Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

www.thestructuralengineer.org

TheStructuralEngineer 11
November 2013

Project
focus
Peer-reviewed papers focusing on the structural engineering challenges
faced during the design and build stages of a construction project.

12 HMYOI Cookham Wood: the first government scheme adoption of BIM Level 2
16 From lonely BIM to Design for Manufacture and Assembly (DfMA)
24 Jumping in at the deep end: how a small company applied BIM to a huge project
32 Working with existing structures in a model environment
40 Manchester Town Hall transformation programme
50 BIM for the Northern Hub ECS1 programme
60 Successful BIM in practice: the Parkside Building in Eastside, Birmingham
66 Digital design collaboration and complex fabrication
72 BIM on the Louvre Abu Dhabi
78 Challenges in implementing BIM: Singapore Sports Hub – a case study
84 BIM approach to a nuclear project: Sellafield Maintenance Facility

TSE23_11.indd 11 29/10/2013 15:04



12 TheStructuralEngineer Project focus
November 2013 UK Government adoption of BIM Level 2

Synopsis

HMYOI In 2012, URS with lead designer HLN Architects


was appointed to develop a new housing block
and education building at Her Majesty’s Young
Offender Institution (HMYOI) Cookham Wood

Cookham
in Rochester, Kent. The project comprised the
construction of a new L-shaped, three-storey
housing block to accommodate 179 young
people, including the provision of full disabled-
access cells with suitable bathrooms, and a new

Wood: the first education building with associated ancillary


works. The scope of the project also included new
security fencing around exercise yards, access
roads and new cross-site services required to

government
supply the additional facilities (Figure 1).
Working with HLN Architects, the project
was planned so that construction work could
be carried out without major impact on the
establishment and its normal operating routines,

scheme with access available from adjoining roads.


The Cookham Wood project was the first of
four Ministry of Justice (MoJ) projects in its Level
2 Building Information Modelling (BIM) ‘Early

adoption of
Adopter Programme’, part of MoJ’s strategy for
meeting the Government’s plan to roll out BIM
Level 2 across all public sector projects by 2016.
This article describes URS’ experience,
from high-level thinking about BIM on this pilot

BIM Level 2 scheme, to the realities of delivering full BIM


models in a tight (six week) programme.

W Figure 1
Federated BIM model of Cookham Wood

David Glennon BSc PGDip MBCS

Allan Brown EngTech TIStructE

All authors: URS Infrastructure & Environment UK Ltd.

