MATERIAL
ITEM NO. ITEM DESCRIPTION QTY UNIT TOTAL AMOUNT
UNIT COST
I SAFETY REQUIREMENTS
I-A Mobilization/Demobilization 1.00 lot
Temporary Facilities 1.00 lot
Safety Requirements 1.00 lot
SUB-TOTAL ITEM I 160,000.00
II GENERAL REQUIREMENTS
II-A Designs, Plans, Certifications and Computations
Electrical Design As-built Plan 1.00 lot
Structural As-built Plan 1.00 lot
SUB-TOTAL ITEM II 120,000.00
STRUCTURAL WORKS
III-A Base Plate, Connector, Gusset and Stiffener Plates
MATERIAL
ITEM NO. ITEM DESCRIPTION QTY UNIT TOTAL AMOUNT
UNIT COST
V SAFETY REQUIREMENTS
LIGHTING BRACKET AND ELECTRICAL WORKS
V-A ELECTRICAL MATERIALS
PVC Conduit 3/4" 18.00 pcs
Elbow 6.00 pcs
Tee 18.00 pcs
Junction box with cover 4x4 18.00 pcs
Cable tie 10" long 1.00 box
Electrical tape 30m. 3.00 pcs
V-B Miscellaneous
Labor Cost for Electrical Works 1.00 lot
SUB-TOTAL ITEM V 20,230.00
VI SUMMARY for Labor and Materials
DIRECT COST Safety Requirements 160,000.00
General Requirements 120,000.00
Structural Works Cost 1,015,250.00
Painting Works Cost 84,000.00
Electrical Works 20,230.00
TOTAL DIRECT COST 1,399,480.00