Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

24 TheStructuralEngineer Project focus


November 2013 Stavros Niarchos Foundation Cultural Centre

W Figure 1
View through Stavros Niarchos Park
towards Stavros Niarchos Cultural Centre

On their own, each of these buildings


would have been a major project. However,
combined, and with associated car parking,
amenities buildings, and major civil works,
the €566M project presents an enormous
coordination challenge. In keeping with the
approach of the practices involved, the core
team of Renzo Piano Building Workshop
(architects), Expedition Engineering
(structural engineers) and Arup (MEP
engineers) decided at an early stage that
the engineering should be integral to the
building architecture, carefully intertwined
with an attention to detail that would

RPBW
deliver a project of monumental quality.
This required a very precise harmonisation

Jumping in at
between disciplines.
In 2008, when the SNFCC project was
in its infancy, BIM, as we now know it, was
only just starting to take root in the UK
and European construction industry. It was
certainly not a process that was discussed

the deep end: at project start up meetings and by clients in


the way that it is now; particularly following
its mandate for centrally procured UK
Government projects. However, it was clear
that to deliver a project of this quality, a truly

how a small collaborative approach was required by


the design team, and with the geographical
separation of the team, this process would
need to be managed in a way that would
not just compensate for the separation,

company but would go beyond the current industry


standard.
The following is an analysis of the lessons
learned from the process that could be
replicated and expanded upon in the future.

applied BIM to a The team. The mind-set. The decision.


We did not take a conscious decision to use
BIM. We took a decision to collaborate as
closely as possible; and for this team, on this

huge project
project, that decision to collaborate led to
the adoption of integrated building models.
More importantly though, it involved using
those models with the absence of many of
the barriers that can sometimes arise during
the design process.
The project. The challenge. The decision to undertake a highly
Alessandro Maccioni MIStructE The desire of the Stavros Niarchos collaborative approach to the project,
Senior Engineer Expedition Engineering Foundation was to create a new educational was made by the core team following the
and cultural destination for the city of completion of the project feasibility study
Jared Keen MIStructE Athens, Greece. From the beginning, the as the project moved into early scheme
Associate Director Expedition Engineering design team shared their desire to make design. At the time, the team as a whole had
these buildings something special. The limited experience of placing a structured
Andrew Weir MIStructE, MICE Stavros Niarchos Foundation Cultural digital format as the heart of collaboration,
Director Expedition Engineering Centre (SNFCC) is set within the expansive especially on a project the size of SNFCC.
new 170 000m2 Stavros Niarchos Public However, of greater importance was that the
Peter Winslow MIStructE, PhD Park (Figure 1) and consists of new buildings organisations and individuals involved had a
Senior Engineer Expedition Engineering for the Greek National Opera and the shared approach to the delivery of projects,
National Library of Greece (Figure 2). and a shared ethos of quality design and the

TSE23_24-30.indd 24 29/10/2013 15:16


25

W Figure 2
Greek National Opera
House (left) and Greek
National Library (right)

RPBW
utilisation of the best tools available for the like Autodesk and Bentley. indicated that coordination benefits during
job (Figure 3). Similarly, the 2012 Olympic Velodrome the design stages could be beneficial in
In 2008, Expedition already had wide- used extensive 3D modelling to develop achieving a more thoroughly and rigorously
ranging experience of working in 3D and a highly integrated design. The step from integrated design. Expedition at the time
digital information management using doing this in an ad hoc manner to something had some limited experience using Revit but
software such as McNeel’s Rhino; often that was more formally agreed across the not an extensive portfolio to draw upon.
utilising scripting to generate structurally project team, was therefore not seen as a Looking back, the greatest hurdles we
informed geometry. We also had experience big step to take. While the industry is now overcame were our own concerns about
of communicating this information to other calling for a digital BIM approach to projects, what might go wrong. Engineers are natural
members of the design team or project it's worth remembering that at its core is appraisers who, on picking up a task, will
collaborators in the most applicable something all good engineers already look easily spot the ways in which things might
format. The most appropriate manner for to achieve: a collaborative design process, not work. There is always the voice at the
communicating this information tends to combined with effective data handling and back of our heads suggesting we wait for
differ from project to project, but developing sharing – another skill which engineers have a smaller, simpler project, or delay until
workflows that allow effective data historically excelled at. The process itself software has advanced further. But if
transfer to enable a collaborative design may require some additional planning but its engineers are adroit at spotting problems,
process was already ingrained within the eventual success will ultimately rest on the we are even more so at solving them. Once
way Expedition worked. The Stockton approach, capabilities, and mind-set of the we had made the decision to implement
Infinity Bridge, which won the Institution individuals implementing it. BIM we could then use all of the tools which
of Structural Engineers’ Supreme Award The client for SNFCC did not expressly make us good designers – careful planning,
in 2009, used Rhino extensively and the stipulate a collaborative digital workflow, an ability to perceive broad goals with
primary method for conveying construction but it was seen by the team as the most the same eye as we see fine detail, and a
geometry to the fabrication contractor appropriate method to achieve the quality balance of creativity and thoroughness – to
was through handover of a digital model. of project which the client had specified, successfully use BIM to take collaboration
This, in fact, was a BIM process, although and which the team desired to achieve. The to the next level.
the information issued was quite different proposal to use Autodesk Revit came from
to that produced by general purpose BIM Renzo Piano Building Workshop (RPBW) Implementation
software packages developed by companies as previous experience within its office had Once the decision was made to use
a collaborative design approach with
S Figure 3
Physical locations of key consultants showing geographic diversity of team
Autodesk Revit as the central tool, a project
deliverables and documentation planning
meeting was held between the key members
of the team to scope out and agree a way
forward. Out of this meeting the following
key decisions were made:

• The principle that work in progress


models would be exchanged on a weekly
basis. These models were understood not
to be complete and merely intended as
information to inform of interim changes.
Any issues identified could then be
discussed via appropriate communication
• At key milestones models would be fully
coordinated and frozen record copies archived
– generally coincident with project deliverables
• Arup MEP, while working primarily in CAD
Duct, would generate Revit compatible files
to facilitate full model sharing
• It was identified that 3D files, while not

TSE23_24-30.indd 25 29/10/2013 15:16



26 TheStructuralEngineer Project focus
November 2013 Stavros Niarchos Foundation Cultural Centre

and absoluteness can make it difficult


for them to allow a scheme model to be
sufficiently vague.
The other major advantage of having
engineers involved with Revit is that it
gave the engineering team an intimate
understanding of Revit’s strengths and
weaknesses. Most of us understand the
sorts of tricks and tools available in CAD
to allow a drawing to be completed leanly
and correctly with a minimum of fuss.
In Revit the old set of tricks and tools

N Figure 4
Structural model of opera house
(left), library (right) and car park (beyond)
are gone, though largely replaced by an
entirely new and different set. Having the
engineers understand the Revit modelling
process enabled the whole production team
contractual deliverables, may eventually be Creating our model to efficiently determine the best way to
passed to the contactor for information in At the time these decisions were being approach the document production process.
the interests of best practice made, the project was progressing
• Models would be overlaid and compared through the scheme design stage, with all How we shared
in suitable software to facilitate model the associated changes and exploration The limitations of the software and internet
coordination inherent in early design phases. Partly connections of the time, meant that a truly
• A BIM FTP (File Transfer Protocol) set was for this reason, we decided that the first live exchange of models was never going
to be set up to act as the repository of the project models would be created by the to be possible. The weekly exchange of the
project models, accessible by all of the team project engineers working on each section initial models did however prove to be a
of the project, rather than a CAD team. success, and communication was certainly
The importance of the weekly model Investment was made in these individuals stimulated by the weekly exchange of work
exchange cannot be overstated. Clearly this in the form of appropriate training, with the in progress models. It is worth highlighting
led to very rapid and direct coordination – view that at this stage their more intimate that with the geographical separation
much more so than is typically achieved by knowledge of the project (and already between the team, it would have been easy
the standard coordination process of issuing developing relationships with the design for communication to be less frequent than
a semi-formal coordination set on a longer team) would permit efficiently developed on a wholly UK based project. The project
cycle. More subtly, but far more importantly, and appropriately detailed (not necessarily models provided a platform to regularly
it both required and created a very high level highly detailed) models to be created for the generate debate and discussion of the
of trust within the design team. As the team scheme design stage of the project (Figure 4). design, which could then be carried out
was sharing its working models with each The use of engineers rather than CAD via a combination of hand drawn sketches,
other as fast as we could create them, there technicians to create the Revit model at early electronic mark-ups of the model/drawings,
was nowhere to hide. None of the parties stages was essential to the success of the interactive online meetings using software
could conceal omissions or errors, but process. During scheme design, the model such as GoToMeeting, and teleconference
equally, all of the parties understood that is like a virtual sketch, but whereas a wobbly calls. The sharing of computer screen
parts of the model would be well developed line on a sketch can convey the appropriate visuals helped form the basis of numerous
while other areas lagged behind. In our case level of uncertainty, a 3D model tempts the conversations and at the scheme design
it created a series of very open and honest modeller to examine increasingly finer levels stage, when project engineers were still the
working relationships. However, for some of precision. An engineer’s understanding of model owners, any required model updates
organisations, the decision to so openly the transient nature of scheme design allows could be completed in real time, with no
place their work on public display, with the them to resist this temptation to make early need to create mark-ups that would then
risks that such action might entail, would be models perfect, whereas in our experience a need to be transcribed into the model by
considered unpalatable. This is perhaps one CAD technician’s natural drive for accuracy technicians.
of the greatest challenges in realising the
full benefits of collaboration via BIM, rather
than simply rolling past practices over into E Figure 5
Weekly model
exchange and
different software. coordination cycle
Although in this case the project team’s
working relationship was in its infancy and
the project requirements novel, this planning
meeting would still be essential at the start
of any project, even for teams with extensive
experience of working together. It is always
likely that projects, project programmes, or
project deliverables will require the agreed
workflow to be modified in some way and
this meeting also provides a chance to
discuss opportunities to implement new
ideas on a project.