TSE23_12-14.indd 12 30/10/2013 11:33


www.thestructuralengineer.org

13

S Figure 2
Gate details LOD

N Figure 3
Fencing details LOD

BIM aspirations such basic elements as the level of detail and and gates (Figures 2 and 3). The design
The HMYOI Cookham Wood scheme was information necessary. team made an early assumption that these
originally developed using a ‘traditional’ The definition of these BIM fundamentals should be modelled in detail, matching the
method of 2D drawings and commonly was agreed, to clarify what was required full 3D coordinated model in providing BIM
adopted software. At the pre-tender stage, at each stage of the project, helping to Level 2 compliance. It later became clear that
the MoJ suggested that the project could form a BIM Execution Plan – now generally the fencing on this particular project did not
become an early adopter of BIM. These accepted as a key document on any BIM require 3D modelling, and that simple lines
aspirations were communicated to the project. There were also challenges with linking back to the perimeter specifications
project team through a workshop, beginning using COBie, due to the lack of supporting would have been sufficient.
a dialogue with the MoJ exploring the technologies to enable the COBie data Detailed work on these fences and gates
implications of adopting BIM on technology, drops; a problem that still exists today. did highlight that a significant amount of
people and processes. time spent creating custom content for
The BIM goals for the project were to Level of detail (LOD) understanding the project could potentially benefit similar
develop a fully coordinated, multi-discipline One of the initial ambitions was to directly projects in the future. The MoJ requested
federated 3D model, and to produce COBie link specification documents to the from the outset, that a library of standard
(Construction Operations and Building resulting BIM model. An important lesson components, that could be distributed
Information Exchange) data drops 2A learned by the project team – with broad to design teams and contractor supply
and 2B, to provide an outline solution for applicability for the industry – was the need chains to aid the BIM process, while also
the project. These data drops provide the for clarity regarding required deliverables encouraging a better understanding of the
rationale to select the main contractor. and especially the level of detail needed critical nature of LOD, should be developed.
At this stage, checks are taken to ensure in the model. For example, in the absence With 3D technology adoption increasing
that the design and specifications meet of any UK-recognised level of detail (LOD) at a rapid pace (a trend that seems unlikely
that of the brief, with a focus on cost and documentation, URS had to base LOD to change) LOD is an aspect that must
performance. A further deliverable was 2D principles on Document E202-20083 by the be fully clarified with clients early in the
drawings created directly from the models. American Institute of Architects (AIA). A process, along with an understanding of
These objectives provided an opportunity number of questions were raised internally, how data will be matured as the project
for project members to develop their own such as: develops. Additional considerations
BIM expertise as well as lessons and that should be considered during LOD
resources for the industry to re-use. • At the point of handover, will end users discussions are:
The initial workshops with the MoJ be able to interrogate the BIM model by
were critical in clearly defining the client’s utilising software they are familiar with to • Understanding the ‘Consultant’ model
requirements and the process needed to locate specifications? versus the ‘Contractor’ model
achieve them. Everyone involved in the • How does URS map the specifications to the • Ownership of models
workshops had the opportunity to understand model, so that during distribution back to the • Fidelity of data exchange between
the holistic BIM process and helped refine MoJ, all linking of coordinated data is retained? software platforms
the resources now available to the industry, • What impact will the linking of external
such as the Construction Industry Council specifications have on the performance of Throughout the development of the
BIM Protocol1 which is a supplementary legal the information model? Will the model size Employer’s Information Requirements and
agreement that can be added to construction increase? Will the model navigation slow the BIM Execution Plan, knowledge about
contracts as that of an amendment, and down? current limitations of how technologies
the shaping of PAS 1192-2:20132 which is • Is the data being used to populate a interact should be highlighted, and
recognised as the supporting document to Facilities Management system? The FM workflows explored to check the quality of
the industry of how to strategically achieve aspects of the design are of particular data exchanges. As part of the BIM process,
BIM Level 2. Without these benchmark importance to the MoJ. the aim is to mature the data over the life
documents, however, there was initial cycle of the project, but the realities are
uncertainty about what was required for One example of the impact of this lack of more complex in terms of technology and
the Cookham Wood development, including clarity over LOD, related to perimeter fencing from an ownership and legal standpoint.

