99 1.4.3.3 DINDING & LANTAI PLAT SS 100% 3 wks Mon 08/04/24 Thu 25/04/24
100 1.4.3.4 HANDRAIL 65% 1 wk Fri 26/04/24 Wed 01/05/24
101 1.4.3.5 ATAP 65% 2 wks Thu 02/05/24 Mon 13/05/24
102 1.4.4 INFRASTRUCTURE 2 75% 174 days Mon 04/12/23 Sat 25/05/24
103 1.4.4.1 COR JALAN BETON AREA SBE (L=215 m2) 50% 4 wks Thu 11/04/24 Sat 04/05/24
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Olahdata_CSA FRACTIN
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Sun 12/05/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 2
BAR CHART SCHEDULE
REFINERY PHASE 2 - FRACTIONATION
CSA PACKAGE
PT. BAKRIE FOOD & ENERGY
PT. MITRA PRATAMA MANDIRI JAYA PERKASA
ID Task WBS Task Name % Duration Start Finish
Mode Complete December January February March April May June
03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 03/03 10/03 17/03 24/03 31/03 07/04 14/04 21/04 28/04 05/05 12/05 19/05 26/05 02/06 09/06
104 1.4.4.2 TIMBUNAN TANAH 42% 2 wks Thu 11/04/24 Mon 22/04/24
105 1.4.4.3 RABAT BETON (Rabat beton lantai 800 x 800, T=80 mm) 93% 24 days Tue 02/04/24 Thu 25/04/24
106 1.4.4.3.1 Area Keliling Plant 100% 1 wk Tue 02/04/24 Sun 07/04/24
107 1.4.4.3.2 Area Clean CT, Dirty CT & Hotwell 90% 3 wks Mon 08/04/24 Thu 25/04/24
108 1.4.4.4 PERBAIKAN PIPERACK 30% 18 days Wed 08/05/24 Sat 25/05/24
109 1.4.4.4.1 COR PEDESTAL PIPERACK SAMPING BUNDWALL 30% 3 wks Wed 08/05/24 Sat 25/05/24
110 1.4.4.5 TANGKI SQUEEZING 25 T/SS & BUNDWALL 100% 4 days Mon 04/12/23 Thu 07/12/23
111 1.4.4.5.1 Pek. Bor Pile 100% 0 days Mon 04/12/23 Mon 04/12/23 04/12
112 1.4.4.5.2 Pek. Pondasi Tangki 100% 0 days Thu 07/12/23 Thu 07/12/23 07/12
113 1.4.4.5.3 Pek. Bundwall 100% 0 days Thu 07/12/23 Thu 07/12/23 07/12
114 1.4.4.5.4 Tangga Baja 100% 0 days Thu 07/12/23 Thu 07/12/23 07/12
115 1.4.4.6 TANGKI BUFFER TANK 86% 139 days Tue 19/12/23 Sun 05/05/24
116 1.4.4.6.1 Pek. Bor Pile 100% 9 days Tue 19/12/23 Wed 27/12/23
117 1.4.4.6.2 Pek. Pondasi Tangki 100% 8 days Thu 28/12/23 Thu 04/01/24
118 1.4.4.6.3 Pek. Bundwall 100% 20 days Thu 11/04/24 Tue 30/04/24
119 1.4.4.6.4 Tangga Baja 65% 25 days Thu 11/04/24 Sun 05/05/24
120 1.4.4.7 PIPERACK RF-1 100% 30 days Mon 04/12/23 Tue 02/01/24
121 1.4.4.7.1 Pek. Pondasi Bor Pile 100% 15 days Mon 04/12/23 Mon 18/12/23
122 1.4.4.7.2 Pek. Piperack RF-1 100% 15 days Tue 19/12/23 Tue 02/01/24
123 1.5 FINISH 0% 0 days Fri 31/05/24 Fri 31/05/24 31/05
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Olahdata_CSA FRACTIN
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Sun 12/05/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 3