TSE23_24-30.indd 26 29/10/2013 15:16


www.thestructuralengineer.org

27

S Figure 8
Opera House auditorium S Figure 9
Stage pit theatre equipment within structural model

The file sharing process began as a be offered and that risk would effectively be Using the models
weekly manual transfer, but was quickly shared between the practices. This was an The software allowed the designers to
streamlined into an automated process, important agreement as it greatly simplified overlay various models to enable ‘clashes’ or
whereby all parties would automatically the interface between the Opera House uncoordinated items to be clearly identified.
upload their files onto an FTP server on a and Library substructures, which were to Tools within the software were utilised
Saturday, and automatically download the be developed and designed by Omete, to create coordination views that could
others files on Sunday. Monday morning and the superstructures that were to be be used to aid this coordination process
rapidly became a model perusal opportunity developed by Expedition. By linking models, (Figure 7). Contrasting coloured visuals were
(Figure 5). the structural interfaces could be more used to easily identify inconsistencies. This
The model sharing was not limited to easily coordinated and it was possible to process was seen to go a long way towards
Expedition and RPBW. The collaborating generate documentation of these interfaces avoiding design problems and conflicts that
local engineering and architectural based on combined data from independent could not have been identified so easily in
practices were also brought into the sources (Figure 6). a 2D environment. A key benefit was the
process as they were appointed to the We were well aware that not all members ability to embed additional information within
project. This, again, relied upon professional of the team and supply chain would be the model, which, while not required for the
trust and understanding of the proposed able to read the native Revit files and so generation of drawing deliverables, could
process. Omete, Expedition’s collaborating we generated interpretable data for these be used to communicate to the rest of the
engineer in Athens, was initially a little colleagues. For instance it was likely, as design team.
sceptical of the process, having no prior specialist sub-consultants joined the team An area of the project which was a
experience of using Revit, although again, as the project developed, that they would particular focus for the design team, was the
it had extensive experience of working in need access to 2D CAD versions of the Opera House’s main auditorium, the main
a 3D CAD environment and the transfer building information. The exchange of stage and its subsurface stage pit (Figures
of this data between different software data between parties internally (including 8 and 9). The creation of an international
packages for design and documentation. collaborating organisations) and externally,
Its fears were, however, successfully was carefully planned from the beginning of
addressed, through developing the the project. The interoperability of project
professional relationship, building trust and data remains one of the key challenges to
making clear that as a team, support would BIM processes to this day.

W Figure 6
Division of
structural models
between Expedition
and Omete

E Figure 7
Project
coordination view
showing structural
model coordination
(red) with lifts and
bathrooms

TSE23_24-30.indd 27 29/10/2013 15:16



28 TheStructuralEngineer Project focus
November 2013 Stavros Niarchos Foundation Cultural Centre

W Figure 10
Base isolator unit showing clearance zone

S Figure 11
Architectural model wrapped around structural model (red)