TSE23_12-14.indd 13 29/10/2013 15:07



14 TheStructuralEngineer Project focus
November 2013 UK Government adoption of BIM Level 2

Similarly, a client’s understanding of Conclusion means there are clear benefits to becoming
the development of a consultant’s model, Over a six week period, the Cookham fully engaged as early as possible, because
such as a structural engineer’s model, and Wood project team moved from traditional the more structured and well defined the
how it subsequently translates into a sub- 2D design methods to full 3D coordinated BIM process is at the outset, the more
contractor’s fabrication model must be models and inclusion of COBie data with effective BIM will be throughout the project.
addressed early in the process, with suitable a basic understanding of the BIM process. This includes setting out clear definitions of
management of expectations. This was a significant challenge, but one project aspirations and client requirements
which the team successfully met. The within the BIM Execution Plan, and ensuring
Importance of training and knowledge measure of this was being able to mobilise these are effectively communicated to the
URS identified two separate challenges the project team from using 2D design project team.
on this project, which has aided in its to 3D design within the six weeks. From It is critical that BIM is applied with an
development of expertise in BIM authoring this experience, URS have managed to understanding of how engineers can adopt
software as well as in BIM processes. build on the success of the adoption of the required processes in a cost-effective
The easier of the two streams to manage BIM authoring technologies across multi- manner. A lack of clarity at the start of
and develop was the technology challenge. disciplines and now have 150+ UK based a project can have a direct impact upon
URS was able to mobilise training plans for formally trained staff. effective delivery at the consultant level.
all offices involved including ‘just-in-time’ URS gained significant knowledge Since the start of the Cookham Wood
training, in line with project start dates, so that and experience from the project, adding project in 2012, there has been significant
no momentum was lost between the training to its understanding of the benefits and progress in making BIM a more practical
and the project. URS’ offices in Plymouth and limitations of employing BIM. The majority of proposition, with the advent of industry-
London were able to collaborate to create benefits were derived from the generation recognised documentation from the CIC
the federated models and generate the of construction documentation and in and the current version of PAS 1192-2: 2013.
construction documentation directly from the the intelligence the information models Client understanding is also improving,
models, as required by the MoJ. contained. Our teams were able to visualise which is a significant step forward for BIM
The development and understanding of their designs quicker and identify issues and its successful adoption. Clients and
the BIM process provided a more complex earlier with regards to potential site clashes. contractors are starting to understand how
challenge. As a pilot project, Cookham Limitations were found regarding the longer projects should be structured to suit the BIM
Wood gave all those involved a chance to process that was taken to embed data in the process, which in itself will bring efficiencies.
collaborate and collectively develop their model objects to suit the COBie data drops. Within little more than a year, BIM has
knowledge and understanding of how to It has been noted that since the inception of developed to the point where a more
apply BIM principles on a working project. Cookham Wood, software vendors are now common language is starting to be spoken,
Internally, HLN and its design teams gained catering their technologies to better handle with many of the fundamentals established at
a clear understanding that BIM is not simply the demands of these data drops. Cookham Wood, fast becoming the standard
about 3D models or specific technologies, but The opportunity to develop a wider view for our industry. URS played a pivotal
rather a change in process that produces a of a project, means URS will be better able role, steering a pilot project from modest
more developed deliverable for the client. to challenge and support its clients in the beginnings to provide a BIM foundation on
COBie data drops also provided one of the process. The collaborative nature of BIM which the industry is now building.
most notable challenges on the project. URS
saw these data drops as BIM at the lowest
common dominator with regards to data. A
References
manual process was needed to develop the
data structure for the COBie drop, which had
an adverse impact on both time and cost, E1 Construction Industry Council (2013) Building
and a significant amount of training for all Information Model (BIM) Protocol [Online] Available at:
involved. Since the development of Cookham www.bimtaskgroup.org/wp-content/uploads/2013/02/
Wood, software vendors have worked to The-BIM-Protocol.pdf (Accessed: October 2013)
enable COBie outputs directly from the BIM
models in a more automated and effective E2 British Standards Institution (2013) PAS 1192-2:2013:
manner (although there is still further work to Specification for information management for the
be done in this area). capital/delivery phase of construction projects using
As a pilot, the project has provided building information modelling [Online] Available at:
worthwhile lessons for the industry which http://shop.bsigroup.com/forms/PASs/PAS-1192-2/
can be found on the UK Government Task (Accessed: October 2013)
Group website4. It has added impetus for
software vendors to improve their software E3 American Institute of Architects (2008) E202-2008:
to suit BIM Level 2 deliverables and helped BIM Protocol Document [Online] Available at: www.
in the development of many of the industry aia.org/contractdocs/training/bim/aias078742
standards available today. Project team (Accessed: October 2013)
members have developed invaluable
expertise and URS has since evolved E4 HM Government Department for Business, Innovation
many of its internal processes to facilitate and Skills (2013) BIM Task Group [Online] Available at:
improved collaborative BIM working www.bimtaskgroup.org/lessons-learned/ (Accessed:
practices, compared to more traditional October 2013)
methods of design.

TSE23_12-14.indd 14 29/10/2013 15:07

You might also like