quality performance space as required for Going further for bigger gains – While the final workflow provided
the Greek National Opera comes from the moving to BIM ‘Level 2’ obvious benefits in terms of the level
careful blend of constraints essential for When the project moved into the of coordination achieved during the final
maintaining the quality of the performance construction information stage, a decision coordination of the project, it can be
space, combined with a creative design was made by the team that greater design questioned whether an earlier move to
process to produce a unique experience coordination and accuracy could be such an approach would have provided
for the performers and audience. achieved by avoiding the replication of any further benefits. Earlier in the design
Space planning requirements, extensive the structural model by RPBW. This was process the evolution of the project is still
mechanical theatre equipment, lighting and accomplished by moving to a workflow quite fluid and creating a structural model
scenery, acoustic performance, necessary whereby the current structural model was with the required level of detail and fixity
sight lines and environmental performance, inserted directly into the architectural (upon which to base an architectural stage
all had to fit within the architectural concept model (Figure 11). The base structural D model for example) would require a far
and structural engineering, to make this model was then effectively supplemented higher level of input from the structural
possible. It was arguably in this area (as it would be in real life) with the various team, with quite possibly very little benefit
that some of the greatest benefits of the finishes and secondary elements to create to the project as a whole. It could even
collaboration were achieved. 3D spatial the envisaged building. As the drawings be argued that the increased fixity of the
information could be coordinated between generated by the software are always live design at an earlier stage could prevent
Expedition, RPBW and Arup MEP, while views of the 3D model in its current state, designs developing to their full potential
these models could then form the basis this created a position whereby a high in response to the design brief. The stage
of acoustic and environmental models for level of coordination between structure at which this fixity is sought is therefore
analysis, as well as sight line analysis by and architecture had to be achieved, since likely to vary from project to project and
the theatre consultant, with their own 3D uncoordinated elements would be quite will no doubt be a strongly debated topic
models being round-tripped back into the clearly visible on the generated architectural (Figure 12).
primary architectural model to confirm drawings. Although coordination overlays While it can be argued that we
coordination. had been used previously there was still a successfully achieved BIM Level 2 from
Although the initial focus had been on noticeable second wave of coordination stage E, from our observations it would
generating the model for the creation of 2D at this point. The move to this workflow be exceptionally challenging (and quite
drawings and coordination, it soon became required a high level of trust between the possibly directly detrimental to design) to
apparent that additional benefits could be consultants, as each other’s deliverables attempt it at a significantly earlier stage for
derived from assembling a data rich model, became highly dependent on the model and a project such as this, given the way our
including: the quality of information supplied by the industry is arranged. The building design
other consultants. This big step in terms of industry has evolved with distinct divisions
• live material quantity counting trust and collaboration could be quite easily between disciplines, but to have both a
• development of construction sequences seen as one of the major steps required flexible design and BIM Level 2, these
• fast production of images/renders to develop from BIM Level 1 to 2, where divisions can no longer exist. We hope and
(Figure 10) information production moves from being expect that project teams will continue to
• live manipulation of scheduled data managed in separate isolated files to sole push these boundaries, but we anticipate
• ease of document control via live linked instances combined within a single model that for significant progress to occur,
drawing titles, revisions, numbering and environment, thereby avoiding duplication or organisational and contractual innovation
batch publication tools misrepresentation. will be required.

TSE23_24-30.indd 28 29/10/2013 15:17


www.thestructuralengineer.org

29

Could BIM hamper the design


exploration?
S Figure 12
Indicative representation of gradual tightening of coordination between consultants, leading to adoption of BIM Level 2

The project was not without its difficulties.


As many users report, challenges were
faced in relation to computing power, file
sizes and allowing access for multiple
users at the same time. In most instances a
resolution was achieved with some research
and clever thinking, but a number of these
are issues that could be overcome by
software providers.
Without doubt, a collaborative use of BIM
will improve the coordination of a building
during the design stage. There is however
a risk that it may stifle creativity earlier in
a project if not appropriately implemented.
Many architects are comfortable with
using 3D models at concept stage to throw
together visualisations of options. Engineers
however, tend to have a more exacting view
of what a model should be – likely influenced
by years of tuning analysis models. On the
SNFCC, it required a conscious effort and
deliberate plan with regard to how we would
use BIM at early stages. We handled it by saving opportunity, and to have incorporated
trying to deliberately adopt a mentality of
using Revit as a virtual sketch – but even
"Once we had this into the design team deliverable, such
that it can form part of the tender package.
so it required constant wariness to avoid
slipping into too early coordination at the
made the decision Clearly the additional deliverable will mean
extra costs for the consultants. In our
expense of allowing the design to evolve. In to implement view, even those clients with considerable
some cases, the current software available
is likely to push BIM into being simply too BIM we could construction industry experience do not
fully appreciate the subtleties of BIM and its
precise a tool for application at the very
early stages. then use all of role in the coordination process, to be able
to adequately leverage it to their advantage.

Where to next? the tools which We believe that in the short term, design
consultants are better placed than any other
While successful use was made of
collaboration via a BIM approach, there are
make us good to advise their clients of the opportunities,
and in the longer term we would be looking
still multiple aspects that could be explored
further.
designers" for industry frameworks to catch up to the
evolving technology.
As shown on this project, it is possible Another area that could be exploited
to intertwine models between consultants. further is embedding more data directly into
In our experience it is also possible to the 3D model. Specification information,
link between structural analysis models connection information and loading data
and structural BIM models, although the could all be usefully and directly attached
achievability of this on complex projects to elements in the model, which would be of
may be argued, with the currently available great use to a competent contractor on site.
tools regularly proving a challenge. Creating Again, contractual and fee arrangements
a workflow that moves from analysis currently offer little incentive for designers
model, to structural BIM model, to other view is that a competent contractor should to do so, and the burden would likely fall to
consultants' BIM models, creates an be able to realise cost savings if provided design consultants to express the potential
additional order of interoperability. Although with a robust, coordinated set of building benefits to clients for this to happen in
there are challenges involved, we believe models. This should be achievable through practice.
they are largely within the realm of the increased certainty of coordination, and the Finally, in the infrastructure sector,
project technical team, and thus entirely ability to more fully understand the project it’s largely the bigger institutional clients
solvable given enough care and thought. at tender stage from the 3D data provided. (that are focused on improving their
On the SNFCC, the Revit models It should also be achievable through the asset management capabilities) that are
were handed over to the contractor for ability to pass on the model to steelwork generating the momentum behind BIM
information only, as they are explicitly fabricators, reinforcing detailers, equipment implementation. Generally, in buildings,
not contractual deliverables. A significant suppliers, pipework installers and any other asset management is a simpler affair, yet
challenge for the building industry (and subcontractors, many of whom are able to in time we anticipate that advances being
one in which clients must be intimately make heavy use of 3D modelling due to their made with regard to BIM in the world of
involved) is how to maximise the value to specialisation. The challenge is for clients to infrastructure will percolate through to
the client of using BIM on a project. Our be able to recognise and quantify this cost buildings.

TSE23_24-30.indd 29 29/10/2013 15:18



30 TheStructuralEngineer Project focus
November 2013 Stavros Niarchos Foundation Cultural Centre

Conclusions
• The right attitude is essential. The design
The SNFCC has now been on site since
autumn 2012, and what was once only a N Figure 13
Construction of undercroft

team must trust each other and have a virtual building is now emerging from the
strong relationship. If that trust exists,
then collaboration through BIM can further
silty ground in the Kallithea district of Athens
(Figure 13). Time will be the best judge of
"Engineers are
enhance relationships. If it doesn’t exist then
true BIM collaboration is unlikely
whether the SNFCC achieves its aim of
becoming a new monument for the people
natural appraisers
• An SME can successfully implement BIM on
projects; even large, complex ones. It takes care
of Athens, but we are quite sure that the BIM
process adopted by the design team has
who, on picking up
and deliberate planning, as well as a design
team that is willing to accommodate each
increased its chances, by creating a truly
integrated response to the architectural
a task, will easily
other’s needs. Training and staff skills profiling
when putting together the team are essential
concept. BIM can make designs better,
but only if people are committed to the
spot the ways in
• Planning is key. Integrated BIM models require
upfront investment of time for later benefits.
philosophy at its heart; collaboration. which things might
The process needs to be thought through and Acknowledgements not work"
agreed with the team at an early stage Client: Stavros Niarchos Foundation Cultural
• The more team members involved, the Centre; Design Architect: Renzo Piano
greater the potential benefits of integrated Building Workshop; Executive Architect:
BIM. The biggest rewards could be achieved Betaplan; Structural & Civil Engineering:
by actively carrying the building information Expedition Engineering and Omete; MEP
models through to construction and facilities Engineer: Arup and LDK; Landscape
management, which requires the client and Design: Deborah Nevins and Associates
contractor to also buy in to the process and Helli Pangalou; Acoustic Design: Arup
• Undoubtedly there are time, cost and Acoustics; Project Manager: Faithful+Gould;
quality benefits that can be achieved for Façade Consultant: Front; Theatre Design
clients, designers and contractors through Consultant: Theatre Projects Consultants;
use of BIM, if it is carefully planned. Library Consultant: Alexi Marmot Associates;
However, insufficient planning can result in Traffic Consultant: Denco
3D modelling causing more problems than it
solves. Additionally the construction industry If you have any comments or questions on
has yet to find an appropriate framework to this article please visit our twitter account
efficiently realise the full benefits of BIM @EXP_Eng

TSE23_24-30.indd 30 29/10/2013 15:18

You might also like